 "meta": {
  "title": "Siaya County development project register",
  "schema_version": 1,
  "compiled": "2026-11-21",
  "scope": "Projects named in the CIDP 2023-2027 capital and flagship tables, the county budget implementation reports for FY 2025/26 (Q1 to Q4), the Controller of Budget annual reports (Siaya tables for FY 2018/19 and FY 2020/21 to 2024/25), the Auditor-General reports in data/siaya-audits.json, and the CADP 2025/26 public participation report. Not exhaustive: these tables list only the highest-spending and stalled projects.",
  "status_states": [
   "planned",
   "tendered",
   "contracted",
   "active",
   "delayed",
   "suspended",
   "completed-reported",
   "completed-independently-verified",
   "cancelled",
   "unknown"
  ],
  "status_rules": [
   "planned: in a plan (CIDP) with no later evidence.",
   "tendered / contracted: tender or contract evidence only, no works evidence (none in this release).",
   "active: works or payments under way and not past the expected completion date in the evidence.",
   "delayed: incomplete after the expected completion date, from the audit or from the county's own dates.",
   "suspended: listed as stalled by the county, or works found stopped or abandoned by the auditor.",
   "completed-reported: the county (directly, in a CoB table, or as quoted by the auditor) reports completion or 100%.",
   "completed-independently-verified: the Auditor-General (or another independent party) states on inspection that the works were complete.",
   "cancelled: contract terminated or budget removed.",
   "unknown: only spending, or conflicting or incomplete evidence.",
   "Where sources disagree, the status follows the latest evidence; independent evidence outranks a county report of the same or earlier date. The disagreement is kept in conflicts."
  ],
  "evidence_types": {
   "audit_physical_verification": "independent: Auditor-General site inspection or physical verification",
   "audit_documentary_review": "independent: Auditor-General review of records or interviews",
   "county_budget_report": "county: quarterly budget implementation report",
   "cob_report_county_data": "county data in a Controller of Budget report (\"Source: Siaya County Treasury\")",
   "county_development_plan": "county plan (CIDP)",
   "county_participation_report": "county public participation report"
  },
  "independent_evidence_types": [
   "audit_physical_verification",
   "audit_documentary_review"
  ],
  "amount_rule": "Amounts are as printed, in the unit given (KSh, or KSh million for the CIDP). fy is the financial year of the document that prints the figure. No figure is summed, converted or inflated. A printed paid amount above a contract sum is kept as printed and noted.",
  "page_rule": "page is the 1-based PDF page, not the printed page number.",
  "names_rule": "No individuals are named. No contractor is named either (owner decision, 21 Nov 2026): where an Auditor-General report prints a company name, the record keeps only contractor_reference (document and page) with the note \"named in the audit report; withheld pending review\". Most reports describe the contractor only as \"a firm\". Road and facility names are kept as printed.",
  "location_rule": "Each printed location is resolved against data/siaya-geography.json (ward or constituency names and aliases) or listed as unresolved with a reason. Towns, facilities and \"Executive\" are not resolved to a ward.",
  "currency": "KSh, nominal",
  "contractor_names": "Withheld from the public site pending editorial review (owner decision, 21 Nov 2026)."
 },
 "documents": [
  {
   "doc_id": "GOV-01-PDF",
   "title": "County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file)",
   "publisher": "County Government of Siaya",
   "doc_type": "county_development_plan",
   "independent": false,
   "published": "2024-01 (PDF metadata 24 Jan 2024; no date printed)",
   "period": "2023-2027",
   "url": "https://siaya.go.ke/wp-content/uploads/2026/10/County-Government-of-Siaya-CIDP-2023-2027-Final-Print-File-2024.pdf",
   "sha256": "650a5bdf71c5d4d43247a837752e0c3f2978d4ef53853033566278e7e6be9d0d",
   "in_source_library": true,
   "in_source_manifest": false,
   "page_basis": "PDF page (1-based)",
   "text_method": "PDF text layer"
  },
  {
   "doc_id": "GOV-02-FY2025-26-Q1",
   "title": "County Government of Siaya, Budget Implementation Report for 1st Quarter Ending September 30th 2025",
   "publisher": "County Government of Siaya (County Treasury)",
   "doc_type": "county_budget_report",
   "independent": false,
   "published": "not stated",
   "period": "FY 2025/26, Q1 (July to September 2025)",
   "url": "https://siaya.go.ke/?cgdp_download=31602",
   "sha256": "4260b70e6878ada577ce2846c675dc1d4ec4eb8f02f80ffc0bea326dc407d6de",
   "in_source_library": true,
   "in_source_manifest": false,
   "page_basis": "PDF page (1-based)",
   "text_method": "PDF text layer"
  },
  {
   "doc_id": "GOV-02-FY2025-26-Q2",
   "title": "County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025",
   "publisher": "County Government of Siaya (County Treasury)",
   "doc_type": "county_budget_report",
   "independent": false,
   "published": "not stated",
   "period": "FY 2025/26, Q2 (October to December 2025)",
   "url": "https://siaya.go.ke/?cgdp_download=31599",
   "sha256": "580c4bbbbd44ed7fcfb503d12967b1d0e0123606c5df902214536a6e697a737a",
   "in_source_library": true,
   "in_source_manifest": false,
   "page_basis": "PDF page (1-based)",
   "text_method": "PDF text layer"
  },
  {
   "doc_id": "GOV-02-FY2025-26-Q3",
   "title": "County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026",
   "publisher": "County Government of Siaya (County Treasury)",
   "doc_type": "county_budget_report",
   "independent": false,
   "published": "not stated",
   "period": "FY 2025/26, Q3 (January to March 2026)",
   "url": "https://siaya.go.ke/?cgdp_download=31595",
   "sha256": "6673545008e72d675252dfcaf40908f0853c396fc0f2733683ca1c9873874796",
   "in_source_library": true,
   "in_source_manifest": false,
   "page_basis": "PDF page (1-based)",
   "text_method": "PDF text layer"
  },
  {
   "doc_id": "GOV-02-FY2025-26-Q4",
   "title": "County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026",
   "publisher": "County Government of Siaya (County Treasury)",
   "doc_type": "county_budget_report",
   "independent": false,
   "published": "not stated",
   "period": "FY 2025/26, Q4 and year to date (to June 2026)",
   "url": "https://siaya.go.ke/?cgdp_download=31593",
   "sha256": "4344ce3966b981e0196b1c81b7a209a294239ccaa473d753b7fc5c85170faec3",
   "in_source_library": true,
   "in_source_manifest": false,
   "page_basis": "PDF page (1-based)",
   "text_method": "PDF text layer"
  },
  {
   "doc_id": "GOV-04-CADP-PP",
   "title": "Report on Public Participation in the Siaya County Annual Development Plan (CADP) 2025-2026",
   "publisher": "County Government of Siaya (Department of Finance & Economic Planning, Directorate of Public Participation & Petitions)",
   "doc_type": "county_participation_report",
   "independent": false,
   "published": "2024-09 (PDF metadata 22 Sep 2024)",
   "period": "CADP FY 2025/26",
   "url": "https://siaya.go.ke/?cgdp_download=31438",
   "document_page": "https://siaya.go.ke/documents/report-on-public-participation-in-the-siaya-county-annual-development-plan-cadp-2025-2026/",
   "sha256": "fa62a517b5ecf037a8c0022753bd6946dd0279a62a7fee8d240ff49da86da5f7",
   "bytes": 2497369,
   "retrieved": "2026-11-21",
   "in_source_library": false,
   "in_source_manifest": false,
   "page_basis": "PDF page (1-based)",
   "text_method": "PDF text layer",
   "note": "Downloaded 21 Nov 2026 from the county documents page (the GOV-04 notice page link did not work). This is the participation report behind programme source GOV-04; it is not yet a record in data/source-library.json. The ADP 2025/26 itself was not obtained."
  },
  {
   "doc_id": "cob-report-2018-19",
   "title": "Annual County Governments Budget Implementation Review Report FY 2018/19",
   "publisher": "Office of the Controller of Budget",
   "doc_type": "cob_report_county_data",
   "independent": false,
   "published": "2019",
   "period": "FY 2018/19",
   "url": "https://libraryir.parliament.go.ke/items/c0a86b90-6178-463e-ab50-56dd3c76ec98",
   "sha256": "7d8c1a0b35e2ca42b53dfa0b6979b4f37c57db61c60e142e727e7b3f29c19798",
   "in_source_library": true,
   "in_source_manifest": true,
   "page_basis": "PDF page (1-based)",
   "text_method": "PDF text layer",
   "note": "Controller of Budget report. The Siaya project tables are marked \"Source: Siaya County Treasury\", so they are county-reported, not independent."
  },
  {
   "doc_id": "cob-report-2020-21",
   "title": "County Governments Budget Implementation Review Report FY 2020/21",
   "publisher": "Office of the Controller of Budget",
   "doc_type": "cob_report_county_data",
   "independent": false,
   "published": "2022-01-25",
   "period": "FY 2020/21",
   "url": "https://libraryir.parliament.go.ke/items/79eb8b51-0c86-4077-aceb-e1e762cce44c",
   "sha256": "498e5e003147fbdb7da09c8a9079a1f940a09aa87076673255da3a2c54937868",
   "in_source_library": true,
   "in_source_manifest": true,
   "page_basis": "PDF page (1-based)",
   "text_method": "scanned; read with tesseract OCR (2020/21 and 2021/22 from the existing OCR text; 2022/23 to 2024/25 re-read at 400 dpi)",
   "note": "Controller of Budget report. The Siaya project tables are marked \"Source: Siaya County Treasury\", so they are county-reported, not independent."
  },
  {
   "doc_id": "cob-report-2021-22",
   "title": "County Governments Budget Implementation Review Report FY 2021/22",
   "publisher": "Office of the Controller of Budget",
   "doc_type": "cob_report_county_data",
   "independent": false,
   "published": "2022-09",
   "period": "FY 2021/22",
   "url": "https://libraryir.parliament.go.ke/items/f2353427-bb93-460c-b895-b3cae22a7178",
   "sha256": "e62e1a599503907bea4d7e144d96b3ffcbe810557d542bcf0fd4c224b109feb0",
   "in_source_library": true,
   "in_source_manifest": true,
   "page_basis": "PDF page (1-based)",
   "text_method": "scanned; read with tesseract OCR (2020/21 and 2021/22 from the existing OCR text; 2022/23 to 2024/25 re-read at 400 dpi)",
   "note": "Controller of Budget report. The Siaya project tables are marked \"Source: Siaya County Treasury\", so they are county-reported, not independent."
  },
  {
   "doc_id": "cob-report-2022-23",
   "title": "Annual County Governments Budget Implementation Review Report FY 2022/23",
   "publisher": "Office of the Controller of Budget",
   "doc_type": "cob_report_county_data",
   "independent": false,
   "published": "2024-04-23",
   "period": "FY 2022/23",
   "url": "https://libraryir.parliament.go.ke/handle/123456789/25332",
   "sha256": "385285d52418d94b8f72379a51dfacbbd4d11f8926840049269fa388dd47d9da",
   "in_source_library": true,
   "in_source_manifest": true,
   "page_basis": "PDF page (1-based)",
   "text_method": "scanned; read with tesseract OCR (2020/21 and 2021/22 from the existing OCR text; 2022/23 to 2024/25 re-read at 400 dpi)",
   "note": "Controller of Budget report. The Siaya project tables are marked \"Source: Siaya County Treasury\", so they are county-reported, not independent."
  },
  {
   "doc_id": "cob-report-2023-24",
   "title": "County Governments Budget Implementation Review Report FY 2023/24",
   "publisher": "Office of the Controller of Budget",
   "doc_type": "cob_report_county_data",
   "independent": false,
   "published": "2024-09-18",
   "period": "FY 2023/24",
   "url": "https://libraryir.parliament.go.ke/handle/123456789/28882",
   "sha256": "7a9690d049576fa1346a54da71f52c1742cdb01e154b99139cd1d445cbd6102f",
   "in_source_library": true,
   "in_source_manifest": true,
   "page_basis": "PDF page (1-based)",
   "text_method": "scanned; read with tesseract OCR (2020/21 and 2021/22 from the existing OCR text; 2022/23 to 2024/25 re-read at 400 dpi)",
   "note": "Controller of Budget report. The Siaya project tables are marked \"Source: Siaya County Treasury\", so they are county-reported, not independent."
  },
  {
   "doc_id": "cob-report-2024-25",
   "title": "County Governments Budget Implementation Review Report FY 2024/25",
   "publisher": "Office of the Controller of Budget",
   "doc_type": "cob_report_county_data",
   "independent": false,
   "published": "2025-09-23",
   "period": "FY 2024/25",
   "url": "https://libraryir.parliament.go.ke/items/e8739aa8-b91b-42db-8402-3b3bd53ff410",
   "sha256": "b69858e28e2c59de961f39e749e9885462e5608e9db2291b807040cc59a35f5c",
   "in_source_library": true,
   "in_source_manifest": true,
   "page_basis": "PDF page (1-based)",
   "text_method": "scanned; read with tesseract OCR (2020/21 and 2021/22 from the existing OCR text; 2022/23 to 2024/25 re-read at 400 dpi)",
   "note": "Controller of Budget report. The Siaya project tables are marked \"Source: Siaya County Treasury\", so they are county-reported, not independent."
  },
  {
   "doc_id": "audit-2020-21",
   "title": "Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021",
   "publisher": "Office of the Auditor-General",
   "doc_type": "audit_report",
   "independent": true,
   "published": "2022-06-30",
   "period": "FY 2020/21",
   "url": "https://libraryir.parliament.go.ke/items/d53598b9-f890-49aa-ad98-f18cf9c5bd6b/full",
   "sha256": "45a4bd1d40704369a109a82a02bac38304de0bf2e0b05dfd0632e2391b5e0a6b",
   "in_source_library": true,
   "in_source_manifest": true,
   "page_basis": "PDF page (1-based)",
   "text_method": "PDF text layer (OCR layer of a scan)",
   "note": "Findings tracker: data/siaya-audits.json."
  },
  {
   "doc_id": "audit-2021-22",
   "title": "Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022",
   "publisher": "Office of the Auditor-General",
   "doc_type": "audit_report",
   "independent": true,
   "published": "not legible (see data/siaya-audits.json)",
   "period": "FY 2021/22",
   "url": "https://libraryir.parliament.go.ke/items/54119713-1b4e-46dd-b95d-5484c7aeb01f/full",
   "sha256": "5066633d5c1201362b6a8520460b8d64918ea901294066ffb28a4b26142d2be7",
   "in_source_library": true,
   "in_source_manifest": true,
   "page_basis": "PDF page (1-based)",
   "text_method": "PDF text layer (OCR layer of a scan)",
   "note": "Findings tracker: data/siaya-audits.json."
  },
  {
   "doc_id": "audit-2022-23",
   "title": "Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023.",
   "publisher": "Office of the Auditor-General",
   "doc_type": "audit_report",
   "independent": true,
   "published": "2024-02-14",
   "period": "FY 2022/23",
   "url": "https://libraryir.parliament.go.ke/items/7e87be17-5566-48c8-ac76-d4658605ee6c/full",
   "sha256": "9eb4ed9e61ac1d512142b0a0d6c0df3f6e10535da9f0f0995f4b58bb4b0101e3",
   "in_source_library": true,
   "in_source_manifest": true,
   "page_basis": "PDF page (1-based)",
   "text_method": "PDF text layer (OCR layer of a scan)",
   "note": "Findings tracker: data/siaya-audits.json."
  },
  {
   "doc_id": "audit-2023-24",
   "title": "Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024",
   "publisher": "Office of the Auditor-General",
   "doc_type": "audit_report",
   "independent": true,
   "published": "2024-12-27",
   "period": "FY 2023/24",
   "url": "https://libraryir.parliament.go.ke/items/42bf64ec-74a8-44f6-be8f-5e1c79b0c407/full",
   "sha256": "d467556765db30e52a70ea38d1cb5ffe0dd56022100ec72d240409571fdfbc48",
   "in_source_library": true,
   "in_source_manifest": true,
   "page_basis": "PDF page (1-based)",
   "text_method": "PDF text layer (OCR layer of a scan)",
   "note": "Findings tracker: data/siaya-audits.json."
  },
  {
   "doc_id": "audit-2024-25",
   "title": "Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025",
   "publisher": "Office of the Auditor-General",
   "doc_type": "audit_report",
   "independent": true,
   "published": "2025-12-09",
   "period": "FY 2024/25",
   "url": "https://libraryir.parliament.go.ke/items/a8d4bb86-fc16-43f1-b109-97514df5e868",
   "sha256": "ac77d76f5df088d5ab1f07d4e0b045abeaa752bf60cc8be693bf20d18bfecabe",
   "in_source_library": false,
   "in_source_manifest": false,
   "page_basis": "PDF page (1-based)",
   "text_method": "no text layer; read with tesseract OCR",
   "note": "Findings tracker: data/siaya-audits.json."
  },
  {
   "doc_id": "audit-asm-2022-23",
   "title": "Report of the Auditor-General on County Assembly of Siaya for the Year Ended 30 June 2023",
   "publisher": "Office of the Auditor-General",
   "doc_type": "audit_report",
   "independent": true,
   "published": "2024-02-14",
   "period": "FY 2022/23",
   "url": "https://libraryir.parliament.go.ke/items/2ffcd198-5520-4407-abcf-a3bba6ebc66e",
   "sha256": "f29e0ab2e2893169a6c79fbeb9511bd5d089a568936b75dd8a13920c89dfd6ca",
   "in_source_library": false,
   "in_source_manifest": false,
   "page_basis": "PDF page (1-based)",
   "text_method": "PDF text layer (OCR layer of a scan)",
   "note": "Findings tracker: data/siaya-audits.json."
  },
  {
   "doc_id": "audit-asm-2023-24",
   "title": "Report of the Auditor-General on County Assembly of Siaya for the Year Ended 30 June, 2024",
   "publisher": "Office of the Auditor-General",
   "doc_type": "audit_report",
   "independent": true,
   "published": "2024-12-27",
   "period": "FY 2023/24",
   "url": "https://libraryir.parliament.go.ke/items/d97ee62e-564b-4a6b-a84a-b66cba4b9883",
   "sha256": "4854ae471a643b06f170b333f383a312e0eb7f77d454b0a03246d32466dac3b5",
   "in_source_library": false,
   "in_source_manifest": false,
   "page_basis": "PDF page (1-based)",
   "text_method": "PDF text layer (OCR layer of a scan)",
   "note": "Findings tracker: data/siaya-audits.json."
  }
 ],
 "projects": [
  {
   "id": "SIA-P-001",
   "name": "Construction of Siaya County Stadium",
   "aliases": [
    {
     "name": "Construction of Siaya County Stadium",
     "doc_id": "cob-report-2018-19",
     "page": 272
    },
    {
     "name": "Proposed construction of Siaya County Stadium",
     "doc_id": "cob-report-2023-24",
     "page": 516
    },
    {
     "name": "Construction of Siaya County Stadium (Siaya Head-quarters)",
     "doc_id": "cob-report-2021-22",
     "page": 411
    }
   ],
   "sector": "sports_culture_tourism",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Siaya town",
      "doc_id": "cob-report-2018-19",
      "page": 272,
      "unresolved_reason": "a town, not a ward or constituency name"
     },
     {
      "text": "Siaya Township (OCR: Siaya'lbwnship)",
      "doc_id": "cob-report-2020-21",
      "page": 376,
      "resolved_to": [
       {
        "ward_id": "siaya-township"
       }
      ]
     },
     {
      "text": "Siaya Head-quarters",
      "doc_id": "cob-report-2021-22",
      "page": 411,
      "unresolved_reason": "the county headquarters, not a ward"
     }
    ],
    "ward_ids": [
     "siaya-township"
    ],
    "constituency_ids": [
     "alego-usonga"
    ],
    "countywide": false,
    "unresolved": [
     {
      "text": "Siaya town",
      "reason": "a town, not a ward or constituency name"
     },
     {
      "text": "Siaya Head-quarters",
      "reason": "the county headquarters, not a ward"
     }
    ]
   },
   "amounts": [
    {
     "kind": "approved_budget",
     "value": 180000000,
     "unit": "KSh",
     "fy": "2018/19",
     "doc_id": "cob-report-2018-19",
     "page": 272,
     "label_as_printed": "Project Budget"
    },
    {
     "kind": "expenditure_in_fy",
     "value": 85303489,
     "unit": "KSh",
     "fy": "2018/19",
     "doc_id": "cob-report-2018-19",
     "page": 272,
     "label_as_printed": "Project Expenditure"
    },
    {
     "kind": "approved_budget",
     "value": 70000000,
     "unit": "KSh",
     "fy": "2020/21",
     "doc_id": "cob-report-2020-21",
     "page": 376,
     "label_as_printed": "Budget (column as read by OCR)"
    },
    {
     "kind": "expenditure_in_fy",
     "value": 117602147,
     "unit": "KSh",
     "fy": "2020/21",
     "doc_id": "cob-report-2020-21",
     "page": 376,
     "label_as_printed": "Expenditure (absorption 168.0%)"
    },
    {
     "kind": "contract_sum",
     "value": 394661767,
     "unit": "KSh",
     "fy": "2020/21",
     "doc_id": "audit-2020-21",
     "page": 41,
     "label_as_printed": "contract sum (contract signed 30 Aug 2018)"
    },
    {
     "kind": "certified_cumulative",
     "value": 327091241,
     "unit": "KSh",
     "fy": "2020/21",
     "doc_id": "audit-2020-21",
     "page": 41,
     "label_as_printed": "total certified works (valuation certificate 1 Mar 2021)",
     "as_at": "2021-03-01"
    },
    {
     "kind": "paid_in_fy",
     "value": 80254180,
     "unit": "KSh",
     "fy": "2020/21",
     "doc_id": "audit-2020-21",
     "page": 41,
     "label_as_printed": "paid to the main contractor"
    },
    {
     "kind": "paid_in_fy",
     "value": 14648670,
     "unit": "KSh",
     "fy": "2020/21",
     "doc_id": "audit-2020-21",
     "page": 41,
     "label_as_printed": "paid to two local sub-contractors (plumbing, electrical)"
    },
    {
     "kind": "contract_sum",
     "value": 394661767,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "cob-report-2021-22",
     "page": 411,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "approved_budget",
     "value": 78207870,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "cob-report-2021-22",
     "page": 411,
     "label_as_printed": "Budget"
    },
    {
     "kind": "paid_cumulative",
     "value": 67093742,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "cob-report-2021-22",
     "page": 411,
     "label_as_printed": "Amount paid to date"
    },
    {
     "kind": "paid_in_fy",
     "value": 57999787,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "audit-2021-22",
     "page": 51,
     "label_as_printed": "paid towards construction (OCR: Kshs.S7,999,787)"
    },
    {
     "kind": "revised_contract_sum",
     "value": 488716823,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "audit-2021-22",
     "page": 51,
     "label_as_printed": "contract sum revised"
    },
    {
     "kind": "variation",
     "value": 94055056,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "audit-2021-22",
     "page": 51,
     "label_as_printed": "variation (24%)"
    },
    {
     "kind": "contract_sum",
     "value": 35512450,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "audit-2022-23",
     "page": 48,
     "label_as_printed": "separate roof-works contract (14 Sep 2022)"
    },
    {
     "kind": "revised_contract_sum",
     "value": 524229273,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "audit-2022-23",
     "page": 48,
     "label_as_printed": "construction cost including roof contract (variation 32%)"
    },
    {
     "kind": "paid_cumulative",
     "value": 425038687,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "audit-2022-23",
     "page": 48,
     "label_as_printed": "total payments to contractors at the time of audit"
    },
    {
     "kind": "contract_sum",
     "value": 424872927,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "paid_cumulative",
     "value": 441964497,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "label_as_printed": "Amount paid to date"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": "2018-08-30",
    "start": "2019-01-01",
    "expected_completion": "2019-12-06"
   },
   "status": "delayed",
   "status_source": {
    "doc_id": "audit-2023-24",
    "page": 55,
    "evidence_type": "audit_documentary_review",
    "as_at": "2024-08-30"
   },
   "last_evidence_date": "2024-08-30",
   "audit_finding_ids": [
    "audit-2020-21-21",
    "audit-2021-22-26",
    "audit-2022-23-22",
    "audit-2023-24-29"
   ],
   "evidence": [
    {
     "doc_id": "cob-report-2018-19",
     "page": 272,
     "evidence_type": "cob_report_county_data",
     "as_at": "2019-06-30",
     "finding_id": null,
     "summary": "Listed among projects with the highest expenditure; 47.4% absorption of the project budget.",
     "confidence": 5
    },
    {
     "doc_id": "cob-report-2020-21",
     "page": 376,
     "evidence_type": "cob_report_county_data",
     "as_at": "2021-06-30",
     "finding_id": null,
     "summary": "Expenditure above budget (168%), attributed to a supplementary budget cut.",
     "confidence": 3
    },
    {
     "doc_id": "audit-2020-21",
     "page": 41,
     "evidence_type": "audit_physical_verification",
     "as_at": "2021-11",
     "finding_id": "audit-2020-21-21",
     "summary": "Audit verification in November 2021: incomplete 23 months after the completion date; about 83% complete per the 1 March 2021 valuation; performance bond expired 20 Apr 2020.",
     "confidence": 4,
     "reported_completion_pct": 83
    },
    {
     "doc_id": "cob-report-2021-22",
     "page": 411,
     "evidence_type": "cob_report_county_data",
     "as_at": "2022-06-30",
     "finding_id": null,
     "summary": "County: implementation status 60%, \"Project is incomplete\".",
     "confidence": 3,
     "reported_completion_pct": 60
    },
    {
     "doc_id": "audit-2021-22",
     "page": 51,
     "evidence_type": "audit_physical_verification",
     "as_at": "2022-11",
     "finding_id": "audit-2021-22-26",
     "summary": "Audit verification in November 2022: still incomplete about 35 months after inception; six extensions, latest to 25 May 2022; 24% variation without evaluation committee.",
     "confidence": 4
    },
    {
     "doc_id": "audit-2022-23",
     "page": 48,
     "evidence_type": "audit_physical_verification",
     "as_at": "2023",
     "finding_id": "audit-2022-23-22",
     "summary": "Contract period expired July 2023; physical verification found pending works; separate roof contract raised cost to KSh 524,229,273.",
     "confidence": 4
    },
    {
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "evidence_type": "cob_report_county_data",
     "as_at": "2024-06-30",
     "finding_id": null,
     "summary": "County: implementation status 85%.",
     "confidence": 3,
     "reported_completion_pct": 85
    },
    {
     "doc_id": "audit-2023-24",
     "page": 55,
     "evidence_type": "audit_documentary_review",
     "as_at": "2024-08-30",
     "finding_id": "audit-2023-24-29",
     "summary": "Project status report shows nine extensions as of 30 Aug 2024 (not verified by the auditor); variation of 24% without evaluation committee.",
     "confidence": 4
    }
   ],
   "conflicts": [
    {
     "field": "contract_sum",
     "note": "Audits print KSh 394,661,767 (original), 488,716,823 (revised) and 524,229,273 (with roof contract); CoB FY 2023/24 prints 424,872,927."
    },
    {
     "field": "paid_in_fy",
     "note": "FY 2020/21: CoB (county data) KSh 117,602,147 against audit KSh 80,254,180 + 14,648,670. FY 2021/22: CoB KSh 67,093,742 against audit KSh 57,999,787."
    }
   ],
   "related_project_ids": [
    "SIA-P-002",
    "SIA-P-003",
    "SIA-P-004",
    "SIA-P-006",
    "SIA-P-112"
   ],
   "status_note": "Not reported complete by any source; the latest independent evidence (FY 2023/24 audit) records nine extensions. A separate completion contract is SIA-P for \"Completion of the Siaya stadium\"."
  },
  {
   "id": "SIA-P-002",
   "name": "Installation of three-phase electricity power at the Siaya Stadium",
   "aliases": [],
   "sector": "energy_lighting",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Siaya Stadium",
      "doc_id": "audit-2023-24",
      "page": 53,
      "unresolved_reason": "a facility, not a ward"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Siaya Stadium",
      "reason": "a facility, not a ward"
     }
    ]
   },
   "amounts": [
    {
     "kind": "paid_in_fy",
     "value": 1336721,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "audit-2023-24",
     "page": 53,
     "label_as_printed": "cost paid 16 Nov 2023"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": {
     "doc": "audit-2023-24",
     "page": 53,
     "note": "named in the audit report; withheld pending review"
    },
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "delayed",
   "status_source": {
    "doc_id": "audit-2023-24",
    "page": 53,
    "evidence_type": "audit_physical_verification",
    "as_at": "2024"
   },
   "last_evidence_date": "2024",
   "audit_finding_ids": [
    "audit-2023-24-25"
   ],
   "evidence": [
    {
     "doc_id": "audit-2023-24",
     "page": 53,
     "evidence_type": "audit_physical_verification",
     "as_at": "2024",
     "finding_id": "audit-2023-24-25",
     "summary": "Physical inspection: transformer not installed; stadium has no power connected. Requisition 23 Sep 2023, payment 16 Nov 2023.",
     "confidence": 4
    }
   ],
   "conflicts": [],
   "related_project_ids": [
    "SIA-P-001"
   ]
  },
  {
   "id": "SIA-P-003",
   "name": "Installation of stadium VIP seats",
   "aliases": [
    {
     "name": "Installation of Stadium VIP seats",
     "doc_id": "cob-report-2024-25",
     "page": 483
    }
   ],
   "sector": "sports_culture_tourism",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Executive",
      "doc_id": "cob-report-2024-25",
      "page": 483,
      "unresolved_reason": "location column reads \"Executive\" (the implementing office), so no place is stated"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Executive",
      "reason": "location column reads \"Executive\" (the implementing office), so no place is stated"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 25101114,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "audit-2023-24",
     "page": 54,
     "label_as_printed": "contract sum"
    },
    {
     "kind": "advance",
     "value": 5020222,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "audit-2023-24",
     "page": 54,
     "label_as_printed": "advance payment (20%)"
    },
    {
     "kind": "contract_sum",
     "value": 25101114,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "paid_cumulative",
     "value": 25101114,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "label_as_printed": "Cumulative expenditure as of 30 June 2025"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": {
     "doc": "audit-2023-24",
     "page": 54,
     "note": "named in the audit report; withheld pending review"
    },
    "signed": "2024-04-08",
    "start": null,
    "expected_completion": "2024-06 (CoB: Jun-24)"
   },
   "status": "completed-reported",
   "status_source": {
    "doc_id": "cob-report-2024-25",
    "page": 483,
    "evidence_type": "cob_report_county_data",
    "as_at": "2025-06-30"
   },
   "last_evidence_date": "2025-06-30",
   "audit_finding_ids": [
    "audit-2023-24-26"
   ],
   "evidence": [
    {
     "doc_id": "audit-2023-24",
     "page": 54,
     "evidence_type": "audit_physical_verification",
     "as_at": "2024",
     "finding_id": "audit-2023-24-26",
     "summary": "Physical inspection: 1,494 fixed seats and 471 foldable seats installed, 45 fewer foldable seats than the bill of quantities (516); advance paid without an inspection report.",
     "confidence": 4
    },
    {
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "evidence_type": "cob_report_county_data",
     "as_at": "2025-06-30",
     "finding_id": null,
     "summary": "County: implementation status 100%.",
     "confidence": 4,
     "reported_completion_pct": 100
    }
   ],
   "conflicts": [
    {
     "field": "status",
     "note": "The county reports 100% (30 June 2025); the earlier FY 2023/24 audit inspection counted 45 fewer foldable seats than contracted. No independent check after the county report."
    }
   ],
   "related_project_ids": [
    "SIA-P-001"
   ]
  },
  {
   "id": "SIA-P-004",
   "name": "Supply and installation of stadium lighting mast for the proposed stadium for the County Government of Siaya",
   "aliases": [],
   "sector": "energy_lighting",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Executive",
      "doc_id": "cob-report-2024-25",
      "page": 483,
      "unresolved_reason": "location column reads \"Executive\" (the implementing office), so no place is stated"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Executive",
      "reason": "location column reads \"Executive\" (the implementing office), so no place is stated"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 20614000,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "paid_cumulative",
     "value": 20614000,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "label_as_printed": "Cumulative expenditure as of 30 June 2025"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": "2024-06 (Jun-24)"
   },
   "status": "completed-reported",
   "status_source": {
    "doc_id": "cob-report-2024-25",
    "page": 483,
    "evidence_type": "cob_report_county_data",
    "as_at": "2025-06-30"
   },
   "last_evidence_date": "2025-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "evidence_type": "cob_report_county_data",
     "as_at": "2025-06-30",
     "finding_id": null,
     "summary": "County: implementation status 100%.",
     "confidence": 4,
     "reported_completion_pct": 100
    }
   ],
   "conflicts": [],
   "related_project_ids": [
    "SIA-P-001"
   ]
  },
  {
   "id": "SIA-P-005",
   "name": "Proposed installation of Tartan on the running track",
   "aliases": [],
   "sector": "sports_culture_tourism",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Executive",
      "doc_id": "cob-report-2024-25",
      "page": 483,
      "unresolved_reason": "location column reads \"Executive\" (the implementing office), so no place is stated"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Executive",
      "reason": "location column reads \"Executive\" (the implementing office), so no place is stated"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 137350000,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "label_as_printed": "Contract sum (two of three OCR reads)"
    },
    {
     "kind": "paid_in_fy",
     "value": 56010500,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "label_as_printed": "Amount paid in FY 2024/25"
    },
    {
     "kind": "paid_cumulative",
     "value": 56010500,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "label_as_printed": "Cumulative expenditure as of 30 June 2025"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": "2024-06 (Jun-24)"
   },
   "status": "delayed",
   "status_source": {
    "doc_id": "cob-report-2024-25",
    "page": 483,
    "evidence_type": "cob_report_county_data",
    "as_at": "2025-06-30"
   },
   "last_evidence_date": "2025-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "evidence_type": "cob_report_county_data",
     "as_at": "2025-06-30",
     "finding_id": null,
     "summary": "County: 70% against an expected completion of June 2024.",
     "confidence": 3,
     "reported_completion_pct": 70
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Delayed on the county's own dates: 70% at 30 June 2025 against an expected completion of June 2024. The table does not say which track."
  },
  {
   "id": "SIA-P-006",
   "name": "Completion of the Siaya stadium",
   "aliases": [],
   "sector": "sports_culture_tourism",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Executive",
      "doc_id": "cob-report-2024-25",
      "page": 483,
      "unresolved_reason": "location column reads \"Executive\" (the implementing office), so no place is stated"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Executive",
      "reason": "location column reads \"Executive\" (the implementing office), so no place is stated"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 28175350,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "paid_cumulative",
     "value": 28175350,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "label_as_printed": "Cumulative expenditure as of 30 June 2025"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": "2024-12 (Dec-24)"
   },
   "status": "completed-reported",
   "status_source": {
    "doc_id": "cob-report-2024-25",
    "page": 483,
    "evidence_type": "cob_report_county_data",
    "as_at": "2025-06-30"
   },
   "last_evidence_date": "2025-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "evidence_type": "cob_report_county_data",
     "as_at": "2025-06-30",
     "finding_id": null,
     "summary": "County: implementation status 100%.",
     "confidence": 4,
     "reported_completion_pct": 100
    }
   ],
   "conflicts": [],
   "related_project_ids": [
    "SIA-P-001"
   ],
   "status_note": "A completion contract reported at 100% by the county. Whether the stadium as a whole is complete has not been independently checked."
  },
  {
   "id": "SIA-P-007",
   "name": "Construction of Siaya Bus Park",
   "aliases": [
    {
     "name": "Siaya Bus Park",
     "doc_id": "audit-2022-23",
     "page": 46
    }
   ],
   "sector": "roads_transport",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Siaya Town",
      "doc_id": "audit-2022-23",
      "page": 46,
      "unresolved_reason": "a town, not a ward or constituency name"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Siaya Town",
      "reason": "a town, not a ward or constituency name"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 23014867,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "audit-2021-22",
     "page": 53,
     "label_as_printed": "cost (awarded March 2020)"
    },
    {
     "kind": "paid_cumulative",
     "value": 12582218,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "audit-2021-22",
     "page": 53,
     "label_as_printed": "paid at the time of audit"
    },
    {
     "kind": "paid_cumulative",
     "value": 17582978,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "audit-2022-23",
     "page": 46,
     "label_as_printed": "total paid before termination"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": "2020-08-07",
    "start": null,
    "expected_completion": "2021-02-22"
   },
   "status": "cancelled",
   "status_source": {
    "doc_id": "audit-2022-23",
    "page": 46,
    "evidence_type": "audit_physical_verification",
    "as_at": "2023-11"
   },
   "last_evidence_date": "2023-11",
   "audit_finding_ids": [
    "audit-2021-22-31",
    "audit-2022-23-17"
   ],
   "evidence": [
    {
     "doc_id": "audit-2021-22",
     "page": 53,
     "evidence_type": "audit_documentary_review",
     "as_at": "2022",
     "finding_id": "audit-2021-22-31",
     "summary": "About 60% complete; duration lapsed by over 16 months; extension to 22 Feb 2022 without evaluation committee.",
     "confidence": 4,
     "reported_completion_pct": 60
    },
    {
     "doc_id": "audit-2022-23",
     "page": 46,
     "evidence_type": "audit_physical_verification",
     "as_at": "2023-11",
     "finding_id": "audit-2022-23-17",
     "summary": "Contract terminated at the contractor's request on 2 June 2023; physical verification in November 2023 found works stalled and abandoned.",
     "confidence": 4
    }
   ],
   "conflicts": [
    {
     "field": "contract.signed",
     "note": "FY 2021/22 audit says awarded in March 2020; FY 2022/23 audit says contract entered on 7 August 2020."
    }
   ],
   "related_project_ids": [],
   "status_note": "Contract terminated 2 June 2023; no later source on re-tendering."
  },
  {
   "id": "SIA-P-008",
   "name": "Construction of Haudinga Sheltered Workshop in Ukwala",
   "aliases": [],
   "sector": "social_services",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Haudinga Sheltered Workshop in Ukwala",
      "doc_id": "audit-2020-21",
      "page": 38,
      "resolved_to": [
       {
        "ward_id": "ukwala"
       }
      ]
     }
    ],
    "ward_ids": [
     "ukwala"
    ],
    "constituency_ids": [
     "ugenya"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 6678405,
     "unit": "KSh",
     "fy": "2020/21",
     "doc_id": "audit-2020-21",
     "page": 38,
     "label_as_printed": "contract sum"
    },
    {
     "kind": "paid_in_fy",
     "value": 5407305,
     "unit": "KSh",
     "fy": "2020/21",
     "doc_id": "audit-2020-21",
     "page": 38,
     "label_as_printed": "paid to a local contractor"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": "2020-06-22",
    "start": null,
    "expected_completion": "2020-10 (16 weeks from award)"
   },
   "status": "delayed",
   "status_source": {
    "doc_id": "audit-2020-21",
    "page": 38,
    "evidence_type": "audit_physical_verification",
    "as_at": "2021-11"
   },
   "last_evidence_date": "2021-11",
   "audit_finding_ids": [
    "audit-2020-21-12"
   ],
   "evidence": [
    {
     "doc_id": "audit-2020-21",
     "page": 38,
     "evidence_type": "audit_physical_verification",
     "as_at": "2021-11",
     "finding_id": "audit-2020-21-12",
     "summary": "Physical inspection November 2021: incomplete over a year after the expected completion; no completion certificate. Management said it was complete and handed over.",
     "confidence": 4
    }
   ],
   "conflicts": [
    {
     "field": "status",
     "note": "Management reported completion and handover; the audit inspection found it incomplete."
    }
   ],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-009",
   "name": "Construction of Nyasanda Sheltered Workshop in Ugunja",
   "aliases": [],
   "sector": "social_services",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Nyasanda Sheltered Workshop in Ugunja",
      "doc_id": "audit-2020-21",
      "page": 38,
      "resolved_to": [
       {
        "constituency_id": "ugunja"
       }
      ],
      "unresolved_reason": "\"Ugunja\" is both a ward and a constituency; resolved to the constituency only"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [
     "ugunja"
    ],
    "countywide": false,
    "unresolved": [
     {
      "text": "Nyasanda Sheltered Workshop in Ugunja",
      "reason": "\"Ugunja\" is both a ward and a constituency; resolved to the constituency only"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 6831702,
     "unit": "KSh",
     "fy": "2020/21",
     "doc_id": "audit-2020-21",
     "page": 38,
     "label_as_printed": "contract sum"
    },
    {
     "kind": "paid_in_fy",
     "value": 1500000,
     "unit": "KSh",
     "fy": "2020/21",
     "doc_id": "audit-2020-21",
     "page": 38,
     "label_as_printed": "paid to a local contractor"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": "2019-06-28",
    "start": null,
    "expected_completion": "2019-10 (four months from award)"
   },
   "status": "delayed",
   "status_source": {
    "doc_id": "audit-2020-21",
    "page": 38,
    "evidence_type": "audit_physical_verification",
    "as_at": "2021-11"
   },
   "last_evidence_date": "2021-11",
   "audit_finding_ids": [
    "audit-2020-21-13"
   ],
   "evidence": [
    {
     "doc_id": "audit-2020-21",
     "page": 38,
     "evidence_type": "audit_physical_verification",
     "as_at": "2021-11",
     "finding_id": "audit-2020-21-13",
     "summary": "Physical verification November 2021: latrine, electricity, water tank and gutters not done; contractor not on site; no extension. Management said complete and handed over.",
     "confidence": 4
    }
   ],
   "conflicts": [
    {
     "field": "status",
     "note": "Management reported completion; the audit found items not done."
    }
   ],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-010",
   "name": "Construction of Nyamnina Youth Polytechnic",
   "aliases": [],
   "sector": "education",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "not stated",
      "doc_id": "audit-2020-21",
      "page": 38,
      "unresolved_reason": "no location printed"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "not stated",
      "reason": "no location printed"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 3870156,
     "unit": "KSh",
     "fy": "2020/21",
     "doc_id": "audit-2020-21",
     "page": 38,
     "label_as_printed": "contract price"
    },
    {
     "kind": "paid_in_fy",
     "value": 2908328,
     "unit": "KSh",
     "fy": "2020/21",
     "doc_id": "audit-2020-21",
     "page": 38,
     "label_as_printed": "paid to a contractor"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": "2020-02-24",
    "expected_completion": "2020-05 (12 weeks)"
   },
   "status": "delayed",
   "status_source": {
    "doc_id": "audit-2020-21",
    "page": 38,
    "evidence_type": "audit_physical_verification",
    "as_at": "2021-11"
   },
   "last_evidence_date": "2021-11",
   "audit_finding_ids": [
    "audit-2020-21-14"
   ],
   "evidence": [
    {
     "doc_id": "audit-2020-21",
     "page": 38,
     "evidence_type": "audit_physical_verification",
     "as_at": "2021-11",
     "finding_id": "audit-2020-21-14",
     "summary": "Physical verification November 2021: still incomplete, contractor not on site, despite a completion certificate dated 17 Feb 2021.",
     "confidence": 4
    }
   ],
   "conflicts": [
    {
     "field": "status",
     "note": "County completion certificate (17 Feb 2021) against an incomplete finding at inspection."
    }
   ],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-011",
   "name": "Renovations at Odera Akang'o Campus (works at Directors Office)",
   "aliases": [],
   "sector": "education",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "not stated",
      "doc_id": "audit-2020-21",
      "page": 39,
      "unresolved_reason": "no location printed"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "not stated",
      "reason": "no location printed"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 36653220,
     "unit": "KSh",
     "fy": "2020/21",
     "doc_id": "audit-2020-21",
     "page": 39,
     "label_as_printed": "contract sum"
    },
    {
     "kind": "paid_in_fy",
     "value": 5067399,
     "unit": "KSh",
     "fy": "2020/21",
     "doc_id": "audit-2020-21",
     "page": 39,
     "label_as_printed": "paid on 1 Oct 2020"
    },
    {
     "kind": "certified_cumulative",
     "value": 33955486,
     "unit": "KSh",
     "fy": "2020/21",
     "doc_id": "audit-2020-21",
     "page": 39,
     "label_as_printed": "certified for payment (92% of contract sum)"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": "2018-01",
    "start": null,
    "expected_completion": "2018-10-25"
   },
   "status": "delayed",
   "status_source": {
    "doc_id": "audit-2020-21",
    "page": 39,
    "evidence_type": "audit_physical_verification",
    "as_at": "2021-11"
   },
   "last_evidence_date": "2021-11",
   "audit_finding_ids": [
    "audit-2020-21-15"
   ],
   "evidence": [
    {
     "doc_id": "audit-2020-21",
     "page": 39,
     "evidence_type": "audit_physical_verification",
     "as_at": "2021-11",
     "finding_id": "audit-2020-21-15",
     "summary": "Physical verification November 2021: renovation of the principal's office not started; contractor not on site; practical completion certificate of 10 Feb 2021 without a snag list.",
     "confidence": 4
    }
   ],
   "conflicts": [
    {
     "field": "status",
     "note": "Practical completion certificate (10 Feb 2021) against incomplete works at inspection."
    }
   ],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-012",
   "name": "Construction of a laboratory at Obaga West Asembo Health Centre",
   "aliases": [],
   "sector": "health",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Obaga West Asembo Health Centre",
      "doc_id": "audit-2020-21",
      "page": 39,
      "resolved_to": [
       {
        "ward_id": "west-asembo"
       }
      ]
     }
    ],
    "ward_ids": [
     "west-asembo"
    ],
    "constituency_ids": [
     "rarieda"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "paid_in_fy",
     "value": 1295372,
     "unit": "KSh",
     "fy": "2020/21",
     "doc_id": "audit-2020-21",
     "page": 39,
     "label_as_printed": "paid to a local contractor"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "unknown",
   "status_source": {
    "doc_id": "audit-2020-21",
    "page": 39,
    "evidence_type": "audit_physical_verification",
    "as_at": "2021-11"
   },
   "last_evidence_date": "2021-11",
   "audit_finding_ids": [
    "audit-2020-21-17"
   ],
   "evidence": [
    {
     "doc_id": "audit-2020-21",
     "page": 39,
     "evidence_type": "audit_physical_verification",
     "as_at": "2021-11",
     "finding_id": "audit-2020-21-17",
     "summary": "Physical verification November 2021: cracked door frames, 10 of 14 windows and 4 of 5 doors installed, paving not done; variation not documented; no completion certificate.",
     "confidence": 4
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "The laboratory was built with deviations from the bill of quantities; no source states completion."
  },
  {
   "id": "SIA-P-013",
   "name": "Maintenance of Maira Othatch Road and Bar Okwiri Kayouth roads",
   "aliases": [],
   "sector": "roads_transport",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "not stated",
      "doc_id": "audit-2020-21",
      "page": 40,
      "unresolved_reason": "road names only; no ward printed"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "not stated",
      "reason": "road names only; no ward printed"
     }
    ]
   },
   "amounts": [
    {
     "kind": "paid_in_fy",
     "value": 10305315,
     "unit": "KSh",
     "fy": "2020/21",
     "doc_id": "audit-2020-21",
     "page": 40,
     "label_as_printed": "paid, equal to the contract sum"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "unknown",
   "status_source": {
    "doc_id": "audit-2020-21",
    "page": 40,
    "evidence_type": "audit_physical_verification",
    "as_at": "2021-11"
   },
   "last_evidence_date": "2021-11",
   "audit_finding_ids": [
    "audit-2020-21-18"
   ],
   "evidence": [
    {
     "doc_id": "audit-2020-21",
     "page": 40,
     "evidence_type": "audit_physical_verification",
     "as_at": "2021-11",
     "finding_id": "audit-2020-21-18",
     "summary": "Physical verification November 2021: no evidence of clearing, grading or gravelling. Management said defects were later rectified; no completion certificate.",
     "confidence": 4
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Management says rectified; not verified by any source."
  },
  {
   "id": "SIA-P-014",
   "name": "Rehabilitation of Siaya Slaughterhouse",
   "aliases": [],
   "sector": "agriculture_fisheries",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Siaya",
      "doc_id": "audit-2020-21",
      "page": 40,
      "unresolved_reason": "\"Siaya\" can mean the county, Siaya town or the Siaya/Alego Usonga sub-county; not resolved"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Siaya",
      "reason": "\"Siaya\" can mean the county, Siaya town or the Siaya/Alego Usonga sub-county; not resolved"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 9984993,
     "unit": "KSh",
     "fy": "2020/21",
     "doc_id": "audit-2020-21",
     "page": 40,
     "label_as_printed": "contract sum"
    },
    {
     "kind": "paid_in_fy",
     "value": 3999999,
     "unit": "KSh",
     "fy": "2020/21",
     "doc_id": "audit-2020-21",
     "page": 40,
     "label_as_printed": "paid to a local contractor"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": "2021-02-05",
    "start": null,
    "expected_completion": "2021-06 (16 weeks)"
   },
   "status": "delayed",
   "status_source": {
    "doc_id": "audit-2020-21",
    "page": 40,
    "evidence_type": "audit_physical_verification",
    "as_at": "2021-11"
   },
   "last_evidence_date": "2021-11",
   "audit_finding_ids": [
    "audit-2020-21-19"
   ],
   "evidence": [
    {
     "doc_id": "audit-2020-21",
     "page": 40,
     "evidence_type": "audit_physical_verification",
     "as_at": "2021-11",
     "finding_id": "audit-2020-21-19",
     "summary": "Physical verification November 2021: incomplete four months after the contract period; contractor not on site; no extension evidence.",
     "confidence": 4
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-015",
   "name": "Construction of Migwena Sports Stadium (2017 contract)",
   "aliases": [],
   "sector": "sports_culture_tourism",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "not stated",
      "doc_id": "audit-2020-21",
      "page": 40,
      "unresolved_reason": "no location printed"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "not stated",
      "reason": "no location printed"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 22433511,
     "unit": "KSh",
     "fy": "2020/21",
     "doc_id": "audit-2020-21",
     "page": 40,
     "label_as_printed": "cost sum (24-week contract)"
    },
    {
     "kind": "other_payment",
     "value": 6966833,
     "unit": "KSh",
     "fy": "2019/20",
     "doc_id": "audit-2020-21",
     "page": 40,
     "label_as_printed": "awarded to the contractor for works done, paid in FY 2019/20"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": "2017",
    "start": null,
    "expected_completion": null
   },
   "status": "cancelled",
   "status_source": {
    "doc_id": "audit-2020-21",
    "page": 40,
    "evidence_type": "audit_physical_verification",
    "as_at": "2021-11"
   },
   "last_evidence_date": "2021-11",
   "audit_finding_ids": [
    "audit-2020-21-20"
   ],
   "evidence": [
    {
     "doc_id": "audit-2020-21",
     "page": 40,
     "evidence_type": "audit_physical_verification",
     "as_at": "2021-11",
     "finding_id": "audit-2020-21-20",
     "summary": "Contract ended after a breach by the county; audit inspection November 2021 found only the pavilion foundation and about 15 tonnes of ballast.",
     "confidence": 4
    }
   ],
   "conflicts": [],
   "related_project_ids": [
    "SIA-P-028",
    "SIA-P-029",
    "SIA-P-113"
   ]
  },
  {
   "id": "SIA-P-016",
   "name": "Drainage, grading, gravelling and dozing of Kwaweya Yenga Nyalula Udura Kolum road (12 km)",
   "aliases": [],
   "sector": "roads_transport",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "not stated",
      "doc_id": "audit-2021-22",
      "page": 53,
      "unresolved_reason": "road name only"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "not stated",
      "reason": "road name only"
     }
    ]
   },
   "amounts": [
    {
     "kind": "paid_in_fy",
     "value": 7722584,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "audit-2021-22",
     "page": 53,
     "label_as_printed": "paid"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "delayed",
   "status_source": {
    "doc_id": "audit-2021-22",
    "page": 53,
    "evidence_type": "audit_physical_verification",
    "as_at": "2022-07-27"
   },
   "last_evidence_date": "2022-07-27",
   "audit_finding_ids": [
    "audit-2021-22-29"
   ],
   "evidence": [
    {
     "doc_id": "audit-2021-22",
     "page": 53,
     "evidence_type": "audit_physical_verification",
     "as_at": "2022-07-27",
     "finding_id": "audit-2021-22-29",
     "summary": "Physical verification 27 July 2022: 3 km of the 12 km not graded or gravelled.",
     "confidence": 4
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Incomplete at verification; no later source."
  },
  {
   "id": "SIA-P-017",
   "name": "Repairs and maintenance of Boro-Katondi Road, Ogunga Road and Segere-Ouru Road",
   "aliases": [],
   "sector": "roads_transport",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "not stated",
      "doc_id": "audit-2021-22",
      "page": 53,
      "unresolved_reason": "road names only"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "not stated",
      "reason": "road names only"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 14659268,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "audit-2021-22",
     "page": 53,
     "label_as_printed": "contract sum, three roads"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "unknown",
   "status_source": {
    "doc_id": "audit-2021-22",
    "page": 53,
    "evidence_type": "audit_physical_verification",
    "as_at": "2022-11-10"
   },
   "last_evidence_date": "2022-11-10",
   "audit_finding_ids": [
    "audit-2021-22-30"
   ],
   "evidence": [
    {
     "doc_id": "audit-2021-22",
     "page": 53,
     "evidence_type": "audit_physical_verification",
     "as_at": "2022-11-10",
     "finding_id": "audit-2021-22-30",
     "summary": "Physical verification 10 Nov 2022: damaged culvert line on Boro-Katondi road. The paid amount is partly illegible in the text layer.",
     "confidence": 3
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-018",
   "name": "Tarmacking of Opoda-Bondo township road",
   "aliases": [
    {
     "name": "Tarmacking of Opoda Bondo Township Road",
     "doc_id": "cob-report-2020-21",
     "page": 376
    },
    {
     "name": "Tarmacking of Opoda road in Bondo Township",
     "doc_id": "cob-report-2021-22",
     "page": 412
    }
   ],
   "sector": "roads_transport",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "North Sakwa",
      "doc_id": "cob-report-2020-21",
      "page": 376,
      "resolved_to": [
       {
        "ward_id": "north-sakwa"
       }
      ]
     },
     {
      "text": "North Uyoma",
      "doc_id": "cob-report-2020-21",
      "page": 377,
      "resolved_to": [
       {
        "ward_id": "north-uyoma"
       }
      ]
     },
     {
      "text": "South Sakwa",
      "doc_id": "cob-report-2021-22",
      "page": 412,
      "resolved_to": [
       {
        "ward_id": "south-sakwa"
       }
      ]
     }
    ],
    "ward_ids": [
     "north-sakwa",
     "north-uyoma",
     "south-sakwa"
    ],
    "constituency_ids": [
     "bondo",
     "rarieda"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "approved_budget",
     "value": 152000000,
     "unit": "KSh",
     "fy": "2020/21",
     "doc_id": "cob-report-2020-21",
     "page": 376,
     "label_as_printed": "Budget (OCR \"I 52,000,000\"; the same figure is printed on three rows)",
     "note": "OCR"
    },
    {
     "kind": "expenditure_in_fy",
     "value": 45199541,
     "unit": "KSh",
     "fy": "2020/21",
     "doc_id": "cob-report-2020-21",
     "page": 376,
     "label_as_printed": "Expenditure, row 2 (absorption 29.7%)"
    },
    {
     "kind": "contract_sum",
     "value": 52805116,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "audit-2021-22",
     "page": 53,
     "label_as_printed": "cost (OCR \"S2,805,116\"; 17,692,949 is printed as 33.5% of it)"
    },
    {
     "kind": "paid_cumulative",
     "value": 17692949,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "audit-2021-22",
     "page": 53,
     "label_as_printed": "paid as at 30 June 2022",
     "as_at": "2022-06-30"
    },
    {
     "kind": "paid_cumulative",
     "value": 17692949,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "cob-report-2021-22",
     "page": 412,
     "label_as_printed": "Amount paid to date (also printed in the contract-sum column)"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": "2020-07",
    "start": null,
    "expected_completion": "2021-11-23"
   },
   "status": "delayed",
   "status_source": {
    "doc_id": "audit-2021-22",
    "page": 53,
    "evidence_type": "audit_physical_verification",
    "as_at": "2022"
   },
   "last_evidence_date": "2022-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2020-21",
     "page": 376,
     "evidence_type": "cob_report_county_data",
     "as_at": "2021-06-30",
     "finding_id": null,
     "summary": "Four rows for this road (North Sakwa x3, North Uyoma x1) with absorption 29.7%, 22.1%, 47.5% and 14.4%; only row 2 is transcribed.",
     "confidence": 2
    },
    {
     "doc_id": "cob-report-2021-22",
     "page": 412,
     "evidence_type": "cob_report_county_data",
     "as_at": "2022-06-30",
     "finding_id": null,
     "summary": "County: implementation 100%, \"Project complete and in use\".",
     "confidence": 3,
     "reported_completion_pct": 100
    },
    {
     "doc_id": "audit-2021-22",
     "page": 53,
     "evidence_type": "audit_physical_verification",
     "as_at": "2022",
     "finding_id": null,
     "summary": "Audit paragraph 8.5: executed works estimated at only 20%, contractor not on site (not one of the findings transcribed in data/siaya-audits.json).",
     "confidence": 4,
     "reported_completion_pct": 20
    }
   ],
   "conflicts": [
    {
     "field": "status",
     "note": "County (CoB FY 2021/22) reports 100% complete and in use; the FY 2021/22 audit estimates 20% executed with the contractor off site."
    },
    {
     "field": "location",
     "note": "Printed as North Sakwa, North Uyoma and South Sakwa in different rows and years."
    },
    {
     "field": "amount",
     "note": "CoB FY 2020/21 budget KSh 152,000,000 against an audited contract cost of KSh 52,805,116."
    }
   ],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-019",
   "name": "Construction of five ECD classrooms (Mahero, Kirindo, Ninga, Nyadheho and Nyabondo primary schools)",
   "aliases": [],
   "sector": "education",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Mahero, Kirindo, Ninga, Nyadheho and Nyabondo Primary Schools",
      "doc_id": "audit-2021-22",
      "page": 54,
      "unresolved_reason": "school names only"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Mahero, Kirindo, Ninga, Nyadheho and Nyabondo Primary Schools",
      "reason": "school names only"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 19124181,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "audit-2021-22",
     "page": 54,
     "label_as_printed": "total contract sum"
    },
    {
     "kind": "paid_in_fy",
     "value": 9701685,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "audit-2021-22",
     "page": 54,
     "label_as_printed": "paid (legible in the closing sentence)"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "delayed",
   "status_source": {
    "doc_id": "audit-2021-22",
    "page": 54,
    "evidence_type": "audit_physical_verification",
    "as_at": "2022"
   },
   "last_evidence_date": "2022",
   "audit_finding_ids": [
    "audit-2021-22-32"
   ],
   "evidence": [
    {
     "doc_id": "audit-2021-22",
     "page": 54,
     "evidence_type": "audit_physical_verification",
     "as_at": "2022",
     "finding_id": "audit-2021-22-32",
     "summary": "Physical verification: windows, doors, floors, plastering and electrical works pending; contractors not on site at all five.",
     "confidence": 4
    }
   ],
   "conflicts": [],
   "related_project_ids": [
    "SIA-P-020"
   ]
  },
  {
   "id": "SIA-P-020",
   "name": "Construction of Early Childhood Development (ECD) block at Kirindo primary school",
   "aliases": [],
   "sector": "education",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Kirindo primary school",
      "doc_id": "audit-2022-23",
      "page": 46,
      "unresolved_reason": "school name only"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Kirindo primary school",
      "reason": "school name only"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 3888053,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "audit-2022-23",
     "page": 46,
     "label_as_printed": "contract sum"
    },
    {
     "kind": "paid_cumulative",
     "value": 2570332,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "audit-2022-23",
     "page": 46,
     "label_as_printed": "paid by 30 June 2023",
     "as_at": "2023-06-30"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": "2022-01-03",
    "start": null,
    "expected_completion": "2022-04 (16 weeks)"
   },
   "status": "suspended",
   "status_source": {
    "doc_id": "audit-2022-23",
    "page": 46,
    "evidence_type": "audit_physical_verification",
    "as_at": "2023-11"
   },
   "last_evidence_date": "2023-11",
   "audit_finding_ids": [
    "audit-2021-22-32",
    "audit-2022-23-16"
   ],
   "evidence": [
    {
     "doc_id": "audit-2021-22",
     "page": 54,
     "evidence_type": "audit_physical_verification",
     "as_at": "2022",
     "finding_id": "audit-2021-22-32",
     "summary": "One of the five incomplete ECD classrooms.",
     "confidence": 4
    },
    {
     "doc_id": "audit-2022-23",
     "page": 46,
     "evidence_type": "audit_physical_verification",
     "as_at": "2023-11",
     "finding_id": "audit-2022-23-16",
     "summary": "Site visit November 2023: works stalled; contractor not on site; no extension.",
     "confidence": 4
    }
   ],
   "conflicts": [],
   "related_project_ids": [
    "SIA-P-019"
   ]
  },
  {
   "id": "SIA-P-021",
   "name": "Drilling and equipping of nine boreholes in Ugunja, Alego and Rarieda sub-counties",
   "aliases": [],
   "sector": "water_sanitation",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Ugunja, Alego and Rarienda [sic, Rarieda] sub-counties",
      "doc_id": "audit-2021-22",
      "page": 54,
      "resolved_to": [
       {
        "constituency_id": "ugunja"
       },
       {
        "constituency_id": "alego-usonga"
       },
       {
        "constituency_id": "rarieda"
       }
      ]
     }
    ],
    "ward_ids": [],
    "constituency_ids": [
     "ugunja",
     "alego-usonga",
     "rarieda"
    ],
    "countywide": false,
    "unresolved": [],
    "note": "\"Alego\" is read as Alego Usonga; \"Rarienda\" is an OCR/print variant of Rarieda."
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 29040488,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "audit-2021-22",
     "page": 54,
     "label_as_printed": "contract sum"
    },
    {
     "kind": "paid_in_fy",
     "value": 9640750,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "audit-2021-22",
     "page": 54,
     "label_as_printed": "paid (legible in the closing sentence)"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "delayed",
   "status_source": {
    "doc_id": "audit-2021-22",
    "page": 54,
    "evidence_type": "audit_physical_verification",
    "as_at": "2022"
   },
   "last_evidence_date": "2022",
   "audit_finding_ids": [
    "audit-2021-22-33"
   ],
   "evidence": [
    {
     "doc_id": "audit-2021-22",
     "page": 54,
     "evidence_type": "audit_physical_verification",
     "as_at": "2022",
     "finding_id": "audit-2021-22-33",
     "summary": "Physical verification of sampled boreholes (Alara, Pala Kobong and Kolo primary schools): not equipped; contractors not on site; no extension.",
     "confidence": 4
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-022",
   "name": "Supply and installation of machines, wiring repairs and construction of a powerhouse at Madiany Ginnery",
   "aliases": [],
   "sector": "agriculture_fisheries",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Madiany Ginnery in West Uyoma ward",
      "doc_id": "audit-2021-22",
      "page": 54,
      "resolved_to": [
       {
        "ward_id": "west-uyoma"
       }
      ]
     }
    ],
    "ward_ids": [
     "west-uyoma"
    ],
    "constituency_ids": [
     "rarieda"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 10237191,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "audit-2021-22",
     "page": 54,
     "label_as_printed": "contract sum"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "unknown",
   "status_source": {
    "doc_id": "audit-2021-22",
    "page": 54,
    "evidence_type": "audit_physical_verification",
    "as_at": "2022-11-15"
   },
   "last_evidence_date": "2022-11-15",
   "audit_finding_ids": [
    "audit-2021-22-34"
   ],
   "evidence": [
    {
     "doc_id": "audit-2021-22",
     "page": 54,
     "evidence_type": "audit_physical_verification",
     "as_at": "2022-11-15",
     "finding_id": "audit-2021-22-34",
     "summary": "Visit 15 Nov 2022: no power, cracked powerhouse slab, project not operational.",
     "confidence": 4
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Works were done but the facility was not operational; no source reports completion."
  },
  {
   "id": "SIA-P-023",
   "name": "Construction of Kagwa Dispensary laboratory",
   "aliases": [
    {
     "name": "Kagwa Health Centre Laboratory",
     "doc_id": "audit-2021-22",
     "page": 54
    }
   ],
   "sector": "health",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "not stated",
      "doc_id": "audit-2021-22",
      "page": 54,
      "unresolved_reason": "facility name only"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "not stated",
      "reason": "facility name only"
     }
    ]
   },
   "amounts": [
    {
     "kind": "certified_cumulative",
     "value": 4326869,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "audit-2021-22",
     "page": 54,
     "label_as_printed": "works certified complete as per bills of quantities"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "completed-reported",
   "status_source": {
    "doc_id": "audit-2021-22",
    "page": 54,
    "evidence_type": "audit_physical_verification",
    "as_at": "2022-07"
   },
   "last_evidence_date": "2022-07",
   "audit_finding_ids": [
    "audit-2021-22-35"
   ],
   "evidence": [
    {
     "doc_id": "audit-2021-22",
     "page": 54,
     "evidence_type": "audit_physical_verification",
     "as_at": "2022-07",
     "finding_id": "audit-2021-22-35",
     "summary": "Works certified complete by a county technical inspection report (21 June 2021); audit site verification in July 2022 found the laboratory not in use.",
     "confidence": 4
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Completion rests on the county's technical inspection report quoted in the audit. The audit visit found the laboratory unused but does not itself state that the works were complete, so it is not marked independently verified."
  },
  {
   "id": "SIA-P-024",
   "name": "Construction of Modern Market in Ukwala Market",
   "aliases": [],
   "sector": "markets_trade",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Ukwala Market",
      "doc_id": "audit-2022-23",
      "page": 47,
      "resolved_to": [
       {
        "ward_id": "ukwala"
       }
      ]
     }
    ],
    "ward_ids": [
     "ukwala"
    ],
    "constituency_ids": [
     "ugenya"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 5740187.46,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "audit-2022-23",
     "page": 47,
     "label_as_printed": "contract award"
    },
    {
     "kind": "paid_cumulative",
     "value": 4252545,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "audit-2022-23",
     "page": 47,
     "label_as_printed": "paid to date"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": "2021-03-16",
    "start": null,
    "expected_completion": "2021-07 (16 weeks)"
   },
   "status": "suspended",
   "status_source": {
    "doc_id": "audit-2022-23",
    "page": 47,
    "evidence_type": "audit_physical_verification",
    "as_at": "2023-09"
   },
   "last_evidence_date": "2023-09",
   "audit_finding_ids": [
    "audit-2022-23-18"
   ],
   "evidence": [
    {
     "doc_id": "audit-2022-23",
     "page": 47,
     "evidence_type": "audit_physical_verification",
     "as_at": "2023-09",
     "finding_id": "audit-2022-23-18",
     "summary": "Physical verification September 2023: floor works, stalls and electrical works incomplete; contractor had abandoned the project; performance bond expired.",
     "confidence": 4
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-025",
   "name": "Construction of Nyadorera Modern Market",
   "aliases": [],
   "sector": "markets_trade",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "not stated",
      "doc_id": "audit-2022-23",
      "page": 47,
      "unresolved_reason": "market name only"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "not stated",
      "reason": "market name only"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 11665784,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "audit-2022-23",
     "page": 47,
     "label_as_printed": "contract sum"
    },
    {
     "kind": "paid_cumulative",
     "value": 8532406,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "audit-2022-23",
     "page": 47,
     "label_as_printed": "paid as at 30 June 2023",
     "as_at": "2023-06-30"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": "2022-03-15",
    "start": null,
    "expected_completion": "2022-07 (16 weeks)"
   },
   "status": "delayed",
   "status_source": {
    "doc_id": "audit-2022-23",
    "page": 47,
    "evidence_type": "audit_physical_verification",
    "as_at": "2023-11"
   },
   "last_evidence_date": "2023-11",
   "audit_finding_ids": [
    "audit-2022-23-19"
   ],
   "evidence": [
    {
     "doc_id": "audit-2022-23",
     "page": 47,
     "evidence_type": "audit_physical_verification",
     "as_at": "2023-11",
     "finding_id": "audit-2022-23-19",
     "summary": "Visit November 2023: floor, surface, painting and toilet works incomplete; contractor not on site; bond expired.",
     "confidence": 4
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-026",
   "name": "Fencing and gravelling works at Akala and Ramba Markets",
   "aliases": [],
   "sector": "markets_trade",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Ramba Market Siaya township ward",
      "doc_id": "audit-2022-23",
      "page": 47,
      "resolved_to": [
       {
        "ward_id": "siaya-township"
       }
      ]
     },
     {
      "text": "Akala Market in South gem ward",
      "doc_id": "audit-2022-23",
      "page": 47,
      "resolved_to": [
       {
        "ward_id": "south-gem"
       }
      ]
     }
    ],
    "ward_ids": [
     "siaya-township",
     "south-gem"
    ],
    "constituency_ids": [
     "alego-usonga",
     "gem"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 7715774,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "audit-2022-23",
     "page": 47,
     "label_as_printed": "contract price"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": "2022-05-22",
    "start": null,
    "expected_completion": "2022-07-15"
   },
   "status": "delayed",
   "status_source": {
    "doc_id": "audit-2022-23",
    "page": 47,
    "evidence_type": "audit_physical_verification",
    "as_at": "2023-10"
   },
   "last_evidence_date": "2023-10",
   "audit_finding_ids": [
    "audit-2022-23-20"
   ],
   "evidence": [
    {
     "doc_id": "audit-2022-23",
     "page": 47,
     "evidence_type": "audit_physical_verification",
     "as_at": "2023-10",
     "finding_id": "audit-2022-23-20",
     "summary": "Interim certificates (22 June 2022): Ramba 88%, Akala 55%; site visits October 2023 found remaining works not done; overall 73%.",
     "confidence": 4,
     "reported_completion_pct": 73
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-027",
   "name": "Drilling and equipping of Aila WC Borehole",
   "aliases": [],
   "sector": "water_sanitation",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Aila WC",
      "doc_id": "audit-2022-23",
      "page": 48,
      "unresolved_reason": "institution name only"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Aila WC",
      "reason": "institution name only"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 4479975,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "audit-2022-23",
     "page": 48,
     "label_as_printed": "contract sum"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": "2023-03-29",
    "start": null,
    "expected_completion": null
   },
   "status": "unknown",
   "status_source": {
    "doc_id": "audit-2022-23",
    "page": 48,
    "evidence_type": "audit_physical_verification",
    "as_at": "2023-08"
   },
   "last_evidence_date": "2023-08",
   "audit_finding_ids": [
    "audit-2022-23-21"
   ],
   "evidence": [
    {
     "doc_id": "audit-2022-23",
     "page": 48,
     "evidence_type": "audit_physical_verification",
     "as_at": "2023-08",
     "finding_id": "audit-2022-23-21",
     "summary": "County inspection and acceptance report says fully executed; physical verification August 2023 found no drilling at the site. Management said works were done elsewhere, without documents.",
     "confidence": 4
    }
   ],
   "conflicts": [
    {
     "field": "status",
     "note": "County acceptance report (fully executed) against no borehole found at the contracted site."
    }
   ],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-028",
   "name": "Proposed construction of perimeter wall at Migwena Sports and Cultural Centre (Piny Luo)",
   "aliases": [
    {
     "name": "Construction of Perimeter Wall at Migwena Sports Cultural Center",
     "doc_id": "audit-2023-24",
     "page": 54
    }
   ],
   "sector": "sports_culture_tourism",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Executive",
      "doc_id": "cob-report-2024-25",
      "page": 483,
      "unresolved_reason": "location column reads \"Executive\" (the implementing office), so no place is stated"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Executive",
      "reason": "location column reads \"Executive\" (the implementing office), so no place is stated"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 33841097,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "audit-2023-24",
     "page": 54,
     "label_as_printed": "contract sum"
    },
    {
     "kind": "paid_in_fy",
     "value": 28718584,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "audit-2023-24",
     "page": 54,
     "label_as_printed": "cumulative payments, certificates 1 and 2 (85%)"
    },
    {
     "kind": "contract_sum",
     "value": 33841097.5,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "paid_cumulative",
     "value": 28834584,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "label_as_printed": "Cumulative expenditure as of 30 June 2025"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": "2024-01-31",
    "expected_completion": "2024-07-31"
   },
   "status": "completed-reported",
   "status_source": {
    "doc_id": "cob-report-2024-25",
    "page": 483,
    "evidence_type": "cob_report_county_data",
    "as_at": "2025-06-30"
   },
   "last_evidence_date": "2025-06-30",
   "audit_finding_ids": [
    "audit-2023-24-27"
   ],
   "evidence": [
    {
     "doc_id": "audit-2023-24",
     "page": 54,
     "evidence_type": "audit_physical_verification",
     "as_at": "2024-09",
     "finding_id": "audit-2023-24-27",
     "summary": "Physical verification September 2024: keying and plaster differ from the bill of quantities; project not complete; only a perimeter wall exists.",
     "confidence": 4
    },
    {
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "evidence_type": "cob_report_county_data",
     "as_at": "2025-06-30",
     "finding_id": null,
     "summary": "County: implementation status 100%.",
     "confidence": 4,
     "reported_completion_pct": 100
    }
   ],
   "conflicts": [
    {
     "field": "status",
     "note": "County reports 100% at 30 June 2025; the September 2024 audit inspection found it incomplete and not to specification."
    },
    {
     "field": "paid",
     "note": "Audit KSh 28,718,584 paid in FY 2023/24; county cumulative KSh 28,834,584 at 30 June 2025."
    }
   ],
   "related_project_ids": [
    "SIA-P-015",
    "SIA-P-029"
   ]
  },
  {
   "id": "SIA-P-029",
   "name": "Proposed washroom, gravelling works, waterworks, powerhouse and electrification at Migwena",
   "aliases": [],
   "sector": "sports_culture_tourism",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Migwena",
      "doc_id": "audit-2023-24",
      "page": 55,
      "unresolved_reason": "a place name that is not a ward or constituency"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Migwena",
      "reason": "a place name that is not a ward or constituency"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 18630456,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "audit-2023-24",
     "page": 55,
     "label_as_printed": "contract sum"
    },
    {
     "kind": "paid_in_fy",
     "value": 4350440,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "audit-2023-24",
     "page": 55,
     "label_as_printed": "paid for works done"
    }
   ],
   "contract": {
    "reference": "CGS/SCM/TCSA/OT/2023-2024/017",
    "reference_as_printed": "CGS/SCM/TCSA/OT12023-2024/017 (OCR)",
    "contractor_reference": {
     "doc": "audit-2023-24",
     "page": 55,
     "note": "named in the audit report; withheld pending review"
    },
    "signed": null,
    "start": "2024-02-08",
    "expected_completion": "2024-08-08"
   },
   "status": "delayed",
   "status_source": {
    "doc_id": "audit-2023-24",
    "page": 55,
    "evidence_type": "audit_documentary_review",
    "as_at": "2024"
   },
   "last_evidence_date": "2024",
   "audit_finding_ids": [
    "audit-2023-24-28"
   ],
   "evidence": [
    {
     "doc_id": "audit-2023-24",
     "page": 55,
     "evidence_type": "audit_documentary_review",
     "as_at": "2024",
     "finding_id": "audit-2023-24-28",
     "summary": "Paid KSh 4,350,440; no approved extension of time after the intended completion of 8 Aug 2024.",
     "confidence": 4
    }
   ],
   "conflicts": [],
   "related_project_ids": [
    "SIA-P-028"
   ]
  },
  {
   "id": "SIA-P-030",
   "name": "Construction of County Aggregation and Industrial Park",
   "aliases": [
    {
     "name": "Establishment of industrial park",
     "doc_id": "cob-report-2023-24",
     "page": 516
    },
    {
     "name": "Construction of Siaya County Aggregation and Industrial Park",
     "doc_id": "audit-2024-25",
     "page": 54
    }
   ],
   "sector": "industry",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Central Alego",
      "doc_id": "cob-report-2023-24",
      "page": 516,
      "resolved_to": [
       {
        "ward_id": "central-alego"
       }
      ]
     }
    ],
    "ward_ids": [
     "central-alego"
    ],
    "constituency_ids": [
     "alego-usonga"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 483688922.23,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "audit-2023-24",
     "page": 55,
     "label_as_printed": "contract sum (multi-year project)"
    },
    {
     "kind": "advance",
     "value": 48368892.2,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "audit-2023-24",
     "page": 55,
     "label_as_printed": "advance payment"
    },
    {
     "kind": "contract_sum",
     "value": 483688922,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "paid_cumulative",
     "value": 48368892,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "label_as_printed": "Amount paid to date"
    },
    {
     "kind": "contract_sum",
     "value": 483688922,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "audit-2024-25",
     "page": 54,
     "label_as_printed": "cost (co-funded equally with the National Government)"
    },
    {
     "kind": "other_payment",
     "value": 62500000,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "audit-2024-25",
     "page": 54,
     "label_as_printed": "National Government transfer as at 30 March 2025",
     "as_at": "2025-03-30"
    }
   ],
   "contract": {
    "reference": "CGS/SCM/E&ID/OT/2022-2023/055",
    "reference_as_printed": "CGS/SCM/ElDlOT12022- 20231055 (OCR)",
    "contractor_reference": null,
    "signed": "2023-08-18",
    "start": "2023-08-30 (site possession)",
    "expected_completion": "28 weeks from possession (FY 2023/24 audit); 80 weeks (FY 2024/25 audit)"
   },
   "status": "suspended",
   "status_source": {
    "doc_id": "audit-2024-25",
    "page": 54,
    "evidence_type": "audit_physical_verification",
    "as_at": "2025-10"
   },
   "last_evidence_date": "2025-10",
   "audit_finding_ids": [
    "audit-2023-24-30",
    "audit-2024-25-18"
   ],
   "evidence": [
    {
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "evidence_type": "cob_report_county_data",
     "as_at": "2024-06-30",
     "finding_id": null,
     "summary": "County: implementation status 15%.",
     "confidence": 3,
     "reported_completion_pct": 15
    },
    {
     "doc_id": "audit-2023-24",
     "page": 55,
     "evidence_type": "audit_physical_verification",
     "as_at": "2024-09-16",
     "finding_id": "audit-2023-24-30",
     "summary": "Physical inspection 16 Sep 2024: foundations for some warehouses only; no plant, materials or ongoing work on site.",
     "confidence": 4
    },
    {
     "doc_id": "audit-2024-25",
     "page": 54,
     "evidence_type": "audit_physical_verification",
     "as_at": "2025-10",
     "finding_id": "audit-2024-25-18",
     "summary": "Progress report of 9 Sep 2024: 12% complete; physical inspection October 2025: contractor not on site, project stalled.",
     "confidence": 3,
     "reported_completion_pct": 12
    }
   ],
   "conflicts": [
    {
     "field": "contract.expected_completion",
     "note": "FY 2023/24 audit: 28 weeks; FY 2024/25 audit: 80 weeks."
    }
   ],
   "related_project_ids": [
    "SIA-P-110"
   ]
  },
  {
   "id": "SIA-P-031",
   "name": "Proposed Construction of Yala Cattle Ring in Yala Township Ward",
   "aliases": [],
   "sector": "agriculture_fisheries",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Yala township ward",
      "doc_id": "audit-2023-24",
      "page": 56,
      "resolved_to": [
       {
        "ward_id": "yala-township"
       }
      ]
     }
    ],
    "ward_ids": [
     "yala-township"
    ],
    "constituency_ids": [
     "gem"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 4500962.55,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "audit-2023-24",
     "page": 56,
     "label_as_printed": "contract price inclusive of 16% VAT"
    }
   ],
   "contract": {
    "reference": "CGS/SCM/E&ID/OT/2023-2024/039",
    "reference_as_printed": "CGS/SCM/E\\D|OT|2O23-20241039 (OCR)",
    "contractor_reference": null,
    "signed": "2024-02-12",
    "start": "2024-03-20 (site possession)",
    "expected_completion": "2024-07-20"
   },
   "status": "delayed",
   "status_source": {
    "doc_id": "audit-2023-24",
    "page": 56,
    "evidence_type": "audit_physical_verification",
    "as_at": "2024"
   },
   "last_evidence_date": "2024",
   "audit_finding_ids": [
    "audit-2023-24-31"
   ],
   "evidence": [
    {
     "doc_id": "audit-2023-24",
     "page": 56,
     "evidence_type": "audit_physical_verification",
     "as_at": "2024",
     "finding_id": "audit-2023-24-31",
     "summary": "Physical inspection: completion date elapsed; contractor not on site.",
     "confidence": 4
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-032",
   "name": "Construction of four door flushable toilets and four bathrooms at Akala Health Centre",
   "aliases": [],
   "sector": "health",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Akala Health Centre in South Gem Ward",
      "doc_id": "audit-2023-24",
      "page": 56,
      "resolved_to": [
       {
        "ward_id": "south-gem"
       }
      ]
     }
    ],
    "ward_ids": [
     "south-gem"
    ],
    "constituency_ids": [
     "gem"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 3215578.8,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "audit-2023-24",
     "page": 56,
     "label_as_printed": "contract sum"
    },
    {
     "kind": "paid_in_fy",
     "value": 1000000,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "audit-2023-24",
     "page": 56,
     "label_as_printed": "paid against invoice of 8 Apr 2024"
    }
   ],
   "contract": {
    "reference": "CGS/HEALTH/Q/2023-2024/034",
    "reference_as_printed": "CGS/HEALTH|Q|2023-20241034 (OCR)",
    "contractor_reference": null,
    "signed": "2024-02-16",
    "start": "2024-03-07",
    "expected_completion": "2024-06-10"
   },
   "status": "suspended",
   "status_source": {
    "doc_id": "audit-2023-24",
    "page": 56,
    "evidence_type": "audit_physical_verification",
    "as_at": "2024-09-17"
   },
   "last_evidence_date": "2024-09-17",
   "audit_finding_ids": [
    "audit-2023-24-32"
   ],
   "evidence": [
    {
     "doc_id": "audit-2023-24",
     "page": 56,
     "evidence_type": "audit_physical_verification",
     "as_at": "2024-09-17",
     "finding_id": "audit-2023-24-32",
     "summary": "Certified 36% on 1 Apr 2024; inspection 17 Sep 2024 found no work since; only substructure and wall frames.",
     "confidence": 4,
     "reported_completion_pct": 36
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-033",
   "name": "Construction of ECD Block at Maranyona Primary School",
   "aliases": [],
   "sector": "education",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Maranyona Primary School",
      "doc_id": "audit-2024-25",
      "page": 54,
      "unresolved_reason": "school name only"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Maranyona Primary School",
      "reason": "school name only"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 4134669,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "audit-2024-25",
     "page": 54,
     "label_as_printed": "contract sum"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": "FY 2022/23",
    "start": "2023-05",
    "expected_completion": "2023-08 (12 weeks)"
   },
   "status": "delayed",
   "status_source": {
    "doc_id": "audit-2024-25",
    "page": 54,
    "evidence_type": "audit_physical_verification",
    "as_at": "2025-07"
   },
   "last_evidence_date": "2025-07",
   "audit_finding_ids": [
    "audit-2024-25-19"
   ],
   "evidence": [
    {
     "doc_id": "audit-2024-25",
     "page": 54,
     "evidence_type": "audit_physical_verification",
     "as_at": "2025-07",
     "finding_id": "audit-2024-25-19",
     "summary": "Physical inspection July 2025: not completed over 25 months from the contract date; painting, tiling, glazing and latrine incomplete.",
     "confidence": 3
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-034",
   "name": "Proposed completion of ECD Block at Nyabera Primary School",
   "aliases": [],
   "sector": "education",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Nyabera Primary School",
      "doc_id": "audit-2024-25",
      "page": 55,
      "unresolved_reason": "school name only"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Nyabera Primary School",
      "reason": "school name only"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 4307957,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "audit-2024-25",
     "page": 55,
     "label_as_printed": "contract sum"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": "2022-03-09",
    "expected_completion": "2022-06"
   },
   "status": "suspended",
   "status_source": {
    "doc_id": "audit-2024-25",
    "page": 55,
    "evidence_type": "audit_physical_verification",
    "as_at": "2025-07"
   },
   "last_evidence_date": "2025-07",
   "audit_finding_ids": [
    "audit-2024-25-21"
   ],
   "evidence": [
    {
     "doc_id": "audit-2024-25",
     "page": 55,
     "evidence_type": "audit_physical_verification",
     "as_at": "2025-07",
     "finding_id": "audit-2024-25-21",
     "summary": "As at July 2025 the project had stalled; contractor not on site; site neglected.",
     "confidence": 3
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-035",
   "name": "Construction of a modern Early Childhood Development Education (ECDE) Centre in Bondo Sub-County",
   "aliases": [],
   "sector": "education",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Bondo Sub-County",
      "doc_id": "audit-2024-25",
      "page": 58,
      "resolved_to": [
       {
        "constituency_id": "bondo"
       }
      ]
     }
    ],
    "ward_ids": [],
    "constituency_ids": [
     "bondo"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "advance",
     "value": 10931825,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "audit-2024-25",
     "page": 58,
     "label_as_printed": "advance payment (20% of the contract sum)"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": "FY 2024/25",
    "start": null,
    "expected_completion": null
   },
   "status": "active",
   "status_source": {
    "doc_id": "audit-2024-25",
    "page": 58,
    "evidence_type": "audit_physical_verification",
    "as_at": "2025-10"
   },
   "last_evidence_date": "2025-10",
   "audit_finding_ids": [
    "audit-2024-25-30"
   ],
   "evidence": [
    {
     "doc_id": "audit-2024-25",
     "page": 58,
     "evidence_type": "audit_physical_verification",
     "as_at": "2025-10",
     "finding_id": "audit-2024-25-30",
     "summary": "Physical inspections July and October 2025: unauthorised changes (roof fixings, windows, truss spacing 4.4 m against 2 m).",
     "confidence": 3
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Under construction with unapproved design changes; no completion percentage printed."
  },
  {
   "id": "SIA-P-036",
   "name": "Supply, delivery, installation and commissioning of mortuary cold-room plant at Bondo Sub-County Hospital",
   "aliases": [
    {
     "name": "Refrigeration at Bondo hospital morgue (mortuary cold room plant)",
     "doc_id": "cob-report-2024-25",
     "page": 483
    }
   ],
   "sector": "health",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Bondo Sub-County Hospital",
      "doc_id": "audit-2024-25",
      "page": 59,
      "resolved_to": [
       {
        "constituency_id": "bondo"
       }
      ]
     }
    ],
    "ward_ids": [],
    "constituency_ids": [
     "bondo"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 54685880,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "audit-2024-25",
     "page": 59,
     "label_as_printed": "contract sum"
    },
    {
     "kind": "contract_sum",
     "value": 54685880,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "paid_cumulative",
     "value": 51785880,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "label_as_printed": "Cumulative expenditure as of 30 June 2025"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": "2024-04-04",
    "start": null,
    "expected_completion": "2024-06-27 (audit); 2025-05-01 (CoB)"
   },
   "status": "delayed",
   "status_source": {
    "doc_id": "audit-2024-25",
    "page": 59,
    "evidence_type": "audit_physical_verification",
    "as_at": "2025-10"
   },
   "last_evidence_date": "2025-10",
   "audit_finding_ids": [
    "audit-2024-25-31"
   ],
   "evidence": [
    {
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "evidence_type": "cob_report_county_data",
     "as_at": "2025-06-30",
     "finding_id": null,
     "summary": "County: implementation status 100%.",
     "confidence": 4,
     "reported_completion_pct": 100
    },
    {
     "doc_id": "audit-2024-25",
     "page": 59,
     "evidence_type": "audit_physical_verification",
     "as_at": "2025-10",
     "finding_id": "audit-2024-25-31",
     "summary": "At the audit in October 2025 the cold-room plant was not yet installed; contractor on site; contract period lapsed without extension.",
     "confidence": 3
    }
   ],
   "conflicts": [
    {
     "field": "status",
     "note": "County reports 100% at 30 June 2025; the October 2025 audit found the plant not installed."
    }
   ],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-037",
   "name": "Supply, delivery and installation of medical equipment at Siaya Hospital Theatre Complex",
   "aliases": [
    {
     "name": "Equipping of 3 theatres at SCRH",
     "doc_id": "cob-report-2024-25",
     "page": 483
    }
   ],
   "sector": "health",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Siaya Hospital Theatre Complex",
      "doc_id": "audit-2024-25",
      "page": 55,
      "unresolved_reason": "facility name only"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Siaya Hospital Theatre Complex",
      "reason": "facility name only"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 22974650,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "audit-2024-25",
     "page": 55,
     "label_as_printed": "cost"
    },
    {
     "kind": "paid_cumulative",
     "value": 20477338,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "audit-2024-25",
     "page": 55,
     "label_as_printed": "paid (89%)"
    },
    {
     "kind": "paid_cumulative",
     "value": 20477338,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "label_as_printed": "Cumulative expenditure as of 30 June 2025"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": "2025-01",
    "start": null,
    "expected_completion": "2024-05-01 (CoB, as printed)"
   },
   "status": "delayed",
   "status_source": {
    "doc_id": "audit-2024-25",
    "page": 56,
    "evidence_type": "audit_physical_verification",
    "as_at": "2025-10"
   },
   "last_evidence_date": "2025-10",
   "audit_finding_ids": [
    "audit-2024-25-22"
   ],
   "evidence": [
    {
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "evidence_type": "cob_report_county_data",
     "as_at": "2025-06-30",
     "finding_id": null,
     "summary": "County: implementation status 100%.",
     "confidence": 3,
     "reported_completion_pct": 100
    },
    {
     "doc_id": "audit-2024-25",
     "page": 56,
     "evidence_type": "audit_physical_verification",
     "as_at": "2025-10",
     "finding_id": "audit-2024-25-22",
     "summary": "Physical inspection October 2025: equipment delivered 6 Feb 2025 but not installed or commissioned; some stored in open spaces.",
     "confidence": 3
    }
   ],
   "conflicts": [
    {
     "field": "status",
     "note": "County reports 100%; the October 2025 audit found the equipment not installed."
    }
   ],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-038",
   "name": "Proposed construction of maternity block at Malunga Dispensary",
   "aliases": [],
   "sector": "health",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Malunga Dispensary",
      "doc_id": "audit-2024-25",
      "page": 56,
      "unresolved_reason": "facility name only"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Malunga Dispensary",
      "reason": "facility name only"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 4400000,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "audit-2024-25",
     "page": 56,
     "label_as_printed": "cost"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": "FY 2024/25",
    "start": null,
    "expected_completion": null
   },
   "status": "completed-independently-verified",
   "status_source": {
    "doc_id": "audit-2024-25",
    "page": 56,
    "evidence_type": "audit_physical_verification",
    "as_at": "2025-07"
   },
   "last_evidence_date": "2025-07",
   "audit_finding_ids": [
    "audit-2024-25-23"
   ],
   "evidence": [
    {
     "doc_id": "audit-2024-25",
     "page": 56,
     "evidence_type": "audit_physical_verification",
     "as_at": "2025-07",
     "finding_id": "audit-2024-25-23",
     "summary": "Physical verification July 2025 \"revealed that the facility was complete but remained idle\".",
     "confidence": 3,
     "verifies_completion": true
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Completion seen by the Auditor-General on site (July 2025). The facility was idle, so complete does not mean in service."
  },
  {
   "id": "SIA-P-039",
   "name": "Drilling and equipping of two boreholes at Ligose Primary and Ligala Dispensary",
   "aliases": [],
   "sector": "water_sanitation",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Ligose Primary and Ligala Dispensary",
      "doc_id": "audit-2024-25",
      "page": 56,
      "unresolved_reason": "institution names only"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Ligose Primary and Ligala Dispensary",
      "reason": "institution names only"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 5819100,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "audit-2024-25",
     "page": 56,
     "label_as_printed": "contract cost, two boreholes"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": "FY 2024/25",
    "start": null,
    "expected_completion": null
   },
   "status": "unknown",
   "status_source": {
    "doc_id": "audit-2024-25",
    "page": 56,
    "evidence_type": "audit_physical_verification",
    "as_at": "2025-07"
   },
   "last_evidence_date": "2025-07",
   "audit_finding_ids": [
    "audit-2024-25-23"
   ],
   "evidence": [
    {
     "doc_id": "audit-2024-25",
     "page": 56,
     "evidence_type": "audit_physical_verification",
     "as_at": "2025-07",
     "finding_id": "audit-2024-25-23",
     "summary": "Physical inspection July 2025: Ligose borehole non-operational (vandalism); Ligala has leaking pipes and corroded tank supports.",
     "confidence": 3
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Built, but neither borehole works as intended; no source states completion."
  },
  {
   "id": "SIA-P-040",
   "name": "Drilling and equipping of a borehole at Yenga",
   "aliases": [],
   "sector": "water_sanitation",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Yenga",
      "doc_id": "audit-2024-25",
      "page": 56,
      "unresolved_reason": "a place name that is not a ward or constituency"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Yenga",
      "reason": "a place name that is not a ward or constituency"
     }
    ]
   },
   "amounts": [],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": "FY 2024/25",
    "start": null,
    "expected_completion": null
   },
   "status": "unknown",
   "status_source": {
    "doc_id": "audit-2024-25",
    "page": 56,
    "evidence_type": "audit_physical_verification",
    "as_at": "2025-10"
   },
   "last_evidence_date": "2025-10",
   "audit_finding_ids": [
    "audit-2024-25-23"
   ],
   "evidence": [
    {
     "doc_id": "audit-2024-25",
     "page": 56,
     "evidence_type": "audit_physical_verification",
     "as_at": "2025-10",
     "finding_id": "audit-2024-25-23",
     "summary": "Physical verification October 2025: not functional (no flow from the elevated tank); poor paint on the tank supports.",
     "confidence": 3
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "No contract sum printed for this borehole."
  },
  {
   "id": "SIA-P-041",
   "name": "Supply, installation, configuration, customisation, testing, commissioning and support of an Enterprise Resource Planning (ERP) management information system",
   "aliases": [
    {
     "name": "Supply, Installation, Configuration, Customisation, testing, commissioning and support of Enterprise Resource ERP",
     "doc_id": "cob-report-2021-22",
     "page": 413
    }
   ],
   "sector": "ict",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Siaya Head-quarters",
      "doc_id": "cob-report-2021-22",
      "page": 413,
      "unresolved_reason": "the county headquarters, not a ward"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Siaya Head-quarters",
      "reason": "the county headquarters, not a ward"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 72420000,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "cob-report-2021-22",
     "page": 413,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "paid_cumulative",
     "value": 10000000,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "cob-report-2021-22",
     "page": 413,
     "label_as_printed": "Amount paid to date"
    },
    {
     "kind": "paid_cumulative",
     "value": 21600000,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "audit-2021-22",
     "page": 51,
     "label_as_printed": "paid"
    },
    {
     "kind": "contract_sum",
     "value": 72420000,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "audit-2022-23",
     "page": 49,
     "label_as_printed": "contract sum"
    },
    {
     "kind": "paid_cumulative",
     "value": 28000000,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "audit-2022-23",
     "page": 49,
     "label_as_printed": "paid as at June 2023",
     "as_at": "2023-06"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": "2021-08-10",
    "start": null,
    "expected_completion": "2021-11 (16 weeks)"
   },
   "status": "delayed",
   "status_source": {
    "doc_id": "audit-2022-23",
    "page": 49,
    "evidence_type": "audit_documentary_review",
    "as_at": "2023"
   },
   "last_evidence_date": "2023",
   "audit_finding_ids": [
    "audit-2021-22-25",
    "audit-2022-23-23"
   ],
   "evidence": [
    {
     "doc_id": "cob-report-2021-22",
     "page": 413,
     "evidence_type": "cob_report_county_data",
     "as_at": "2022-06-30",
     "finding_id": null,
     "summary": "County: 20%, \"Project still ongoing\".",
     "confidence": 3,
     "reported_completion_pct": 20
    },
    {
     "doc_id": "audit-2021-22",
     "page": 51,
     "evidence_type": "audit_documentary_review",
     "as_at": "2022",
     "finding_id": "audit-2021-22-25",
     "summary": "Still in development 14 months after the contract.",
     "confidence": 4
    },
    {
     "doc_id": "audit-2022-23",
     "page": 49,
     "evidence_type": "audit_documentary_review",
     "as_at": "2023",
     "finding_id": "audit-2022-23-23",
     "summary": "Interviews with ICT staff: still under development 24 months after signing.",
     "confidence": 4
    }
   ],
   "conflicts": [
    {
     "field": "paid",
     "note": "CoB FY 2021/22 KSh 10,000,000 paid to date against the FY 2021/22 audit KSh 21,600,000."
    }
   ],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-042",
   "name": "Drilling and equipping of boreholes and construction of water kiosks in the ward offices",
   "aliases": [
    {
     "name": "Geo-survey, Drilling and equipping of Boreholes in 30 wards",
     "doc_id": "cob-report-2021-22",
     "page": 412
    },
    {
     "name": "Geo-Survey, Drilling and Equipping of Boreholes in the 30 Ward Offices",
     "doc_id": "cob-report-2022-23",
     "page": 581
    }
   ],
   "sector": "water_sanitation",
   "implementing_entity": "county_assembly",
   "location": {
    "as_printed": [
     {
      "text": "County wide",
      "doc_id": "cob-report-2021-22",
      "page": 412,
      "unresolved_reason": "countywide (all ward offices)"
     },
     {
      "text": "All Wards",
      "doc_id": "cob-report-2022-23",
      "page": 581,
      "unresolved_reason": "countywide (all ward offices)"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": true,
    "unresolved": [
     {
      "text": "County wide",
      "reason": "countywide (all ward offices)"
     },
     {
      "text": "All Wards",
      "reason": "countywide (all ward offices)"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 80730095,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "cob-report-2021-22",
     "page": 412,
     "label_as_printed": "Contract sum (OCR \"80,730,09s\")",
     "note": "last digit read from OCR"
    },
    {
     "kind": "paid_cumulative",
     "value": 19066450,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "cob-report-2021-22",
     "page": 412,
     "label_as_printed": "Amount paid to date (OCR \"r9,066,450\")"
    },
    {
     "kind": "contract_sum",
     "value": 125662548,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "cob-report-2022-23",
     "page": 581,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "approved_budget",
     "value": 63558814,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "cob-report-2022-23",
     "page": 581,
     "label_as_printed": "Budget"
    },
    {
     "kind": "paid_cumulative",
     "value": 64836353,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "cob-report-2022-23",
     "page": 581,
     "label_as_printed": "Amount paid to date"
    },
    {
     "kind": "contract_sum",
     "value": 117133552,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "audit-asm-2022-23",
     "page": 54,
     "label_as_printed": "contract sum (28 ward offices)"
    },
    {
     "kind": "paid_cumulative",
     "value": 64836353,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "audit-asm-2022-23",
     "page": 54,
     "label_as_printed": "payments made"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": "2020-10-15",
    "start": null,
    "expected_completion": "2021-07-10 (extended to May 2022)"
   },
   "status": "suspended",
   "status_source": {
    "doc_id": "audit-asm-2023-24",
    "page": 56,
    "evidence_type": "audit_physical_verification",
    "as_at": "2024-09"
   },
   "last_evidence_date": "2024-09",
   "audit_finding_ids": [
    "audit-asm-2022-23-06",
    "audit-asm-2023-24-06"
   ],
   "evidence": [
    {
     "doc_id": "cob-report-2021-22",
     "page": 412,
     "evidence_type": "cob_report_county_data",
     "as_at": "2022-06-30",
     "finding_id": null,
     "summary": "County: 50%, \"Projects still ongoing\".",
     "confidence": 3,
     "reported_completion_pct": 50
    },
    {
     "doc_id": "cob-report-2022-23",
     "page": 581,
     "evidence_type": "cob_report_county_data",
     "as_at": "2023-06-30",
     "finding_id": null,
     "summary": "County: 51.6%.",
     "confidence": 4,
     "reported_completion_pct": 51.6
    },
    {
     "doc_id": "audit-asm-2022-23",
     "page": 54,
     "evidence_type": "audit_documentary_review",
     "as_at": "2023-11",
     "finding_id": "audit-asm-2022-23-06",
     "summary": "Still incomplete at the audit in November 2023 after extension to May 2022.",
     "confidence": 4
    },
    {
     "doc_id": "audit-asm-2023-24",
     "page": 56,
     "evidence_type": "audit_physical_verification",
     "as_at": "2024-09",
     "finding_id": "audit-asm-2023-24-06",
     "summary": "Field verification September 2024: projects stalled; water kiosks completed but unlabelled.",
     "confidence": 4
    }
   ],
   "conflicts": [
    {
     "field": "contract_sum",
     "note": "KSh 80,730,095 (CoB 2021/22), 125,662,548 (CoB 2022/23) and 117,133,552 (audit). The audit counts 28 ward offices, the CoB tables 30."
    }
   ],
   "related_project_ids": [
    "SIA-P-043"
   ]
  },
  {
   "id": "SIA-P-043",
   "name": "Construction of meeting halls in the ward offices",
   "aliases": [
    {
     "name": "Construction of meeting Halls in 30 ward offices",
     "doc_id": "cob-report-2021-22",
     "page": 412
    }
   ],
   "sector": "governance_offices",
   "implementing_entity": "county_assembly",
   "location": {
    "as_printed": [
     {
      "text": "County wide",
      "doc_id": "cob-report-2021-22",
      "page": 412,
      "unresolved_reason": "countywide (all ward offices)"
     },
     {
      "text": "All Wards",
      "doc_id": "cob-report-2022-23",
      "page": 581,
      "unresolved_reason": "countywide (all ward offices)"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": true,
    "unresolved": [
     {
      "text": "County wide",
      "reason": "countywide (all ward offices)"
     },
     {
      "text": "All Wards",
      "reason": "countywide (all ward offices)"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 65000000,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "cob-report-2021-22",
     "page": 412,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "paid_cumulative",
     "value": 15099708,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "cob-report-2021-22",
     "page": 412,
     "label_as_printed": "Amount paid to date"
    },
    {
     "kind": "contract_sum",
     "value": 149913785,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "cob-report-2022-23",
     "page": 581,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "approved_budget",
     "value": 104900292,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "cob-report-2022-23",
     "page": 581,
     "label_as_printed": "Budget"
    },
    {
     "kind": "paid_cumulative",
     "value": 90168197,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "cob-report-2022-23",
     "page": 581,
     "label_as_printed": "Amount paid to date"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": "2023-06-01 (audit)",
    "start": null,
    "expected_completion": "2023-12-31 after extension (audit)"
   },
   "status": "suspended",
   "status_source": {
    "doc_id": "audit-asm-2023-24",
    "page": 56,
    "evidence_type": "audit_physical_verification",
    "as_at": "2024-09"
   },
   "last_evidence_date": "2024-09",
   "audit_finding_ids": [
    "audit-asm-2023-24-06"
   ],
   "evidence": [
    {
     "doc_id": "cob-report-2021-22",
     "page": 412,
     "evidence_type": "cob_report_county_data",
     "as_at": "2022-06-30",
     "finding_id": null,
     "summary": "County: 30%, ongoing.",
     "confidence": 3,
     "reported_completion_pct": 30
    },
    {
     "doc_id": "cob-report-2022-23",
     "page": 581,
     "evidence_type": "cob_report_county_data",
     "as_at": "2023-06-30",
     "finding_id": null,
     "summary": "County: 60.1%.",
     "confidence": 4,
     "reported_completion_pct": 60.1
    },
    {
     "doc_id": "audit-asm-2023-24",
     "page": 56,
     "evidence_type": "audit_physical_verification",
     "as_at": "2024-09",
     "finding_id": "audit-asm-2023-24-06",
     "summary": "Notices issued to contractors 23 May 2024 over the quality of works; field verification September 2024: stalled.",
     "confidence": 4
    }
   ],
   "conflicts": [
    {
     "field": "contract.signed",
     "note": "The audit dates the meeting-hall contracts 1 June 2023, but CoB tables show payments for meeting halls in FY 2021/22 and FY 2022/23."
    }
   ],
   "related_project_ids": [
    "SIA-P-042",
    "SIA-P-044"
   ]
  },
  {
   "id": "SIA-P-044",
   "name": "Construction and Fencing of Ward Offices",
   "aliases": [
    {
     "name": "Construction and Fencing of 30 Ward Offices",
     "doc_id": "cob-report-2021-22",
     "page": 412
    },
    {
     "name": "Construction and fencing of ward offices",
     "doc_id": "cob-report-2023-24",
     "page": 516
    }
   ],
   "sector": "governance_offices",
   "implementing_entity": "county_assembly",
   "location": {
    "as_printed": [
     {
      "text": "County wide",
      "doc_id": "cob-report-2021-22",
      "page": 412,
      "unresolved_reason": "countywide"
     },
     {
      "text": "All Wards",
      "doc_id": "cob-report-2022-23",
      "page": 580,
      "unresolved_reason": "countywide"
     },
     {
      "text": "Ward HQs",
      "doc_id": "cob-report-2023-24",
      "page": 516,
      "unresolved_reason": "countywide (ward headquarters)"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": true,
    "unresolved": [
     {
      "text": "County wide",
      "reason": "countywide"
     },
     {
      "text": "All Wards",
      "reason": "countywide"
     },
     {
      "text": "Ward HQs",
      "reason": "countywide (ward headquarters)"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 57934334,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "cob-report-2021-22",
     "page": 412,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "paid_cumulative",
     "value": 19205163,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "cob-report-2021-22",
     "page": 412,
     "label_as_printed": "Amount paid to date"
    },
    {
     "kind": "contract_sum",
     "value": 160167929,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "cob-report-2022-23",
     "page": 580,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "approved_budget",
     "value": 34759153,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "cob-report-2022-23",
     "page": 580,
     "label_as_printed": "Budget"
    },
    {
     "kind": "paid_cumulative",
     "value": 124001160,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "cob-report-2022-23",
     "page": 580,
     "label_as_printed": "Amount paid to date"
    },
    {
     "kind": "contract_sum",
     "value": 160167929,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "paid_cumulative",
     "value": 125408776,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "label_as_printed": "Amount paid to date"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "active",
   "status_source": {
    "doc_id": "cob-report-2023-24",
    "page": 516,
    "evidence_type": "cob_report_county_data",
    "as_at": "2024-06-30"
   },
   "last_evidence_date": "2024-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2021-22",
     "page": 412,
     "evidence_type": "cob_report_county_data",
     "as_at": "2022-06-30",
     "finding_id": null,
     "summary": "County: 50%, ongoing.",
     "confidence": 3,
     "reported_completion_pct": 50
    },
    {
     "doc_id": "cob-report-2022-23",
     "page": 580,
     "evidence_type": "cob_report_county_data",
     "as_at": "2023-06-30",
     "finding_id": null,
     "summary": "County: 77.4%.",
     "confidence": 4,
     "reported_completion_pct": 77.4
    },
    {
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "evidence_type": "cob_report_county_data",
     "as_at": "2024-06-30",
     "finding_id": null,
     "summary": "County: 78.3%.",
     "confidence": 3,
     "reported_completion_pct": 78.3
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Last reported at 78.3% (30 June 2024); no later source."
  },
  {
   "id": "SIA-P-045",
   "name": "Networking of Ward offices",
   "aliases": [],
   "sector": "ict",
   "implementing_entity": "county_assembly",
   "location": {
    "as_printed": [
     {
      "text": "Ward HQs",
      "doc_id": "cob-report-2023-24",
      "page": 516,
      "unresolved_reason": "countywide (ward headquarters)"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": true,
    "unresolved": [
     {
      "text": "Ward HQs",
      "reason": "countywide (ward headquarters)"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 102183608,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "paid_cumulative",
     "value": 100520437,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "label_as_printed": "Amount paid to date"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "active",
   "status_source": {
    "doc_id": "cob-report-2023-24",
    "page": 516,
    "evidence_type": "cob_report_county_data",
    "as_at": "2024-06-30"
   },
   "last_evidence_date": "2024-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "evidence_type": "cob_report_county_data",
     "as_at": "2024-06-30",
     "finding_id": null,
     "summary": "County: 98.4%.",
     "confidence": 3,
     "reported_completion_pct": 98.4
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-046",
   "name": "Acquisition, Supervision and Installation of Hansard and Information Technology System Infrastructure and Equipment Development",
   "aliases": [
    {
     "name": "Acquisition, Supervision and Installation of Hansard ICT System Infrastructure and Equipment Development (E-Business)",
     "doc_id": "cob-report-2021-22",
     "page": 412
    }
   ],
   "sector": "ict",
   "implementing_entity": "county_assembly",
   "location": {
    "as_printed": [
     {
      "text": "County Assembly Chambers",
      "doc_id": "cob-report-2018-19",
      "page": 272,
      "unresolved_reason": "a building, not a ward"
     },
     {
      "text": "County Assembly Head-quarters",
      "doc_id": "cob-report-2021-22",
      "page": 412,
      "unresolved_reason": "a building, not a ward"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "County Assembly Chambers",
      "reason": "a building, not a ward"
     },
     {
      "text": "County Assembly Head-quarters",
      "reason": "a building, not a ward"
     }
    ]
   },
   "amounts": [
    {
     "kind": "approved_budget",
     "value": 60735050,
     "unit": "KSh",
     "fy": "2018/19",
     "doc_id": "cob-report-2018-19",
     "page": 272,
     "label_as_printed": "Project Budget"
    },
    {
     "kind": "expenditure_in_fy",
     "value": 32897056,
     "unit": "KSh",
     "fy": "2018/19",
     "doc_id": "cob-report-2018-19",
     "page": 272,
     "label_as_printed": "Project Expenditure"
    },
    {
     "kind": "contract_sum",
     "value": 14564983,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "cob-report-2021-22",
     "page": 412,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "paid_cumulative",
     "value": 14564983,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "cob-report-2021-22",
     "page": 412,
     "label_as_printed": "Amount paid to date"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "completed-reported",
   "status_source": {
    "doc_id": "cob-report-2021-22",
    "page": 412,
    "evidence_type": "cob_report_county_data",
    "as_at": "2022-06-30"
   },
   "last_evidence_date": "2022-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2018-19",
     "page": 272,
     "evidence_type": "cob_report_county_data",
     "as_at": "2019-06-30",
     "finding_id": null,
     "summary": "54.2% absorption of the project budget.",
     "confidence": 5
    },
    {
     "doc_id": "cob-report-2021-22",
     "page": 412,
     "evidence_type": "cob_report_county_data",
     "as_at": "2022-06-30",
     "finding_id": null,
     "summary": "County: 100%, \"Project completed and in use\".",
     "confidence": 3,
     "reported_completion_pct": 100
    }
   ],
   "conflicts": [
    {
     "field": "amount",
     "note": "FY 2018/19 budget KSh 60,735,050 against a FY 2021/22 contract sum of KSh 14,564,983; may be separate phases."
    }
   ],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-047",
   "name": "Development, Installation and Commissioning of Asset Inventory and fleet Management System",
   "aliases": [],
   "sector": "ict",
   "implementing_entity": "county_assembly",
   "location": {
    "as_printed": [
     {
      "text": "County Assembly Head-quarters",
      "doc_id": "cob-report-2021-22",
      "page": 412,
      "unresolved_reason": "a building, not a ward"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "County Assembly Head-quarters",
      "reason": "a building, not a ward"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 12850000,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "cob-report-2021-22",
     "page": 412,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "paid_cumulative",
     "value": 12260000,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "cob-report-2021-22",
     "page": 412,
     "label_as_printed": "Amount paid to date"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "completed-reported",
   "status_source": {
    "doc_id": "cob-report-2021-22",
    "page": 412,
    "evidence_type": "cob_report_county_data",
    "as_at": "2022-06-30"
   },
   "last_evidence_date": "2022-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2021-22",
     "page": 412,
     "evidence_type": "cob_report_county_data",
     "as_at": "2022-06-30",
     "finding_id": null,
     "summary": "County: 100%, \"Project complete and in use\".",
     "confidence": 3,
     "reported_completion_pct": 100
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-048",
   "name": "Development, Supply, Installation and Commissioning of Virtual Conference Boardrooms",
   "aliases": [],
   "sector": "ict",
   "implementing_entity": "county_assembly",
   "location": {
    "as_printed": [
     {
      "text": "County Assembly Head-quarters",
      "doc_id": "cob-report-2021-22",
      "page": 412,
      "unresolved_reason": "a building, not a ward"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "County Assembly Head-quarters",
      "reason": "a building, not a ward"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 14792974,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "cob-report-2021-22",
     "page": 412,
     "label_as_printed": "Contract sum (OCR \"r4,792,974\")"
    },
    {
     "kind": "paid_cumulative",
     "value": 11476177,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "cob-report-2021-22",
     "page": 412,
     "label_as_printed": "Amount paid to date (OCR \"tt,476,177\")"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "active",
   "status_source": {
    "doc_id": "cob-report-2021-22",
    "page": 412,
    "evidence_type": "cob_report_county_data",
    "as_at": "2022-06-30"
   },
   "last_evidence_date": "2022-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2021-22",
     "page": 412,
     "evidence_type": "cob_report_county_data",
     "as_at": "2022-06-30",
     "finding_id": null,
     "summary": "County: 70%, \"Project still ongoing\".",
     "confidence": 3,
     "reported_completion_pct": 70
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Last reported June 2022; no later source."
  },
  {
   "id": "SIA-P-049",
   "name": "Construction of modern market at Sigomere",
   "aliases": [],
   "sector": "markets_trade",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Sigomere ward",
      "doc_id": "cob-report-2021-22",
      "page": 412,
      "resolved_to": [
       {
        "ward_id": "sigomere"
       }
      ]
     }
    ],
    "ward_ids": [
     "sigomere"
    ],
    "constituency_ids": [
     "ugunja"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 17450085,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "cob-report-2021-22",
     "page": 412,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "approved_budget",
     "value": 4800000,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "cob-report-2021-22",
     "page": 412,
     "label_as_printed": "Budget"
    },
    {
     "kind": "paid_cumulative",
     "value": 11765952,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "cob-report-2021-22",
     "page": 412,
     "label_as_printed": "Amount paid to date (OCR \"t1,765,952\")"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "active",
   "status_source": {
    "doc_id": "cob-report-2021-22",
    "page": 412,
    "evidence_type": "cob_report_county_data",
    "as_at": "2022-06-30"
   },
   "last_evidence_date": "2022-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2021-22",
     "page": 412,
     "evidence_type": "cob_report_county_data",
     "as_at": "2022-06-30",
     "finding_id": null,
     "summary": "County: 80%, \"Project still ongoing\".",
     "confidence": 3,
     "reported_completion_pct": 80
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Last reported June 2022."
  },
  {
   "id": "SIA-P-050",
   "name": "Installation of High masts lighting in Siaya County",
   "aliases": [],
   "sector": "energy_lighting",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Siaya Head-quarters",
      "doc_id": "cob-report-2021-22",
      "page": 411,
      "unresolved_reason": "the county headquarters, not a ward"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Siaya Head-quarters",
      "reason": "the county headquarters, not a ward"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 59865960,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "cob-report-2021-22",
     "page": 411,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "paid_cumulative",
     "value": 25105080,
     "unit": "KSh",
     "fy": "2021/22",
     "doc_id": "cob-report-2021-22",
     "page": 411,
     "label_as_printed": "Amount paid to date (OCR \"25, I 05,080\")"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "active",
   "status_source": {
    "doc_id": "cob-report-2021-22",
    "page": 411,
    "evidence_type": "cob_report_county_data",
    "as_at": "2022-06-30"
   },
   "last_evidence_date": "2022-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2021-22",
     "page": 411,
     "evidence_type": "cob_report_county_data",
     "as_at": "2022-06-30",
     "finding_id": null,
     "summary": "County: 70%, \"Projects still ongoing\".",
     "confidence": 3,
     "reported_completion_pct": 70
    }
   ],
   "conflicts": [],
   "related_project_ids": [
    "SIA-P-051"
   ]
  },
  {
   "id": "SIA-P-051",
   "name": "Installation of High mast lights in various locations in Siaya County",
   "aliases": [],
   "sector": "energy_lighting",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Executive",
      "doc_id": "cob-report-2024-25",
      "page": 483,
      "unresolved_reason": "location column reads \"Executive\" (the implementing office), so no place is stated"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Executive",
      "reason": "location column reads \"Executive\" (the implementing office), so no place is stated"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 179009460,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "paid_in_fy",
     "value": 66241800,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "label_as_printed": "Amount paid in FY 2024/25"
    },
    {
     "kind": "paid_cumulative",
     "value": 132452280,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "label_as_printed": "Cumulative expenditure as of 30 June 2025"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": "2022-09-30"
   },
   "status": "delayed",
   "status_source": {
    "doc_id": "cob-report-2024-25",
    "page": 483,
    "evidence_type": "cob_report_county_data",
    "as_at": "2025-06-30"
   },
   "last_evidence_date": "2025-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "evidence_type": "cob_report_county_data",
     "as_at": "2025-06-30",
     "finding_id": null,
     "summary": "County: 65% against an expected completion of 30 Sep 2022.",
     "confidence": 4,
     "reported_completion_pct": 65
    }
   ],
   "conflicts": [],
   "related_project_ids": [
    "SIA-P-050"
   ],
   "status_note": "Delayed on the county's own dates. May be the same programme as the FY 2021/22 high-mast entry; not merged because the contract sums differ."
  },
  {
   "id": "SIA-P-052",
   "name": "Supply, Installation, and Maintenance of the Integrated Revenue Management System for the County Government of Siaya",
   "aliases": [],
   "sector": "ict",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Alego Usonga H/Q",
      "doc_id": "cob-report-2024-25",
      "page": 483,
      "resolved_to": [
       {
        "constituency_id": "alego-usonga"
       }
      ]
     }
    ],
    "ward_ids": [],
    "constituency_ids": [
     "alego-usonga"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 50914550.92,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "paid_cumulative",
     "value": 24986440,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "label_as_printed": "Cumulative expenditure as of 30 June 2025"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": "2026-03-20"
   },
   "status": "active",
   "status_source": {
    "doc_id": "cob-report-2024-25",
    "page": 483,
    "evidence_type": "cob_report_county_data",
    "as_at": "2025-06-30"
   },
   "last_evidence_date": "2025-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "evidence_type": "cob_report_county_data",
     "as_at": "2025-06-30",
     "finding_id": null,
     "summary": "County: 95%.",
     "confidence": 4,
     "reported_completion_pct": 95
    }
   ],
   "conflicts": [],
   "related_project_ids": [
    "SIA-P-076"
   ]
  },
  {
   "id": "SIA-P-053",
   "name": "Promotion of agro-processing rice (Installation of Siriwo rice mill)",
   "aliases": [],
   "sector": "agriculture_fisheries",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Executive",
      "doc_id": "cob-report-2024-25",
      "page": 483,
      "unresolved_reason": "location column reads \"Executive\" (the implementing office), so no place is stated"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Executive",
      "reason": "location column reads \"Executive\" (the implementing office), so no place is stated"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 31020000.05,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "paid_cumulative",
     "value": 31020000.05,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "label_as_printed": "Cumulative expenditure as of 30 June 2025"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": "2024-11-11"
   },
   "status": "completed-reported",
   "status_source": {
    "doc_id": "cob-report-2024-25",
    "page": 483,
    "evidence_type": "cob_report_county_data",
    "as_at": "2025-06-30"
   },
   "last_evidence_date": "2025-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "evidence_type": "cob_report_county_data",
     "as_at": "2025-06-30",
     "finding_id": null,
     "summary": "County: 100%.",
     "confidence": 4,
     "reported_completion_pct": 100
    }
   ],
   "conflicts": [],
   "related_project_ids": [
    "SIA-P-054",
    "SIA-P-071"
   ]
  },
  {
   "id": "SIA-P-054",
   "name": "Construction of rice milling plant",
   "aliases": [],
   "sector": "agriculture_fisheries",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Siriwo",
      "doc_id": "cob-report-2023-24",
      "page": 516,
      "unresolved_reason": "a place name that is not a ward or constituency"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Siriwo",
      "reason": "a place name that is not a ward or constituency"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 47721373,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "paid_cumulative",
     "value": 40000000,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "label_as_printed": "Amount paid to date"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "active",
   "status_source": {
    "doc_id": "cob-report-2023-24",
    "page": 516,
    "evidence_type": "cob_report_county_data",
    "as_at": "2024-06-30"
   },
   "last_evidence_date": "2024-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "evidence_type": "cob_report_county_data",
     "as_at": "2024-06-30",
     "finding_id": null,
     "summary": "County: 83%. Row partly illegible; name from the low-resolution OCR.",
     "confidence": 2,
     "reported_completion_pct": 83
    }
   ],
   "conflicts": [],
   "related_project_ids": [
    "SIA-P-053"
   ]
  },
  {
   "id": "SIA-P-055",
   "name": "Upgrade to bitumen standard. Rabango - Siaya Township School Road",
   "aliases": [],
   "sector": "roads_transport",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Rabango -Siaya Township School Road.",
      "doc_id": "cob-report-2023-24",
      "page": 516,
      "unresolved_reason": "a road name; \"Siaya Township\" here names a school, not the ward"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Rabango -Siaya Township School Road.",
      "reason": "a road name; \"Siaya Township\" here names a school, not the ward"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 52542620,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "paid_cumulative",
     "value": 50000000,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "label_as_printed": "Amount paid to date"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "active",
   "status_source": {
    "doc_id": "cob-report-2023-24",
    "page": 516,
    "evidence_type": "cob_report_county_data",
    "as_at": "2024-06-30"
   },
   "last_evidence_date": "2024-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "evidence_type": "cob_report_county_data",
     "as_at": "2024-06-30",
     "finding_id": null,
     "summary": "County: 90%.",
     "confidence": 3,
     "reported_completion_pct": 90
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-056",
   "name": "Upgrade to bitumen standard. Yala ring road",
   "aliases": [],
   "sector": "roads_transport",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Yala ring road (OCR \"rind\")",
      "doc_id": "cob-report-2023-24",
      "page": 516,
      "unresolved_reason": "a road name; Yala town lies across wards"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Yala ring road (OCR \"rind\")",
      "reason": "a road name; Yala town lies across wards"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 26900000,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "paid_cumulative",
     "value": 39850732,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "label_as_printed": "Amount paid to date (above the contract sum, as printed)"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "completed-reported",
   "status_source": {
    "doc_id": "cob-report-2023-24",
    "page": 516,
    "evidence_type": "cob_report_county_data",
    "as_at": "2024-06-30"
   },
   "last_evidence_date": "2024-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "evidence_type": "cob_report_county_data",
     "as_at": "2024-06-30",
     "finding_id": null,
     "summary": "County: 100%.",
     "confidence": 3,
     "reported_completion_pct": 100
    }
   ],
   "conflicts": [
    {
     "field": "amount",
     "note": "Amount paid (KSh 39,850,732) exceeds the contract sum (KSh 26,900,000) as printed."
    }
   ],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-057",
   "name": "Purchase of land for bus park",
   "aliases": [],
   "sector": "roads_transport",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Ugunja",
      "doc_id": "cob-report-2023-24",
      "page": 516,
      "resolved_to": [
       {
        "constituency_id": "ugunja"
       }
      ],
      "unresolved_reason": "\"Ugunja\" is both a ward and a constituency; resolved to the constituency only"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [
     "ugunja"
    ],
    "countywide": false,
    "unresolved": [
     {
      "text": "Ugunja",
      "reason": "\"Ugunja\" is both a ward and a constituency; resolved to the constituency only"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 23000000,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "paid_cumulative",
     "value": 15000000,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "label_as_printed": "Amount paid to date"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "completed-reported",
   "status_source": {
    "doc_id": "cob-report-2023-24",
    "page": 516,
    "evidence_type": "cob_report_county_data",
    "as_at": "2024-06-30"
   },
   "last_evidence_date": "2024-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "evidence_type": "cob_report_county_data",
     "as_at": "2024-06-30",
     "finding_id": null,
     "summary": "County: 100%.",
     "confidence": 3,
     "reported_completion_pct": 100
    }
   ],
   "conflicts": [
    {
     "field": "amount",
     "note": "100% reported with KSh 15,000,000 of KSh 23,000,000 paid."
    }
   ],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-058",
   "name": "Refrigeration at Siaya Referral Morgue (48-body capacity refrigeration machine)",
   "aliases": [
    {
     "name": "48 body refrigeration machine (Siaya and Bondo hospital morgues)",
     "doc_id": "cob-report-2023-24",
     "page": 516
    }
   ],
   "sector": "health",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Siaya Municipality",
      "doc_id": "cob-report-2022-23",
      "page": 581,
      "unresolved_reason": "a municipality, not a ward or constituency"
     },
     {
      "text": "Siaya and Bondo hospital morgues",
      "doc_id": "cob-report-2023-24",
      "page": 516,
      "resolved_to": [
       {
        "constituency_id": "bondo"
       }
      ],
      "unresolved_reason": "Siaya part: \"Siaya\" can mean the county, Siaya town or the Siaya/Alego Usonga sub-county; not resolved"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [
     "bondo"
    ],
    "countywide": false,
    "unresolved": [
     {
      "text": "Siaya Municipality",
      "reason": "a municipality, not a ward or constituency"
     },
     {
      "text": "Siaya and Bondo hospital morgues",
      "reason": "Siaya part: \"Siaya\" can mean the county, Siaya town or the Siaya/Alego Usonga sub-county; not resolved"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 50227989.24,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "cob-report-2022-23",
     "page": 581,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "approved_budget",
     "value": 50000000,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "cob-report-2022-23",
     "page": 581,
     "label_as_printed": "Budget"
    },
    {
     "kind": "paid_cumulative",
     "value": 35159593,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "cob-report-2022-23",
     "page": 581,
     "label_as_printed": "Amount paid to date (OCR \"35,r59,593\")"
    },
    {
     "kind": "contract_sum",
     "value": 50227989,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "paid_cumulative",
     "value": 47659593,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "label_as_printed": "Amount paid to date"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "completed-reported",
   "status_source": {
    "doc_id": "cob-report-2023-24",
    "page": 516,
    "evidence_type": "cob_report_county_data",
    "as_at": "2024-06-30"
   },
   "last_evidence_date": "2024-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2022-23",
     "page": 581,
     "evidence_type": "cob_report_county_data",
     "as_at": "2023-06-30",
     "finding_id": null,
     "summary": "County: 70%.",
     "confidence": 3,
     "reported_completion_pct": 70
    },
    {
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "evidence_type": "cob_report_county_data",
     "as_at": "2024-06-30",
     "finding_id": null,
     "summary": "County: 100%.",
     "confidence": 3,
     "reported_completion_pct": 100
    }
   ],
   "conflicts": [
    {
     "field": "location",
     "note": "FY 2022/23 names the Siaya Referral morgue only; FY 2023/24 names Siaya and Bondo hospital morgues with the same contract sum."
    }
   ],
   "related_project_ids": [
    "SIA-P-036"
   ]
  },
  {
   "id": "SIA-P-059",
   "name": "Construction of Abura Dam",
   "aliases": [],
   "sector": "water_sanitation",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "not stated",
      "doc_id": "cob-report-2022-23",
      "page": 581,
      "unresolved_reason": "location cell blank"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "not stated",
      "reason": "location cell blank"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 44044800,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "cob-report-2022-23",
     "page": 581,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "approved_budget",
     "value": 44620240,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "cob-report-2022-23",
     "page": 581,
     "label_as_printed": "Budget"
    },
    {
     "kind": "paid_cumulative",
     "value": 44044800,
     "unit": "KSh",
     "fy": "2022/23",
     "doc_id": "cob-report-2022-23",
     "page": 581,
     "label_as_printed": "Amount paid to date"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "completed-reported",
   "status_source": {
    "doc_id": "cob-report-2022-23",
    "page": 581,
    "evidence_type": "cob_report_county_data",
    "as_at": "2023-06-30"
   },
   "last_evidence_date": "2023-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2022-23",
     "page": 581,
     "evidence_type": "cob_report_county_data",
     "as_at": "2023-06-30",
     "finding_id": null,
     "summary": "County: 100%.",
     "confidence": 4,
     "reported_completion_pct": 100
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-060",
   "name": "Completion of Randago VTC",
   "aliases": [],
   "sector": "education",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Randago",
      "doc_id": "cob-report-2023-24",
      "page": 516,
      "unresolved_reason": "a place name that is not a ward or constituency"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Randago",
      "reason": "a place name that is not a ward or constituency"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 3293368,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "paid_cumulative",
     "value": 3293368,
     "unit": "KSh",
     "fy": "2023/24",
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "label_as_printed": "Amount paid to date"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "completed-reported",
   "status_source": {
    "doc_id": "cob-report-2023-24",
    "page": 516,
    "evidence_type": "cob_report_county_data",
    "as_at": "2024-06-30"
   },
   "last_evidence_date": "2024-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2023-24",
     "page": 516,
     "evidence_type": "cob_report_county_data",
     "as_at": "2024-06-30",
     "finding_id": null,
     "summary": "County: 100% (OCR \"vompiction of Randago\").",
     "confidence": 3,
     "reported_completion_pct": 100
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-061",
   "name": "Construction of bus park at Bondo",
   "aliases": [],
   "sector": "roads_transport",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "North Sakwa",
      "doc_id": "cob-report-2020-21",
      "page": 377,
      "resolved_to": [
       {
        "ward_id": "north-sakwa"
       }
      ]
     }
    ],
    "ward_ids": [
     "north-sakwa"
    ],
    "constituency_ids": [
     "bondo"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "approved_budget",
     "value": 28947290,
     "unit": "KSh",
     "fy": "2020/21",
     "doc_id": "cob-report-2020-21",
     "page": 377,
     "label_as_printed": "Budget"
    },
    {
     "kind": "expenditure_in_fy",
     "value": 15244220,
     "unit": "KSh",
     "fy": "2020/21",
     "doc_id": "cob-report-2020-21",
     "page": 377,
     "label_as_printed": "Expenditure (absorption 52.7%)"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "unknown",
   "status_source": {
    "doc_id": "cob-report-2020-21",
    "page": 377,
    "evidence_type": "cob_report_county_data",
    "as_at": "2021-06-30"
   },
   "last_evidence_date": "2021-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2020-21",
     "page": 377,
     "evidence_type": "cob_report_county_data",
     "as_at": "2021-06-30",
     "finding_id": null,
     "summary": "Absorption 52.7%; no completion status printed.",
     "confidence": 3
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-062",
   "name": "Equipping of Poye, Mbaga, Karapul, Uwasi, Nyamuango, Daho and Angolo Mkt",
   "aliases": [],
   "sector": "markets_trade",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Ugunja",
      "doc_id": "cob-report-2020-21",
      "page": 377,
      "resolved_to": [
       {
        "constituency_id": "ugunja"
       }
      ],
      "unresolved_reason": "\"Ugunja\" is both a ward and a constituency; resolved to the constituency only"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [
     "ugunja"
    ],
    "countywide": false,
    "unresolved": [
     {
      "text": "Ugunja",
      "reason": "\"Ugunja\" is both a ward and a constituency; resolved to the constituency only"
     }
    ]
   },
   "amounts": [
    {
     "kind": "approved_budget",
     "value": 11432917,
     "unit": "KSh",
     "fy": "2020/21",
     "doc_id": "cob-report-2020-21",
     "page": 377,
     "label_as_printed": "Budget (OCR \"11,432,9t7\")"
    },
    {
     "kind": "expenditure_in_fy",
     "value": 11432917,
     "unit": "KSh",
     "fy": "2020/21",
     "doc_id": "cob-report-2020-21",
     "page": 377,
     "label_as_printed": "Expenditure (absorption 100%)"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "unknown",
   "status_source": {
    "doc_id": "cob-report-2020-21",
    "page": 377,
    "evidence_type": "cob_report_county_data",
    "as_at": "2021-06-30"
   },
   "last_evidence_date": "2021-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2020-21",
     "page": 377,
     "evidence_type": "cob_report_county_data",
     "as_at": "2021-06-30",
     "finding_id": null,
     "summary": "Absorption 100% of the budget; no completion status printed.",
     "confidence": 3
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-063",
   "name": "Drilling of boreholes at Ochienga, Kobonyo, Okela, Bonde, Dhere, Utonga & Kanyichudo",
   "aliases": [],
   "sector": "water_sanitation",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Rarieda and Bondo Subs",
      "doc_id": "cob-report-2020-21",
      "page": 377,
      "resolved_to": [
       {
        "constituency_id": "rarieda"
       },
       {
        "constituency_id": "bondo"
       }
      ]
     }
    ],
    "ward_ids": [],
    "constituency_ids": [
     "rarieda",
     "bondo"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "approved_budget",
     "value": 11338862,
     "unit": "KSh",
     "fy": "2020/21",
     "doc_id": "cob-report-2020-21",
     "page": 377,
     "label_as_printed": "Budget"
    },
    {
     "kind": "expenditure_in_fy",
     "value": 11338862,
     "unit": "KSh",
     "fy": "2020/21",
     "doc_id": "cob-report-2020-21",
     "page": 377,
     "label_as_printed": "Expenditure (absorption 100%)"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "unknown",
   "status_source": {
    "doc_id": "cob-report-2020-21",
    "page": 377,
    "evidence_type": "cob_report_county_data",
    "as_at": "2021-06-30"
   },
   "last_evidence_date": "2021-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2020-21",
     "page": 377,
     "evidence_type": "cob_report_county_data",
     "as_at": "2021-06-30",
     "finding_id": null,
     "summary": "Absorption 100% of the budget; no completion status printed.",
     "confidence": 3
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-064",
   "name": "Maintenance of River Yala and Lake Kanyaboli dykes",
   "aliases": [],
   "sector": "environment",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Central Alego Ward",
      "doc_id": "cob-report-2018-19",
      "page": 272,
      "resolved_to": [
       {
        "ward_id": "central-alego"
       }
      ]
     }
    ],
    "ward_ids": [
     "central-alego"
    ],
    "constituency_ids": [
     "alego-usonga"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "approved_budget",
     "value": 20000000,
     "unit": "KSh",
     "fy": "2018/19",
     "doc_id": "cob-report-2018-19",
     "page": 272,
     "label_as_printed": "Project Budget"
    },
    {
     "kind": "expenditure_in_fy",
     "value": 19925666,
     "unit": "KSh",
     "fy": "2018/19",
     "doc_id": "cob-report-2018-19",
     "page": 272,
     "label_as_printed": "Project Expenditure"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "unknown",
   "status_source": {
    "doc_id": "cob-report-2018-19",
    "page": 272,
    "evidence_type": "cob_report_county_data",
    "as_at": "2019-06-30"
   },
   "last_evidence_date": "2019-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2018-19",
     "page": 272,
     "evidence_type": "cob_report_county_data",
     "as_at": "2019-06-30",
     "finding_id": null,
     "summary": "Absorption 99.6%; no completion status printed.",
     "confidence": 5
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-065",
   "name": "Construction of County Annex Siaya",
   "aliases": [],
   "sector": "governance_offices",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "County Headquarters",
      "doc_id": "cob-report-2018-19",
      "page": 272,
      "unresolved_reason": "the county headquarters, not a ward"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "County Headquarters",
      "reason": "the county headquarters, not a ward"
     }
    ]
   },
   "amounts": [
    {
     "kind": "approved_budget",
     "value": 35000000,
     "unit": "KSh",
     "fy": "2018/19",
     "doc_id": "cob-report-2018-19",
     "page": 272,
     "label_as_printed": "Project Budget"
    },
    {
     "kind": "expenditure_in_fy",
     "value": 11995022,
     "unit": "KSh",
     "fy": "2018/19",
     "doc_id": "cob-report-2018-19",
     "page": 272,
     "label_as_printed": "Project Expenditure"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "unknown",
   "status_source": {
    "doc_id": "cob-report-2018-19",
    "page": 272,
    "evidence_type": "cob_report_county_data",
    "as_at": "2019-06-30"
   },
   "last_evidence_date": "2019-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2018-19",
     "page": 272,
     "evidence_type": "cob_report_county_data",
     "as_at": "2019-06-30",
     "finding_id": null,
     "summary": "Absorption 34.3%; no completion status printed.",
     "confidence": 5
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-066",
   "name": "Development of East Uyoma Water Project (co-funding of the project)",
   "aliases": [],
   "sector": "water_sanitation",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "East Uyoma Ward",
      "doc_id": "cob-report-2018-19",
      "page": 272,
      "unresolved_reason": "no East Uyoma ward in the IEBC register (Rarieda has North, South and West Uyoma); left unresolved"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "East Uyoma Ward",
      "reason": "no East Uyoma ward in the IEBC register (Rarieda has North, South and West Uyoma); left unresolved"
     }
    ]
   },
   "amounts": [
    {
     "kind": "approved_budget",
     "value": 10000000,
     "unit": "KSh",
     "fy": "2018/19",
     "doc_id": "cob-report-2018-19",
     "page": 272,
     "label_as_printed": "Project Budget"
    },
    {
     "kind": "expenditure_in_fy",
     "value": 9915691,
     "unit": "KSh",
     "fy": "2018/19",
     "doc_id": "cob-report-2018-19",
     "page": 272,
     "label_as_printed": "Project Expenditure"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "unknown",
   "status_source": {
    "doc_id": "cob-report-2018-19",
    "page": 272,
    "evidence_type": "cob_report_county_data",
    "as_at": "2019-06-30"
   },
   "last_evidence_date": "2019-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2018-19",
     "page": 272,
     "evidence_type": "cob_report_county_data",
     "as_at": "2019-06-30",
     "finding_id": null,
     "summary": "Absorption 99.2%; no completion status printed.",
     "confidence": 5
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-067",
   "name": "Construction of Pap - Kodero Twin Box Culvert FL",
   "aliases": [],
   "sector": "roads_transport",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "West Uyoma Ward",
      "doc_id": "cob-report-2018-19",
      "page": 272,
      "resolved_to": [
       {
        "ward_id": "west-uyoma"
       }
      ]
     }
    ],
    "ward_ids": [
     "west-uyoma"
    ],
    "constituency_ids": [
     "rarieda"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "approved_budget",
     "value": 12119733,
     "unit": "KSh",
     "fy": "2018/19",
     "doc_id": "cob-report-2018-19",
     "page": 272,
     "label_as_printed": "Project Budget"
    },
    {
     "kind": "expenditure_in_fy",
     "value": 8954460,
     "unit": "KSh",
     "fy": "2018/19",
     "doc_id": "cob-report-2018-19",
     "page": 272,
     "label_as_printed": "Project Expenditure"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "unknown",
   "status_source": {
    "doc_id": "cob-report-2018-19",
    "page": 272,
    "evidence_type": "cob_report_county_data",
    "as_at": "2019-06-30"
   },
   "last_evidence_date": "2019-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2018-19",
     "page": 272,
     "evidence_type": "cob_report_county_data",
     "as_at": "2019-06-30",
     "finding_id": null,
     "summary": "Absorption 73.9%; no completion status printed.",
     "confidence": 5
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-068",
   "name": "Routine Maintenance Of Ndai/Kanyaboli/Kubar Pr. Sch. /Obambo Pr. Sch. Road",
   "aliases": [],
   "sector": "roads_transport",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Central Alego Ward",
      "doc_id": "cob-report-2018-19",
      "page": 272,
      "resolved_to": [
       {
        "ward_id": "central-alego"
       }
      ]
     }
    ],
    "ward_ids": [
     "central-alego"
    ],
    "constituency_ids": [
     "alego-usonga"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "approved_budget",
     "value": 8265600,
     "unit": "KSh",
     "fy": "2018/19",
     "doc_id": "cob-report-2018-19",
     "page": 272,
     "label_as_printed": "Project Budget"
    },
    {
     "kind": "expenditure_in_fy",
     "value": 8252145,
     "unit": "KSh",
     "fy": "2018/19",
     "doc_id": "cob-report-2018-19",
     "page": 272,
     "label_as_printed": "Project Expenditure"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "unknown",
   "status_source": {
    "doc_id": "cob-report-2018-19",
    "page": 272,
    "evidence_type": "cob_report_county_data",
    "as_at": "2019-06-30"
   },
   "last_evidence_date": "2019-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2018-19",
     "page": 272,
     "evidence_type": "cob_report_county_data",
     "as_at": "2019-06-30",
     "finding_id": null,
     "summary": "Absorption 99.8%; no completion status printed.",
     "confidence": 5
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-069",
   "name": "Completion of the Apuoyo animal feed pelletizing plant",
   "aliases": [],
   "sector": "agriculture_fisheries",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "West Gem",
      "doc_id": "cob-report-2024-25",
      "page": 483,
      "resolved_to": [
       {
        "ward_id": "west-gem"
       }
      ]
     }
    ],
    "ward_ids": [
     "west-gem"
    ],
    "constituency_ids": [
     "gem"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "estimated_value",
     "value": 1500000,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "label_as_printed": "Estimated Value of the Project"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "cancelled",
   "status_source": {
    "doc_id": "cob-report-2024-25",
    "page": 483,
    "evidence_type": "cob_report_county_data",
    "as_at": "2025-06-30"
   },
   "last_evidence_date": "2025-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "evidence_type": "cob_report_county_data",
     "as_at": "2025-06-30",
     "finding_id": null,
     "summary": "County stalled-projects list: \"terminated\"; 25% complete before stalling.",
     "confidence": 3,
     "reported_completion_pct": 25
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-070",
   "name": "Fencing and installation of a gate at Kokach Beach",
   "aliases": [],
   "sector": "agriculture_fisheries",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "East Asembo",
      "doc_id": "cob-report-2024-25",
      "page": 483,
      "resolved_to": [
       {
        "ward_id": "east-asembo"
       }
      ]
     }
    ],
    "ward_ids": [
     "east-asembo"
    ],
    "constituency_ids": [
     "rarieda"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "suspended",
   "status_source": {
    "doc_id": "cob-report-2024-25",
    "page": 483,
    "evidence_type": "cob_report_county_data",
    "as_at": "2025-06-30"
   },
   "last_evidence_date": "2025-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "evidence_type": "cob_report_county_data",
     "as_at": "2025-06-30",
     "finding_id": null,
     "summary": "County stalled-projects list: \"Not awarded due to budget deficit\"; 0% complete before stalling.",
     "confidence": 3,
     "reported_completion_pct": 0
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-071",
   "name": "Renovation and repairs of the Siriwo rice drying floor",
   "aliases": [],
   "sector": "agriculture_fisheries",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Executive",
      "doc_id": "cob-report-2024-25",
      "page": 483,
      "unresolved_reason": "location column reads \"Executive\" (the implementing office), so no place is stated"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Executive",
      "reason": "location column reads \"Executive\" (the implementing office), so no place is stated"
     }
    ]
   },
   "amounts": [],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "cancelled",
   "status_source": {
    "doc_id": "cob-report-2024-25",
    "page": 483,
    "evidence_type": "cob_report_county_data",
    "as_at": "2025-06-30"
   },
   "last_evidence_date": "2025-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2024-25",
     "page": 483,
     "evidence_type": "cob_report_county_data",
     "as_at": "2025-06-30",
     "finding_id": null,
     "summary": "County stalled-projects list: \"Not implemented; the budget of Kshs.4,500,000 removed in the supplementary\"; 0% complete before stalling.",
     "confidence": 3,
     "reported_completion_pct": 0
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-072",
   "name": "Construction of modern washrooms at Ralayo beach",
   "aliases": [],
   "sector": "water_sanitation",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "East Asembo",
      "doc_id": "cob-report-2024-25",
      "page": 484,
      "resolved_to": [
       {
        "ward_id": "east-asembo"
       }
      ]
     }
    ],
    "ward_ids": [
     "east-asembo"
    ],
    "constituency_ids": [
     "rarieda"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "suspended",
   "status_source": {
    "doc_id": "cob-report-2024-25",
    "page": 484,
    "evidence_type": "cob_report_county_data",
    "as_at": "2025-06-30"
   },
   "last_evidence_date": "2025-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2024-25",
     "page": 484,
     "evidence_type": "cob_report_county_data",
     "as_at": "2025-06-30",
     "finding_id": null,
     "summary": "County stalled-projects list: \"Budgetary Deficit\".",
     "confidence": 3
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-073",
   "name": "Acquisition of storage tanks for Bondo Sub-County Hospital",
   "aliases": [],
   "sector": "health",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Bondo sch",
      "doc_id": "cob-report-2024-25",
      "page": 484,
      "unresolved_reason": "a hospital abbreviation (\"sch\"), read as a facility not a ward; constituency not inferred"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Bondo sch",
      "reason": "a hospital abbreviation (\"sch\"), read as a facility not a ward; constituency not inferred"
     }
    ]
   },
   "amounts": [
    {
     "kind": "estimated_value",
     "value": 4899401,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "cob-report-2024-25",
     "page": 484,
     "label_as_printed": "Estimated Value of the Project"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "suspended",
   "status_source": {
    "doc_id": "cob-report-2024-25",
    "page": 484,
    "evidence_type": "cob_report_county_data",
    "as_at": "2025-06-30"
   },
   "last_evidence_date": "2025-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2024-25",
     "page": 484,
     "evidence_type": "cob_report_county_data",
     "as_at": "2025-06-30",
     "finding_id": null,
     "summary": "County stalled-projects list: \"insufficient funding\".",
     "confidence": 3
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-074",
   "name": "Completion of Oboch dispensary (Pending)",
   "aliases": [],
   "sector": "health",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "East Asembo (OCR \"East Aamo\")",
      "doc_id": "cob-report-2024-25",
      "page": 484,
      "resolved_to": [
       {
        "ward_id": "east-asembo"
       }
      ]
     }
    ],
    "ward_ids": [
     "east-asembo"
    ],
    "constituency_ids": [
     "rarieda"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "estimated_value",
     "value": 3200000,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "cob-report-2024-25",
     "page": 484,
     "label_as_printed": "Estimated Value of the Project"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "suspended",
   "status_source": {
    "doc_id": "cob-report-2024-25",
    "page": 484,
    "evidence_type": "cob_report_county_data",
    "as_at": "2025-06-30"
   },
   "last_evidence_date": "2025-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2024-25",
     "page": 484,
     "evidence_type": "cob_report_county_data",
     "as_at": "2025-06-30",
     "finding_id": null,
     "summary": "County stalled-projects list: \"insufficient funding\"; 70% complete before stalling.",
     "confidence": 3,
     "reported_completion_pct": 70
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-075",
   "name": "Improving the sewer system and gate at the Rwambwa sub-County hospital",
   "aliases": [],
   "sector": "health",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Usonga",
      "doc_id": "cob-report-2024-25",
      "page": 484,
      "resolved_to": [
       {
        "ward_id": "usonga"
       }
      ]
     }
    ],
    "ward_ids": [
     "usonga"
    ],
    "constituency_ids": [
     "alego-usonga"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "estimated_value",
     "value": 1200000,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "cob-report-2024-25",
     "page": 484,
     "label_as_printed": "Estimated Value of the Project"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "suspended",
   "status_source": {
    "doc_id": "cob-report-2024-25",
    "page": 484,
    "evidence_type": "cob_report_county_data",
    "as_at": "2025-06-30"
   },
   "last_evidence_date": "2025-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2024-25",
     "page": 484,
     "evidence_type": "cob_report_county_data",
     "as_at": "2025-06-30",
     "finding_id": null,
     "summary": "County stalled-projects list: \"inadequate funding\"; 70% complete before stalling.",
     "confidence": 3,
     "reported_completion_pct": 70
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-076",
   "name": "Complete Automation of Revenue",
   "aliases": [],
   "sector": "ict",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Executive",
      "doc_id": "GOV-02-FY2025-26-Q4",
      "page": 11,
      "unresolved_reason": "location column reads \"Executive\" (the implementing office), so no place is stated"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Executive",
      "reason": "location column reads \"Executive\" (the implementing office), so no place is stated"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 33013561,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 11,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "funding_in_fy",
     "value": 33013561,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 11,
     "label_as_printed": "Total Funding in FY 2025/26"
    },
    {
     "kind": "expenditure_in_fy",
     "value": 16314695.69,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q2",
     "page": 16,
     "label_as_printed": "Expenditure (accrual basis) in FY 2025/26 to 31 Dec 2025",
     "as_at": "2025-12-31"
    },
    {
     "kind": "paid_cumulative",
     "value": 28629391,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 11,
     "label_as_printed": "Cumulative project expenditure as of 30 June 2026"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "active",
   "status_source": {
    "doc_id": "GOV-02-FY2025-26-Q4",
    "page": 11,
    "evidence_type": "county_budget_report",
    "as_at": "2026-06-30"
   },
   "last_evidence_date": "2026-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-02-FY2025-26-Q2",
     "page": 16,
     "evidence_type": "county_budget_report",
     "as_at": "2025-12-31",
     "finding_id": null,
     "summary": "County: 49.40%.",
     "confidence": 4,
     "reported_completion_pct": 49.4
    },
    {
     "doc_id": "GOV-02-FY2025-26-Q3",
     "page": 13,
     "evidence_type": "county_budget_report",
     "as_at": "2026-03-31",
     "finding_id": null,
     "summary": "County: 86.72%.",
     "confidence": 4,
     "reported_completion_pct": 86.72
    },
    {
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 11,
     "evidence_type": "county_budget_report",
     "as_at": "2026-06-30",
     "finding_id": null,
     "summary": "County: 86.72%.",
     "confidence": 4,
     "reported_completion_pct": 86.72
    }
   ],
   "conflicts": [],
   "related_project_ids": [
    "SIA-P-052"
   ]
  },
  {
   "id": "SIA-P-077",
   "name": "Completion of casualty and maternity complex at Yala SCH",
   "aliases": [],
   "sector": "health",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Executive",
      "doc_id": "GOV-02-FY2025-26-Q4",
      "page": 11,
      "unresolved_reason": "location column reads \"Executive\" (the implementing office), so no place is stated"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Executive",
      "reason": "location column reads \"Executive\" (the implementing office), so no place is stated"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 78084128,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 11,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "funding_in_fy",
     "value": 30000000,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 11,
     "label_as_printed": "Total Funding in FY 2025/26"
    },
    {
     "kind": "paid_cumulative",
     "value": 30881701,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 11,
     "label_as_printed": "Cumulative project expenditure as of 30 June 2026"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": "2023-12 (Dec-23)",
    "expected_completion": "2026-02 (Feb-26)"
   },
   "status": "delayed",
   "status_source": {
    "doc_id": "GOV-02-FY2025-26-Q4",
    "page": 11,
    "evidence_type": "county_budget_report",
    "as_at": "2026-06-30"
   },
   "last_evidence_date": "2026-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-02-FY2025-26-Q2",
     "page": 16,
     "evidence_type": "county_budget_report",
     "as_at": "2025-12-31",
     "finding_id": null,
     "summary": "County: 86%.",
     "confidence": 4,
     "reported_completion_pct": 86
    },
    {
     "doc_id": "GOV-02-FY2025-26-Q3",
     "page": 13,
     "evidence_type": "county_budget_report",
     "as_at": "2026-03-31",
     "finding_id": null,
     "summary": "County: 90%.",
     "confidence": 4,
     "reported_completion_pct": 90
    },
    {
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 11,
     "evidence_type": "county_budget_report",
     "as_at": "2026-06-30",
     "finding_id": null,
     "summary": "County: 90%.",
     "confidence": 4,
     "reported_completion_pct": 90
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Delayed on the county's own dates: 90% at 30 June 2026 against an expected completion of February 2026."
  },
  {
   "id": "SIA-P-078",
   "name": "Phased construction of Ugenya Sub County Office at Ukwala",
   "aliases": [],
   "sector": "governance_offices",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Ugenya Sub County Office at Ukwala",
      "doc_id": "GOV-02-FY2025-26-Q4",
      "page": 12,
      "resolved_to": [
       {
        "ward_id": "ukwala"
       }
      ]
     }
    ],
    "ward_ids": [
     "ukwala"
    ],
    "constituency_ids": [
     "ugenya"
    ],
    "countywide": false,
    "unresolved": [],
    "note": "Location column reads \"Executive\"; the ward is taken from the project name."
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 41233141.48,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q3",
     "page": 13,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "funding_in_fy",
     "value": 15233141,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "label_as_printed": "Total Funding in FY 2025/26"
    },
    {
     "kind": "paid_cumulative",
     "value": 8246628.3,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q3",
     "page": 13,
     "label_as_printed": "Cumulative project expenditure as of 31 March 2026",
     "as_at": "2026-03-31"
    },
    {
     "kind": "paid_cumulative",
     "value": 8246628,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "label_as_printed": "Cumulative project expenditure as of 30 June 2026"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": "2025-04-11",
    "expected_completion": "2025-11 (Nov-25)"
   },
   "status": "unknown",
   "status_source": {
    "doc_id": "GOV-02-FY2025-26-Q4",
    "page": 12,
    "evidence_type": "county_budget_report",
    "as_at": "2026-06-30"
   },
   "last_evidence_date": "2026-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-02-FY2025-26-Q3",
     "page": 13,
     "evidence_type": "county_budget_report",
     "as_at": "2026-03-31",
     "finding_id": null,
     "summary": "No completion percentage printed.",
     "confidence": 4
    },
    {
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "evidence_type": "county_budget_report",
     "as_at": "2026-06-30",
     "finding_id": null,
     "summary": "No completion percentage printed.",
     "confidence": 4
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-079",
   "name": "Phased construction of Gem Sub County Office at Yala",
   "aliases": [],
   "sector": "governance_offices",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Gem Sub County Office at Yala",
      "doc_id": "GOV-02-FY2025-26-Q3",
      "page": 13,
      "resolved_to": [
       {
        "constituency_id": "gem"
       }
      ],
      "unresolved_reason": "Yala part: a town, not a ward name"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [
     "gem"
    ],
    "countywide": false,
    "unresolved": [
     {
      "text": "Gem Sub County Office at Yala",
      "reason": "Yala part: a town, not a ward name"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 41593818.75,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q3",
     "page": 13,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "funding_in_fy",
     "value": 15593819,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q3",
     "page": 13,
     "label_as_printed": "Total Funding in FY 2025/26"
    },
    {
     "kind": "paid_cumulative",
     "value": 5673544.75,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q3",
     "page": 13,
     "label_as_printed": "Cumulative project expenditure as of 31 March 2026"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": "2025-05-12",
    "expected_completion": "2025-11-12"
   },
   "status": "delayed",
   "status_source": {
    "doc_id": "GOV-02-FY2025-26-Q3",
    "page": 13,
    "evidence_type": "county_budget_report",
    "as_at": "2026-03-31"
   },
   "last_evidence_date": "2026-03-31",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-02-FY2025-26-Q3",
     "page": 13,
     "evidence_type": "county_budget_report",
     "as_at": "2026-03-31",
     "finding_id": null,
     "summary": "County: 2% against an expected completion of 12 Nov 2025.",
     "confidence": 4,
     "reported_completion_pct": 2
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Delayed on the county's own dates. Not in the Q4 table."
  },
  {
   "id": "SIA-P-080",
   "name": "Completion of upgrading to bitumen standard of Ndori market ring Road (phased)",
   "aliases": [],
   "sector": "roads_transport",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "East Asembo",
      "doc_id": "GOV-02-FY2025-26-Q4",
      "page": 12,
      "resolved_to": [
       {
        "ward_id": "east-asembo"
       }
      ]
     }
    ],
    "ward_ids": [
     "east-asembo"
    ],
    "constituency_ids": [
     "rarieda"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 100283313,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "funding_in_fy",
     "value": 44649708,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "label_as_printed": "Total Funding in FY 2025/26"
    },
    {
     "kind": "paid_cumulative",
     "value": 43990003,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "label_as_printed": "Cumulative project expenditure as of 30 June 2026"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": "1st January (year not printed)",
    "expected_completion": "30th June (year not printed)"
   },
   "status": "completed-reported",
   "status_source": {
    "doc_id": "GOV-02-FY2025-26-Q4",
    "page": 12,
    "evidence_type": "county_budget_report",
    "as_at": "2026-06-30"
   },
   "last_evidence_date": "2026-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "evidence_type": "county_budget_report",
     "as_at": "2026-06-30",
     "finding_id": null,
     "summary": "County: 100%.",
     "confidence": 4,
     "reported_completion_pct": 100
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Phased project: 100% may refer to the phase funded in FY 2025/26."
  },
  {
   "id": "SIA-P-081",
   "name": "Completion of construction and equipping of Municipal Office complex - Phase 2 (multi- year project)",
   "aliases": [],
   "sector": "urban_housing_lands",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Siaya municipal Coumpound [sic]",
      "doc_id": "GOV-02-FY2025-26-Q4",
      "page": 12,
      "unresolved_reason": "a compound in Siaya municipality, not a ward"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Siaya municipal Coumpound [sic]",
      "reason": "a compound in Siaya municipality, not a ward"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 62557284,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "funding_in_fy",
     "value": 50147536,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "label_as_printed": "Total Funding in FY 2025/26"
    },
    {
     "kind": "expenditure_in_fy",
     "value": 17878166,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "label_as_printed": "Expenditure (accrual basis) in FY 2025/26"
    },
    {
     "kind": "paid_cumulative",
     "value": 30389622,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "label_as_printed": "Cumulative project expenditure as of 30 June 2026"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": "2025-05-26",
    "expected_completion": "2026-05-26"
   },
   "status": "delayed",
   "status_source": {
    "doc_id": "GOV-02-FY2025-26-Q4",
    "page": 12,
    "evidence_type": "county_budget_report",
    "as_at": "2026-06-30"
   },
   "last_evidence_date": "2026-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-02-FY2025-26-Q3",
     "page": 13,
     "evidence_type": "county_budget_report",
     "as_at": "2026-03-31",
     "finding_id": null,
     "summary": "County: 60%.",
     "confidence": 4,
     "reported_completion_pct": 60
    },
    {
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "evidence_type": "county_budget_report",
     "as_at": "2026-06-30",
     "finding_id": null,
     "summary": "County: 60% against an expected completion of 26 May 2026.",
     "confidence": 4,
     "reported_completion_pct": 60
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Delayed on the county's own dates."
  },
  {
   "id": "SIA-P-082",
   "name": "Revamping South Sakwa (Olago)",
   "aliases": [],
   "sector": "water_sanitation",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Revamping South Sakwa (Olago) [project name; location column \"Executive\"]",
      "doc_id": "GOV-02-FY2025-26-Q4",
      "page": 12,
      "resolved_to": [
       {
        "ward_id": "south-sakwa"
       }
      ]
     }
    ],
    "ward_ids": [
     "south-sakwa"
    ],
    "constituency_ids": [
     "bondo"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 47023421,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "funding_in_fy",
     "value": 17150000,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "label_as_printed": "Total Funding in FY 2025/26"
    },
    {
     "kind": "paid_cumulative",
     "value": 17146272,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "label_as_printed": "Cumulative project expenditure as of 30 June 2026"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": "2025-03-07",
    "expected_completion": "2025-09-07"
   },
   "status": "delayed",
   "status_source": {
    "doc_id": "GOV-02-FY2025-26-Q4",
    "page": 12,
    "evidence_type": "county_budget_report",
    "as_at": "2026-06-30"
   },
   "last_evidence_date": "2026-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-02-FY2025-26-Q2",
     "page": 16,
     "evidence_type": "county_budget_report",
     "as_at": "2025-12-31",
     "finding_id": null,
     "summary": "County: 60%.",
     "confidence": 4,
     "reported_completion_pct": 60
    },
    {
     "doc_id": "GOV-02-FY2025-26-Q3",
     "page": 13,
     "evidence_type": "county_budget_report",
     "as_at": "2026-03-31",
     "finding_id": null,
     "summary": "County: 60%.",
     "confidence": 4,
     "reported_completion_pct": 60
    },
    {
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "evidence_type": "county_budget_report",
     "as_at": "2026-06-30",
     "finding_id": null,
     "summary": "County: 60% against an expected completion of 7 Sep 2025.",
     "confidence": 4,
     "reported_completion_pct": 60
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Sector code WECC&NR (water, environment). Delayed on the county's own dates; unchanged at 60% for three quarters."
  },
  {
   "id": "SIA-P-083",
   "name": "Provision of improved kienyeji chicks to South Gem groups",
   "aliases": [],
   "sector": "agriculture_fisheries",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "South Gem",
      "doc_id": "GOV-02-FY2025-26-Q4",
      "page": 12,
      "resolved_to": [
       {
        "ward_id": "south-gem"
       }
      ]
     }
    ],
    "ward_ids": [
     "south-gem"
    ],
    "constituency_ids": [
     "gem"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 10412743,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "funding_in_fy",
     "value": 10000000,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "label_as_printed": "Total Funding in FY 2025/26"
    },
    {
     "kind": "paid_cumulative",
     "value": 8436415,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "label_as_printed": "Cumulative project expenditure as of 30 June 2026"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "completed-reported",
   "status_source": {
    "doc_id": "GOV-02-FY2025-26-Q4",
    "page": 12,
    "evidence_type": "county_budget_report",
    "as_at": "2026-06-30"
   },
   "last_evidence_date": "2026-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-02-FY2025-26-Q2",
     "page": 16,
     "evidence_type": "county_budget_report",
     "as_at": "2025-12-31",
     "finding_id": null,
     "summary": "County: 100%.",
     "confidence": 4,
     "reported_completion_pct": 100
    },
    {
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "evidence_type": "county_budget_report",
     "as_at": "2026-06-30",
     "finding_id": null,
     "summary": "County: 100%.",
     "confidence": 4,
     "reported_completion_pct": 100
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "An input supply, not a construction project; kept because the county lists it as a development project."
  },
  {
   "id": "SIA-P-084",
   "name": "Phased of upgrading to Bitumen standard- Sega market ring road",
   "aliases": [],
   "sector": "roads_transport",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "north Ugenya",
      "doc_id": "GOV-02-FY2025-26-Q4",
      "page": 12,
      "resolved_to": [
       {
        "ward_id": "north-ugenya"
       }
      ]
     }
    ],
    "ward_ids": [
     "north-ugenya"
    ],
    "constituency_ids": [
     "ugenya"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 98097505,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "funding_in_fy",
     "value": 48380499,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "label_as_printed": "Total Funding in FY 2025/26"
    },
    {
     "kind": "paid_cumulative",
     "value": 45355577,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "label_as_printed": "Cumulative project expenditure as of 30 June 2026"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": "1st January (year not printed)",
    "expected_completion": "30th June (year not printed)"
   },
   "status": "completed-reported",
   "status_source": {
    "doc_id": "GOV-02-FY2025-26-Q4",
    "page": 12,
    "evidence_type": "county_budget_report",
    "as_at": "2026-06-30"
   },
   "last_evidence_date": "2026-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-02-FY2025-26-Q2",
     "page": 16,
     "evidence_type": "county_budget_report",
     "as_at": "2025-12-31",
     "finding_id": null,
     "summary": "County: 100%.",
     "confidence": 4,
     "reported_completion_pct": 100
    },
    {
     "doc_id": "GOV-02-FY2025-26-Q3",
     "page": 13,
     "evidence_type": "county_budget_report",
     "as_at": "2026-03-31",
     "finding_id": null,
     "summary": "County: 100%.",
     "confidence": 4,
     "reported_completion_pct": 100
    },
    {
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "evidence_type": "county_budget_report",
     "as_at": "2026-06-30",
     "finding_id": null,
     "summary": "County: 100%.",
     "confidence": 4,
     "reported_completion_pct": 100
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Phased project: 100% may refer to the phase funded in FY 2025/26."
  },
  {
   "id": "SIA-P-085",
   "name": "Completion of upgrading to bitumen standard of Usenge market ring Road (phased)",
   "aliases": [],
   "sector": "roads_transport",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "West Yimbo",
      "doc_id": "GOV-02-FY2025-26-Q4",
      "page": 12,
      "resolved_to": [
       {
        "ward_id": "west-yimbo"
       }
      ]
     }
    ],
    "ward_ids": [
     "west-yimbo"
    ],
    "constituency_ids": [
     "bondo"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 99214278,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "funding_in_fy",
     "value": 56234818,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "label_as_printed": "Total Funding in FY 2025/26"
    },
    {
     "kind": "paid_cumulative",
     "value": 53007624,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "label_as_printed": "Cumulative project expenditure as of 30 June 2026"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": "1st January (year not printed)",
    "expected_completion": "30th June (year not printed)"
   },
   "status": "completed-reported",
   "status_source": {
    "doc_id": "GOV-02-FY2025-26-Q4",
    "page": 12,
    "evidence_type": "county_budget_report",
    "as_at": "2026-06-30"
   },
   "last_evidence_date": "2026-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "evidence_type": "county_budget_report",
     "as_at": "2026-06-30",
     "finding_id": null,
     "summary": "County: 100%.",
     "confidence": 4,
     "reported_completion_pct": 100
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Phased project: 100% may refer to the phase funded in FY 2025/26."
  },
  {
   "id": "SIA-P-086",
   "name": "Phased construction of Ukwala Sub County Hospital Annex",
   "aliases": [],
   "sector": "health",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Ukwala Sub County Hospital Annex [project name; location column \"Executive\"]",
      "doc_id": "GOV-02-FY2025-26-Q4",
      "page": 12,
      "resolved_to": [
       {
        "ward_id": "ukwala"
       }
      ]
     }
    ],
    "ward_ids": [
     "ukwala"
    ],
    "constituency_ids": [
     "ugenya"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 106901740,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "funding_in_fy",
     "value": 17229901,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "label_as_printed": "Total Funding in FY 2025/26"
    },
    {
     "kind": "paid_cumulative",
     "value": 17229901,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "label_as_printed": "Cumulative project expenditure as of 30 June 2026"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": "2025-08 (Aug-25)",
    "expected_completion": "2026-05 (May-26)"
   },
   "status": "completed-reported",
   "status_source": {
    "doc_id": "GOV-02-FY2025-26-Q4",
    "page": 12,
    "evidence_type": "county_budget_report",
    "as_at": "2026-06-30"
   },
   "last_evidence_date": "2026-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "evidence_type": "county_budget_report",
     "as_at": "2026-06-30",
     "finding_id": null,
     "summary": "County: 100% with KSh 17.2 million of a KSh 106.9 million contract spent.",
     "confidence": 4,
     "reported_completion_pct": 100
    }
   ],
   "conflicts": [
    {
     "field": "status",
     "note": "100% reported with 16% of the contract sum spent; likely the FY 2025/26 phase only."
    }
   ],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-087",
   "name": "Construction of out-patient unit, co-funding of Urenga hospital (KDSP II)",
   "aliases": [
    {
     "name": "construction of out-patient unit Co-funding of urenga hospital-KDSP II",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12
    }
   ],
   "sector": "health",
   "implementing_entity": "county_and_partners",
   "location": {
    "as_printed": [
     {
      "text": "Executive",
      "doc_id": "GOV-02-FY2025-26-Q4",
      "page": 12,
      "unresolved_reason": "location column reads \"Executive\" (the implementing office), so no place is stated"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Executive",
      "reason": "location column reads \"Executive\" (the implementing office), so no place is stated"
     }
    ]
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 84319813.21,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q3",
     "page": 13,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "funding_in_fy",
     "value": 67000000,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "label_as_printed": "Total Funding in FY 2025/26"
    },
    {
     "kind": "paid_cumulative",
     "value": 16119955.08,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q2",
     "page": 17,
     "label_as_printed": "Cumulative project expenditure as of 31 Dec 2025",
     "as_at": "2025-12-31"
    },
    {
     "kind": "paid_cumulative",
     "value": 34606055,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "label_as_printed": "Cumulative project expenditure as of 30 June 2026"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "active",
   "status_source": {
    "doc_id": "GOV-02-FY2025-26-Q4",
    "page": 12,
    "evidence_type": "county_budget_report",
    "as_at": "2026-06-30"
   },
   "last_evidence_date": "2026-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-02-FY2025-26-Q2",
     "page": 17,
     "evidence_type": "county_budget_report",
     "as_at": "2025-12-31",
     "finding_id": null,
     "summary": "County: 26% (donor-funded).",
     "confidence": 4,
     "reported_completion_pct": 26
    },
    {
     "doc_id": "GOV-02-FY2025-26-Q3",
     "page": 13,
     "evidence_type": "county_budget_report",
     "as_at": "2026-03-31",
     "finding_id": null,
     "summary": "County: 55%.",
     "confidence": 4,
     "reported_completion_pct": 55
    },
    {
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "evidence_type": "county_budget_report",
     "as_at": "2026-06-30",
     "finding_id": null,
     "summary": "County: 55%.",
     "confidence": 4,
     "reported_completion_pct": 55
    }
   ],
   "conflicts": [
    {
     "field": "reported_completion_pct",
     "note": "Q3 reports 55% with KSh 16.1 million spent; Q4 also 55% with KSh 34.6 million spent."
    }
   ],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-088",
   "name": "Opening, grading and gravelling of Sianga-Wambarra- Yao Kouma- Kongolo Road",
   "aliases": [],
   "sector": "roads_transport",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "central sakwa",
      "doc_id": "GOV-02-FY2025-26-Q3",
      "page": 13,
      "resolved_to": [
       {
        "ward_id": "central-sakwa"
       }
      ]
     }
    ],
    "ward_ids": [
     "central-sakwa"
    ],
    "constituency_ids": [
     "bondo"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 6448517.98,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q3",
     "page": 13,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "funding_in_fy",
     "value": 6500550,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q3",
     "page": 13,
     "label_as_printed": "Total Funding in FY 2025/26"
    },
    {
     "kind": "paid_cumulative",
     "value": 6367317.98,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q3",
     "page": 13,
     "label_as_printed": "Cumulative project expenditure as of 31 March 2026"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": "1st January (year not printed)",
    "expected_completion": "30th June (year not printed)"
   },
   "status": "completed-reported",
   "status_source": {
    "doc_id": "GOV-02-FY2025-26-Q3",
    "page": 13,
    "evidence_type": "county_budget_report",
    "as_at": "2026-03-31"
   },
   "last_evidence_date": "2026-03-31",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-02-FY2025-26-Q2",
     "page": 16,
     "evidence_type": "county_budget_report",
     "as_at": "2025-12-31",
     "finding_id": null,
     "summary": "County: 100%.",
     "confidence": 4,
     "reported_completion_pct": 100
    },
    {
     "doc_id": "GOV-02-FY2025-26-Q3",
     "page": 13,
     "evidence_type": "county_budget_report",
     "as_at": "2026-03-31",
     "finding_id": null,
     "summary": "County: 100%.",
     "confidence": 4,
     "reported_completion_pct": 100
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-089",
   "name": "Maintenance of Nyangera sports ground access road and Nyagera pitch levelling",
   "aliases": [],
   "sector": "sports_culture_tourism",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Yimbo East",
      "doc_id": "GOV-02-FY2025-26-Q2",
      "page": 17,
      "resolved_to": [
       {
        "ward_id": "yimbo-east"
       }
      ]
     }
    ],
    "ward_ids": [
     "yimbo-east"
    ],
    "constituency_ids": [
     "bondo"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 4969782.09,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q2",
     "page": 17,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "funding_in_fy",
     "value": 7000000,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q2",
     "page": 17,
     "label_as_printed": "Total Funding in FY 2025/26"
    },
    {
     "kind": "expenditure_in_fy",
     "value": 4778324.67,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q2",
     "page": 17,
     "label_as_printed": "Expenditure (accrual basis) to 31 Dec 2025"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": "2024-02 (Feb-24)",
    "expected_completion": "2026-06 (Jun-26)"
   },
   "status": "completed-reported",
   "status_source": {
    "doc_id": "GOV-02-FY2025-26-Q2",
    "page": 17,
    "evidence_type": "county_budget_report",
    "as_at": "2025-12-31"
   },
   "last_evidence_date": "2025-12-31",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-02-FY2025-26-Q2",
     "page": 17,
     "evidence_type": "county_budget_report",
     "as_at": "2025-12-31",
     "finding_id": null,
     "summary": "County: 100%.",
     "confidence": 4,
     "reported_completion_pct": 100
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-090",
   "name": "Maintenace [sic] of Julius Waliera - Sirand Malwa - Uyundi road - 2.5km",
   "aliases": [],
   "sector": "roads_transport",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "West Ugenya",
      "doc_id": "GOV-02-FY2025-26-Q2",
      "page": 17,
      "resolved_to": [
       {
        "ward_id": "west-ugenya"
       }
      ]
     }
    ],
    "ward_ids": [
     "west-ugenya"
    ],
    "constituency_ids": [
     "ugenya"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "contract_sum",
     "value": 4746930.79,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q2",
     "page": 17,
     "label_as_printed": "Contract sum"
    },
    {
     "kind": "funding_in_fy",
     "value": 4700000,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q2",
     "page": 17,
     "label_as_printed": "Total Funding in FY 2025/26"
    },
    {
     "kind": "expenditure_in_fy",
     "value": 4700000,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q2",
     "page": 17,
     "label_as_printed": "Expenditure (accrual basis) to 31 Dec 2025"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": "1st January (year not printed)",
    "expected_completion": "30th June (year not printed)"
   },
   "status": "completed-reported",
   "status_source": {
    "doc_id": "GOV-02-FY2025-26-Q2",
    "page": 17,
    "evidence_type": "county_budget_report",
    "as_at": "2025-12-31"
   },
   "last_evidence_date": "2025-12-31",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-02-FY2025-26-Q2",
     "page": 17,
     "evidence_type": "county_budget_report",
     "as_at": "2025-12-31",
     "finding_id": null,
     "summary": "County: 100%.",
     "confidence": 4,
     "reported_completion_pct": 100
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "The road name is printed as in the source (a place name)."
  },
  {
   "id": "SIA-P-091",
   "name": "Purchase, commissioning, delivery and installation of generator at Ukwala Hospital",
   "aliases": [
    {
     "name": "PURCHASE,COMMISIONING delivery and installation OF GENERATOR AT UKWALA HOSPITAL",
     "doc_id": "GOV-02-FY2025-26-Q2",
     "page": 16
    }
   ],
   "sector": "health",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "UKWALA HOSPITAL [project name; location column \"Executive\"]",
      "doc_id": "GOV-02-FY2025-26-Q2",
      "page": 16,
      "resolved_to": [
       {
        "ward_id": "ukwala"
       }
      ]
     }
    ],
    "ward_ids": [
     "ukwala"
    ],
    "constituency_ids": [
     "ugenya"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "funding_in_fy",
     "value": 5000000,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q2",
     "page": 16,
     "label_as_printed": "Total Funding in FY 2025/26"
    },
    {
     "kind": "expenditure_in_fy",
     "value": 5000000,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q2",
     "page": 16,
     "label_as_printed": "Expenditure (accrual basis) to 31 Dec 2025"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": "2025-05 (\"Mei-25\")",
    "expected_completion": "2025-06 (Jun-25)"
   },
   "status": "completed-reported",
   "status_source": {
    "doc_id": "GOV-02-FY2025-26-Q2",
    "page": 16,
    "evidence_type": "county_budget_report",
    "as_at": "2025-12-31"
   },
   "last_evidence_date": "2025-12-31",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-02-FY2025-26-Q2",
     "page": 16,
     "evidence_type": "county_budget_report",
     "as_at": "2025-12-31",
     "finding_id": null,
     "summary": "County: 100%.",
     "confidence": 4,
     "reported_completion_pct": 100
    }
   ],
   "conflicts": [],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-092",
   "name": "Proposed Construction of Rarieda Sub-County Headquarters in Aram",
   "aliases": [],
   "sector": "governance_offices",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Rarieda Sub-County Headquarters in Aram [project name; location column \"Executive\"]",
      "doc_id": "GOV-02-FY2025-26-Q3",
      "page": 14,
      "resolved_to": [
       {
        "constituency_id": "rarieda"
       }
      ]
     }
    ],
    "ward_ids": [],
    "constituency_ids": [
     "rarieda"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "estimated_value",
     "value": 39900000,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q1",
     "page": 15,
     "label_as_printed": "Estimated Value of the Project"
    },
    {
     "kind": "outstanding_balance",
     "value": 42383851.99,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q1",
     "page": 15,
     "label_as_printed": "Outstanding Balance as of 30 September 2025 (above the estimated value, as printed)",
     "as_at": "2025-09-30"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": "2025-04-16",
    "expected_completion": "2025-11"
   },
   "status": "suspended",
   "status_source": {
    "doc_id": "GOV-02-FY2025-26-Q3",
    "page": 14,
    "evidence_type": "county_budget_report",
    "as_at": "2026-03-31"
   },
   "last_evidence_date": "2026-03-31",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-02-FY2025-26-Q1",
     "page": 15,
     "evidence_type": "county_budget_report",
     "as_at": "2025-09-30",
     "finding_id": null,
     "summary": "County stalled-projects list: \"Land Issues\".",
     "confidence": 4
    },
    {
     "doc_id": "GOV-02-FY2025-26-Q2",
     "page": 18,
     "evidence_type": "county_budget_report",
     "as_at": "2025-12-31",
     "finding_id": null,
     "summary": "Still on the stalled list.",
     "confidence": 4
    },
    {
     "doc_id": "GOV-02-FY2025-26-Q3",
     "page": 14,
     "evidence_type": "county_budget_report",
     "as_at": "2026-03-31",
     "finding_id": null,
     "summary": "Still on the stalled list.",
     "confidence": 4
    }
   ],
   "conflicts": [],
   "related_project_ids": [
    "SIA-P-093"
   ],
   "status_note": "Dropped from the Q4 report, which lists only one stalled project; no reason given."
  },
  {
   "id": "SIA-P-093",
   "name": "Purchase of Land for Construction of Rarieda Sub County Office",
   "aliases": [],
   "sector": "governance_offices",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Rarieda Sub County Office [project name; location column \"Executive\"]",
      "doc_id": "GOV-02-FY2025-26-Q3",
      "page": 14,
      "resolved_to": [
       {
        "constituency_id": "rarieda"
       }
      ]
     }
    ],
    "ward_ids": [],
    "constituency_ids": [
     "rarieda"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "estimated_value",
     "value": 5000000,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q1",
     "page": 15,
     "label_as_printed": "Estimated Value of the Project"
    },
    {
     "kind": "outstanding_balance",
     "value": 5000000,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q1",
     "page": 15,
     "label_as_printed": "Outstanding Balance as of 30 September 2025",
     "as_at": "2025-09-30"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": "2025-05",
    "expected_completion": "2025-05-25"
   },
   "status": "suspended",
   "status_source": {
    "doc_id": "GOV-02-FY2025-26-Q3",
    "page": 14,
    "evidence_type": "county_budget_report",
    "as_at": "2026-03-31"
   },
   "last_evidence_date": "2026-03-31",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-02-FY2025-26-Q1",
     "page": 15,
     "evidence_type": "county_budget_report",
     "as_at": "2025-09-30",
     "finding_id": null,
     "summary": "County stalled-projects list: \"Delayed Procurement Process\".",
     "confidence": 4
    },
    {
     "doc_id": "GOV-02-FY2025-26-Q3",
     "page": 14,
     "evidence_type": "county_budget_report",
     "as_at": "2026-03-31",
     "finding_id": null,
     "summary": "Still on the stalled list.",
     "confidence": 4
    }
   ],
   "conflicts": [],
   "related_project_ids": [
    "SIA-P-092"
   ]
  },
  {
   "id": "SIA-P-094",
   "name": "Completion of Nyamonye juakali",
   "aliases": [],
   "sector": "markets_trade",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Yimbo East",
      "doc_id": "GOV-02-FY2025-26-Q1",
      "page": 15,
      "resolved_to": [
       {
        "ward_id": "yimbo-east"
       }
      ]
     }
    ],
    "ward_ids": [
     "yimbo-east"
    ],
    "constituency_ids": [
     "bondo"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "estimated_value",
     "value": 1878186.2,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q1",
     "page": 15,
     "label_as_printed": "Estimated Value of the Project"
    },
    {
     "kind": "paid_cumulative",
     "value": 3720000,
     "unit": "KSh",
     "fy": "2025/26",
     "doc_id": "GOV-02-FY2025-26-Q2",
     "page": 18,
     "label_as_printed": "Amount Paid on the stalled project (above the estimated value, as printed)",
     "as_at": "2025-12-31"
    },
    {
     "kind": "estimated_value",
     "value": 1878186.2,
     "unit": "KSh",
     "fy": "2024/25",
     "doc_id": "cob-report-2024-25",
     "page": 484,
     "label_as_printed": "Estimated Value of the Project"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": "2023-12-31",
    "expected_completion": "2024-03-31"
   },
   "status": "suspended",
   "status_source": {
    "doc_id": "GOV-02-FY2025-26-Q4",
    "page": 12,
    "evidence_type": "county_budget_report",
    "as_at": "2026-06-30"
   },
   "last_evidence_date": "2026-06-30",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "cob-report-2024-25",
     "page": 484,
     "evidence_type": "cob_report_county_data",
     "as_at": "2025-06-30",
     "finding_id": null,
     "summary": "County stalled-projects list: \"inadequate funding\".",
     "confidence": 3
    },
    {
     "doc_id": "GOV-02-FY2025-26-Q1",
     "page": 15,
     "evidence_type": "county_budget_report",
     "as_at": "2025-09-30",
     "finding_id": null,
     "summary": "County: 40% before stalling; \"Stalled, review of contract awaiting termination\".",
     "confidence": 4,
     "reported_completion_pct": 40
    },
    {
     "doc_id": "GOV-02-FY2025-26-Q3",
     "page": 14,
     "evidence_type": "county_budget_report",
     "as_at": "2026-03-31",
     "finding_id": null,
     "summary": "County: 40% before stalling.",
     "confidence": 4,
     "reported_completion_pct": 40
    },
    {
     "doc_id": "GOV-02-FY2025-26-Q4",
     "page": 12,
     "evidence_type": "county_budget_report",
     "as_at": "2026-06-30",
     "finding_id": null,
     "summary": "County: the one stalled project at 30 June 2026, \"currently under investigation\".",
     "confidence": 4
    }
   ],
   "conflicts": [
    {
     "field": "amount",
     "note": "Amount paid (KSh 3,720,000) is printed above the estimated value (KSh 1,878,186.20). CoB FY 2024/25 prints the completion before stalling as 35% (OCR), the county quarterly reports 40%."
    }
   ],
   "related_project_ids": []
  },
  {
   "id": "SIA-P-095",
   "name": "Completion of an Early Childhood Development (ECD) center at Hawinga",
   "aliases": [],
   "sector": "education",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "West Alego",
      "doc_id": "GOV-04-CADP-PP",
      "page": 6,
      "resolved_to": [
       {
        "ward_id": "west-alego"
       }
      ]
     }
    ],
    "ward_ids": [
     "west-alego"
    ],
    "constituency_ids": [
     "alego-usonga"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "completed-reported",
   "status_source": {
    "doc_id": "GOV-04-CADP-PP",
    "page": 6,
    "evidence_type": "county_participation_report",
    "as_at": "2024-09"
   },
   "last_evidence_date": "2024-09",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-04-CADP-PP",
     "page": 6,
     "evidence_type": "county_participation_report",
     "as_at": "2024-09",
     "finding_id": null,
     "summary": "Success stories: West Alego saw \"the completion of an Early Childhood Development (ECD) center at Hawinga that had been stalled for 10 years\".",
     "confidence": 4
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Reported by the county in its participation report; no amount printed."
  },
  {
   "id": "SIA-P-096",
   "name": "Wagai Multi-Media Resource and Learning Centre",
   "aliases": [],
   "sector": "education",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "not stated (Wagai)",
      "doc_id": "GOV-04-CADP-PP",
      "page": 10,
      "unresolved_reason": "Wagai is not a ward or constituency name in the register"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "not stated (Wagai)",
      "reason": "Wagai is not a ward or constituency name in the register"
     }
    ]
   },
   "amounts": [],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "suspended",
   "status_source": {
    "doc_id": "GOV-04-CADP-PP",
    "page": 10,
    "evidence_type": "county_participation_report",
    "as_at": "2024-09"
   },
   "last_evidence_date": "2024-09",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-04-CADP-PP",
     "page": 10,
     "evidence_type": "county_participation_report",
     "as_at": "2024-09",
     "finding_id": null,
     "summary": "Participants called for completion of stalled projects, \"such as the Wagai Multi-Media Resource and Learning Centre\".",
     "confidence": 3
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Described as stalled by forum participants, as recorded by the county; no amount printed."
  },
  {
   "id": "SIA-P-097",
   "name": "Muluwa Irrigation Scheme in Alego Usonga sub-county",
   "aliases": [],
   "sector": "agriculture_fisheries",
   "implementing_entity": "county_and_partners",
   "location": {
    "as_printed": [
     {
      "text": "Alego Usonga sub-county",
      "doc_id": "GOV-01-PDF",
      "page": 168,
      "resolved_to": [
       {
        "constituency_id": "alego-usonga"
       }
      ]
     }
    ],
    "ward_ids": [],
    "constituency_ids": [
     "alego-usonga"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "estimated_cost",
     "value": 5881,
     "unit": "KSh million",
     "fy": "2023/24-2027/28",
     "doc_id": "GOV-01-PDF",
     "page": 168,
     "label_as_printed": "Sub-Total Muluwa Scheme (estimated cost, M)",
     "note": "Flagship table header: \"Estimated cost (M)\"."
    },
    {
     "kind": "estimated_cost",
     "value": 5478,
     "unit": "KSh million",
     "fy": "2023/24-2027/28",
     "doc_id": "GOV-01-PDF",
     "page": 168,
     "label_as_printed": "Committed (LNIP phase 1)"
    },
    {
     "kind": "estimated_cost",
     "value": 403,
     "unit": "KSh million",
     "fy": "2023/24-2027/28",
     "doc_id": "GOV-01-PDF",
     "page": 168,
     "label_as_printed": "Required"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "active",
   "status_source": {
    "doc_id": "GOV-01-PDF",
    "page": 168,
    "evidence_type": "county_development_plan",
    "as_at": "2024-01-24"
   },
   "last_evidence_date": "2024-01-24",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-01-PDF",
     "page": 168,
     "evidence_type": "county_development_plan",
     "as_at": "2024-01-24",
     "finding_id": null,
     "summary": "CIDP flagship project: expansion of 6,500 acres under rice is \"On-going under Lower Nzoia Irrigation Project (LNIP)\" (committed 5,478 M; required 403 M).",
     "confidence": 5
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "The CIDP says the irrigation expansion is on-going under a national project; the county components are plans. No implementation report was read."
  },
  {
   "id": "SIA-P-098",
   "name": "Anyiko Irrigation Scheme in Ugenya sub-county",
   "aliases": [],
   "sector": "agriculture_fisheries",
   "implementing_entity": "county_and_partners",
   "location": {
    "as_printed": [
     {
      "text": "Ugenya sub-county",
      "doc_id": "GOV-01-PDF",
      "page": 169,
      "resolved_to": [
       {
        "constituency_id": "ugenya"
       }
      ]
     }
    ],
    "ward_ids": [],
    "constituency_ids": [
     "ugenya"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "estimated_cost",
     "value": 615,
     "unit": "KSh million",
     "fy": "2023/24-2027/28",
     "doc_id": "GOV-01-PDF",
     "page": 169,
     "label_as_printed": "SUB-TOTAL ANYIKO SCHEME (estimated cost, M)",
     "note": "Flagship table header: \"Estimated cost (M)\"."
    },
    {
     "kind": "estimated_cost",
     "value": 478,
     "unit": "KSh million",
     "fy": "2023/24-2027/28",
     "doc_id": "GOV-01-PDF",
     "page": 169,
     "label_as_printed": "Committed (on-going scheme expansion project)"
    },
    {
     "kind": "estimated_cost",
     "value": 137,
     "unit": "KSh million",
     "fy": "2023/24-2027/28",
     "doc_id": "GOV-01-PDF",
     "page": 169,
     "label_as_printed": "Required"
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "active",
   "status_source": {
    "doc_id": "GOV-01-PDF",
    "page": 169,
    "evidence_type": "county_development_plan",
    "as_at": "2024-01-24"
   },
   "last_evidence_date": "2024-01-24",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-01-PDF",
     "page": 169,
     "evidence_type": "county_development_plan",
     "as_at": "2024-01-24",
     "finding_id": null,
     "summary": "CIDP flagship project: 2,000 acres under rice \"On-going under Anyiko Scheme Expansion Project\" (committed 478 M; required 137 M).",
     "confidence": 5
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "The CIDP says the expansion is on-going under a national project; the county components are plans. No implementation report was read."
  },
  {
   "id": "SIA-P-099",
   "name": "Last mile connectivity on Ugunja-Sega-Ukwala",
   "aliases": [],
   "sector": "water_sanitation",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Ugunja, Sega, Ukwala",
      "doc_id": "GOV-01-PDF",
      "page": 170,
      "resolved_to": [
       {
        "ward_id": "ukwala"
       },
       {
        "constituency_id": "ugunja"
       }
      ],
      "unresolved_reason": "Sega is a town, not a ward; \"Ugunja\" is both a ward and a constituency; resolved to the constituency only"
     }
    ],
    "ward_ids": [
     "ukwala"
    ],
    "constituency_ids": [
     "ugenya",
     "ugunja"
    ],
    "countywide": false,
    "unresolved": [
     {
      "text": "Ugunja, Sega, Ukwala",
      "reason": "Sega is a town, not a ward; \"Ugunja\" is both a ward and a constituency; resolved to the constituency only"
     }
    ]
   },
   "amounts": [
    {
     "kind": "estimated_cost",
     "value": 482,
     "unit": "KSh million",
     "fy": "2023/24-2027/28",
     "doc_id": "GOV-01-PDF",
     "page": 170,
     "label_as_printed": "Cost",
     "note": "The capital-projects table prints the header \"Cost\" without a unit; read as KSh million, as in the flagship table header \"Estimated cost (M)\"."
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "planned",
   "status_source": {
    "doc_id": "GOV-01-PDF",
    "page": 170,
    "evidence_type": "county_development_plan",
    "as_at": "2024-01-24"
   },
   "last_evidence_date": "2024-01-24",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-01-PDF",
     "page": 170,
     "evidence_type": "county_development_plan",
     "as_at": "2024-01-24",
     "finding_id": null,
     "summary": "Listed in the CIDP 2023-2027 capital projects table.",
     "confidence": 5
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Plan entry only; no budget, contract or implementation evidence found in the sources read."
  },
  {
   "id": "SIA-P-100",
   "name": "Last mile connectivity on SIBOWASCO",
   "aliases": [],
   "sector": "water_sanitation",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Bondo and Siaya",
      "doc_id": "GOV-01-PDF",
      "page": 170,
      "resolved_to": [
       {
        "constituency_id": "bondo"
       }
      ],
      "unresolved_reason": "Siaya part: \"Siaya\" can mean the county, Siaya town or the Siaya/Alego Usonga sub-county; not resolved"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [
     "bondo"
    ],
    "countywide": false,
    "unresolved": [
     {
      "text": "Bondo and Siaya",
      "reason": "Siaya part: \"Siaya\" can mean the county, Siaya town or the Siaya/Alego Usonga sub-county; not resolved"
     }
    ]
   },
   "amounts": [
    {
     "kind": "estimated_cost",
     "value": 50,
     "unit": "KSh million",
     "fy": "2023/24-2027/28",
     "doc_id": "GOV-01-PDF",
     "page": 170,
     "label_as_printed": "Cost",
     "note": "The capital-projects table prints the header \"Cost\" without a unit; read as KSh million, as in the flagship table header \"Estimated cost (M)\"."
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "planned",
   "status_source": {
    "doc_id": "GOV-01-PDF",
    "page": 170,
    "evidence_type": "county_development_plan",
    "as_at": "2024-01-24"
   },
   "last_evidence_date": "2024-01-24",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-01-PDF",
     "page": 170,
     "evidence_type": "county_development_plan",
     "as_at": "2024-01-24",
     "finding_id": null,
     "summary": "Listed in the CIDP 2023-2027 capital projects table.",
     "confidence": 5
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Plan entry only; no budget, contract or implementation evidence found in the sources read."
  },
  {
   "id": "SIA-P-101",
   "name": "Augmentation of Yala intake",
   "aliases": [],
   "sector": "water_sanitation",
   "implementing_entity": "national_government",
   "location": {
    "as_printed": [
     {
      "text": "Yala",
      "doc_id": "GOV-01-PDF",
      "page": 170,
      "unresolved_reason": "Yala town; the ward is \"Yala Township\", not resolved from \"Yala\" alone"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Yala",
      "reason": "Yala town; the ward is \"Yala Township\", not resolved from \"Yala\" alone"
     }
    ]
   },
   "amounts": [
    {
     "kind": "estimated_cost",
     "value": 500,
     "unit": "KSh million",
     "fy": "2023/24-2027/28",
     "doc_id": "GOV-01-PDF",
     "page": 170,
     "label_as_printed": "Cost",
     "note": "The capital-projects table prints the header \"Cost\" without a unit; read as KSh million, as in the flagship table header \"Estimated cost (M)\"."
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "planned",
   "status_source": {
    "doc_id": "GOV-01-PDF",
    "page": 170,
    "evidence_type": "county_development_plan",
    "as_at": "2024-01-24"
   },
   "last_evidence_date": "2024-01-24",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-01-PDF",
     "page": 170,
     "evidence_type": "county_development_plan",
     "as_at": "2024-01-24",
     "finding_id": null,
     "summary": "Listed in the CIDP 2023-2027 capital projects table.",
     "confidence": 5
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Plan entry only; no budget, contract or implementation evidence found in the sources read."
  },
  {
   "id": "SIA-P-102",
   "name": "Wichlum water project",
   "aliases": [],
   "sector": "water_sanitation",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Bondo",
      "doc_id": "GOV-01-PDF",
      "page": 170,
      "resolved_to": [
       {
        "constituency_id": "bondo"
       }
      ]
     }
    ],
    "ward_ids": [],
    "constituency_ids": [
     "bondo"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "estimated_cost",
     "value": 50,
     "unit": "KSh million",
     "fy": "2023/24-2027/28",
     "doc_id": "GOV-01-PDF",
     "page": 170,
     "label_as_printed": "Cost",
     "note": "The capital-projects table prints the header \"Cost\" without a unit; read as KSh million, as in the flagship table header \"Estimated cost (M)\"."
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "planned",
   "status_source": {
    "doc_id": "GOV-01-PDF",
    "page": 170,
    "evidence_type": "county_development_plan",
    "as_at": "2024-01-24"
   },
   "last_evidence_date": "2024-01-24",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-01-PDF",
     "page": 170,
     "evidence_type": "county_development_plan",
     "as_at": "2024-01-24",
     "finding_id": null,
     "summary": "Listed in the CIDP 2023-2027 capital projects table.",
     "confidence": 5
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Plan entry only; no budget, contract or implementation evidence found in the sources read."
  },
  {
   "id": "SIA-P-103",
   "name": "Development irrigation infrastructure",
   "aliases": [],
   "sector": "agriculture_fisheries",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Alego, Ugenya",
      "doc_id": "GOV-01-PDF",
      "page": 170,
      "resolved_to": [
       {
        "constituency_id": "ugenya"
       }
      ],
      "unresolved_reason": "\"Alego\" alone is not a registry name (Alego Usonga has four Alego wards); not resolved"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [
     "ugenya"
    ],
    "countywide": false,
    "unresolved": [
     {
      "text": "Alego, Ugenya",
      "reason": "\"Alego\" alone is not a registry name (Alego Usonga has four Alego wards); not resolved"
     }
    ]
   },
   "amounts": [
    {
     "kind": "estimated_cost",
     "value": 280,
     "unit": "KSh million",
     "fy": "2023/24-2027/28",
     "doc_id": "GOV-01-PDF",
     "page": 170,
     "label_as_printed": "Cost",
     "note": "The capital-projects table prints the header \"Cost\" without a unit; read as KSh million, as in the flagship table header \"Estimated cost (M)\"."
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "planned",
   "status_source": {
    "doc_id": "GOV-01-PDF",
    "page": 170,
    "evidence_type": "county_development_plan",
    "as_at": "2024-01-24"
   },
   "last_evidence_date": "2024-01-24",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-01-PDF",
     "page": 170,
     "evidence_type": "county_development_plan",
     "as_at": "2024-01-24",
     "finding_id": null,
     "summary": "Listed in the CIDP 2023-2027 capital projects table.",
     "confidence": 5
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Plan entry only; no budget, contract or implementation evidence found in the sources read."
  },
  {
   "id": "SIA-P-104",
   "name": "Upgrading of airstrips",
   "aliases": [],
   "sector": "roads_transport",
   "implementing_entity": "county_and_partners",
   "location": {
    "as_printed": [
     {
      "text": "Sega, Gombe, Migwena",
      "doc_id": "GOV-01-PDF",
      "page": 171,
      "unresolved_reason": "place names that are not wards or constituencies"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Sega, Gombe, Migwena",
      "reason": "place names that are not wards or constituencies"
     }
    ]
   },
   "amounts": [
    {
     "kind": "estimated_cost",
     "value": 100,
     "unit": "KSh million",
     "fy": "2023/24-2027/28",
     "doc_id": "GOV-01-PDF",
     "page": 171,
     "label_as_printed": "Cost",
     "note": "The capital-projects table prints the header \"Cost\" without a unit; read as KSh million, as in the flagship table header \"Estimated cost (M)\"."
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "planned",
   "status_source": {
    "doc_id": "GOV-01-PDF",
    "page": 171,
    "evidence_type": "county_development_plan",
    "as_at": "2024-01-24"
   },
   "last_evidence_date": "2024-01-24",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-01-PDF",
     "page": 171,
     "evidence_type": "county_development_plan",
     "as_at": "2024-01-24",
     "finding_id": null,
     "summary": "Listed in the CIDP 2023-2027 capital projects table.",
     "confidence": 5
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Plan entry only; no budget, contract or implementation evidence found in the sources read."
  },
  {
   "id": "SIA-P-105",
   "name": "Establishment of Asembo bay feeder port",
   "aliases": [],
   "sector": "roads_transport",
   "implementing_entity": "county_and_partners",
   "location": {
    "as_printed": [
     {
      "text": "Rarieda",
      "doc_id": "GOV-01-PDF",
      "page": 171,
      "resolved_to": [
       {
        "constituency_id": "rarieda"
       }
      ]
     }
    ],
    "ward_ids": [],
    "constituency_ids": [
     "rarieda"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "estimated_cost",
     "value": 30,
     "unit": "KSh million",
     "fy": "2023/24-2027/28",
     "doc_id": "GOV-01-PDF",
     "page": 171,
     "label_as_printed": "Cost",
     "note": "The capital-projects table prints the header \"Cost\" without a unit; read as KSh million, as in the flagship table header \"Estimated cost (M)\"."
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "planned",
   "status_source": {
    "doc_id": "GOV-01-PDF",
    "page": 171,
    "evidence_type": "county_development_plan",
    "as_at": "2024-01-24"
   },
   "last_evidence_date": "2024-01-24",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-01-PDF",
     "page": 171,
     "evidence_type": "county_development_plan",
     "as_at": "2024-01-24",
     "finding_id": null,
     "summary": "Listed in the CIDP 2023-2027 capital projects table.",
     "confidence": 5
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Plan entry only; no budget, contract or implementation evidence found in the sources read."
  },
  {
   "id": "SIA-P-106",
   "name": "Construction of energy centres",
   "aliases": [],
   "sector": "energy_lighting",
   "implementing_entity": "county_and_partners",
   "location": {
    "as_printed": [
     {
      "text": "Siaya, Bondo and Ugunja",
      "doc_id": "GOV-01-PDF",
      "page": 171,
      "resolved_to": [
       {
        "constituency_id": "bondo"
       },
       {
        "constituency_id": "ugunja"
       }
      ],
      "unresolved_reason": "Siaya part: \"Siaya\" can mean the county, Siaya town or the Siaya/Alego Usonga sub-county; not resolved; \"Ugunja\" is both a ward and a constituency; resolved to the constituency only"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [
     "bondo",
     "ugunja"
    ],
    "countywide": false,
    "unresolved": [
     {
      "text": "Siaya, Bondo and Ugunja",
      "reason": "Siaya part: \"Siaya\" can mean the county, Siaya town or the Siaya/Alego Usonga sub-county; not resolved; \"Ugunja\" is both a ward and a constituency; resolved to the constituency only"
     }
    ]
   },
   "amounts": [
    {
     "kind": "estimated_cost",
     "value": 30,
     "unit": "KSh million",
     "fy": "2023/24-2027/28",
     "doc_id": "GOV-01-PDF",
     "page": 171,
     "label_as_printed": "Cost",
     "note": "The capital-projects table prints the header \"Cost\" without a unit; read as KSh million, as in the flagship table header \"Estimated cost (M)\"."
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "planned",
   "status_source": {
    "doc_id": "GOV-01-PDF",
    "page": 171,
    "evidence_type": "county_development_plan",
    "as_at": "2024-01-24"
   },
   "last_evidence_date": "2024-01-24",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-01-PDF",
     "page": 171,
     "evidence_type": "county_development_plan",
     "as_at": "2024-01-24",
     "finding_id": null,
     "summary": "Listed in the CIDP 2023-2027 capital projects table.",
     "confidence": 5
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Plan entry only; no budget, contract or implementation evidence found in the sources read."
  },
  {
   "id": "SIA-P-107",
   "name": "Construction of hospital complexes",
   "aliases": [],
   "sector": "health",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Siaya and Bondo",
      "doc_id": "GOV-01-PDF",
      "page": 171,
      "resolved_to": [
       {
        "constituency_id": "bondo"
       }
      ],
      "unresolved_reason": "Siaya part: \"Siaya\" can mean the county, Siaya town or the Siaya/Alego Usonga sub-county; not resolved"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [
     "bondo"
    ],
    "countywide": false,
    "unresolved": [
     {
      "text": "Siaya and Bondo",
      "reason": "Siaya part: \"Siaya\" can mean the county, Siaya town or the Siaya/Alego Usonga sub-county; not resolved"
     }
    ]
   },
   "amounts": [
    {
     "kind": "estimated_cost",
     "value": 122,
     "unit": "KSh million",
     "fy": "2023/24-2027/28",
     "doc_id": "GOV-01-PDF",
     "page": 171,
     "label_as_printed": "Cost",
     "note": "The capital-projects table prints the header \"Cost\" without a unit; read as KSh million, as in the flagship table header \"Estimated cost (M)\"."
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "planned",
   "status_source": {
    "doc_id": "GOV-01-PDF",
    "page": 171,
    "evidence_type": "county_development_plan",
    "as_at": "2024-01-24"
   },
   "last_evidence_date": "2024-01-24",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-01-PDF",
     "page": 171,
     "evidence_type": "county_development_plan",
     "as_at": "2024-01-24",
     "finding_id": null,
     "summary": "Listed in the CIDP 2023-2027 capital projects table.",
     "confidence": 5
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Plan entry only; no budget, contract or implementation evidence found in the sources read."
  },
  {
   "id": "SIA-P-108",
   "name": "KEMRI -Siaya County Research and Biotech Complex",
   "aliases": [],
   "sector": "health",
   "implementing_entity": "county_and_partners",
   "location": {
    "as_printed": [
     {
      "text": "Siaya",
      "doc_id": "GOV-01-PDF",
      "page": 171,
      "unresolved_reason": "\"Siaya\" can mean the county, Siaya town or the Siaya/Alego Usonga sub-county; not resolved"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Siaya",
      "reason": "\"Siaya\" can mean the county, Siaya town or the Siaya/Alego Usonga sub-county; not resolved"
     }
    ]
   },
   "amounts": [
    {
     "kind": "estimated_cost",
     "value": 12400,
     "unit": "KSh million",
     "fy": "2023/24-2027/28",
     "doc_id": "GOV-01-PDF",
     "page": 171,
     "label_as_printed": "Cost",
     "note": "The capital-projects table prints the header \"Cost\" without a unit; read as KSh million, as in the flagship table header \"Estimated cost (M)\"."
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "planned",
   "status_source": {
    "doc_id": "GOV-01-PDF",
    "page": 171,
    "evidence_type": "county_development_plan",
    "as_at": "2024-01-24"
   },
   "last_evidence_date": "2024-01-24",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-01-PDF",
     "page": 171,
     "evidence_type": "county_development_plan",
     "as_at": "2024-01-24",
     "finding_id": null,
     "summary": "Listed in the CIDP 2023-2027 capital projects table.",
     "confidence": 5
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Plan entry only; no budget, contract or implementation evidence found in the sources read."
  },
  {
   "id": "SIA-P-109",
   "name": "Construction and equipping of MRI Centre",
   "aliases": [],
   "sector": "health",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Siaya",
      "doc_id": "GOV-01-PDF",
      "page": 171,
      "unresolved_reason": "\"Siaya\" can mean the county, Siaya town or the Siaya/Alego Usonga sub-county; not resolved"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Siaya",
      "reason": "\"Siaya\" can mean the county, Siaya town or the Siaya/Alego Usonga sub-county; not resolved"
     }
    ]
   },
   "amounts": [
    {
     "kind": "estimated_cost",
     "value": 45,
     "unit": "KSh million",
     "fy": "2023/24-2027/28",
     "doc_id": "GOV-01-PDF",
     "page": 171,
     "label_as_printed": "Cost",
     "note": "The capital-projects table prints the header \"Cost\" without a unit; read as KSh million, as in the flagship table header \"Estimated cost (M)\"."
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "planned",
   "status_source": {
    "doc_id": "GOV-01-PDF",
    "page": 171,
    "evidence_type": "county_development_plan",
    "as_at": "2024-01-24"
   },
   "last_evidence_date": "2024-01-24",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-01-PDF",
     "page": 171,
     "evidence_type": "county_development_plan",
     "as_at": "2024-01-24",
     "finding_id": null,
     "summary": "Listed in the CIDP 2023-2027 capital projects table.",
     "confidence": 5
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Plan entry only; no budget, contract or implementation evidence found in the sources read."
  },
  {
   "id": "SIA-P-110",
   "name": "Establishment of Industrial Park",
   "aliases": [],
   "sector": "industry",
   "implementing_entity": "county_and_partners",
   "location": {
    "as_printed": [
     {
      "text": "Siaya",
      "doc_id": "GOV-01-PDF",
      "page": 172,
      "unresolved_reason": "\"Siaya\" can mean the county, Siaya town or the Siaya/Alego Usonga sub-county; not resolved"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Siaya",
      "reason": "\"Siaya\" can mean the county, Siaya town or the Siaya/Alego Usonga sub-county; not resolved"
     }
    ]
   },
   "amounts": [
    {
     "kind": "estimated_cost",
     "value": 200,
     "unit": "KSh million",
     "fy": "2023/24-2027/28",
     "doc_id": "GOV-01-PDF",
     "page": 172,
     "label_as_printed": "Cost",
     "note": "The capital-projects table prints the header \"Cost\" without a unit; read as KSh million, as in the flagship table header \"Estimated cost (M)\"."
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "planned",
   "status_source": {
    "doc_id": "GOV-01-PDF",
    "page": 172,
    "evidence_type": "county_development_plan",
    "as_at": "2024-01-24"
   },
   "last_evidence_date": "2024-01-24",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-01-PDF",
     "page": 172,
     "evidence_type": "county_development_plan",
     "as_at": "2024-01-24",
     "finding_id": null,
     "summary": "Listed in the CIDP 2023-2027 capital projects table.",
     "confidence": 5
    }
   ],
   "conflicts": [],
   "related_project_ids": [
    "SIA-P-030"
   ],
   "status_note": "Plan entry only; no budget, contract or implementation evidence found in the sources read."
  },
  {
   "id": "SIA-P-111",
   "name": "Development of Got Ramogi",
   "aliases": [],
   "sector": "sports_culture_tourism",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Bondo",
      "doc_id": "GOV-01-PDF",
      "page": 172,
      "resolved_to": [
       {
        "constituency_id": "bondo"
       }
      ]
     }
    ],
    "ward_ids": [],
    "constituency_ids": [
     "bondo"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "estimated_cost",
     "value": 152,
     "unit": "KSh million",
     "fy": "2023/24-2027/28",
     "doc_id": "GOV-01-PDF",
     "page": 172,
     "label_as_printed": "Cost",
     "note": "The capital-projects table prints the header \"Cost\" without a unit; read as KSh million, as in the flagship table header \"Estimated cost (M)\"."
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "planned",
   "status_source": {
    "doc_id": "GOV-01-PDF",
    "page": 172,
    "evidence_type": "county_development_plan",
    "as_at": "2024-01-24"
   },
   "last_evidence_date": "2024-01-24",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-01-PDF",
     "page": 172,
     "evidence_type": "county_development_plan",
     "as_at": "2024-01-24",
     "finding_id": null,
     "summary": "Listed in the CIDP 2023-2027 capital projects table.",
     "confidence": 5
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Plan entry only; no budget, contract or implementation evidence found in the sources read."
  },
  {
   "id": "SIA-P-112",
   "name": "Construction of phase II Siaya Stadium",
   "aliases": [],
   "sector": "sports_culture_tourism",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Siaya",
      "doc_id": "GOV-01-PDF",
      "page": 172,
      "unresolved_reason": "\"Siaya\" can mean the county, Siaya town or the Siaya/Alego Usonga sub-county; not resolved"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Siaya",
      "reason": "\"Siaya\" can mean the county, Siaya town or the Siaya/Alego Usonga sub-county; not resolved"
     }
    ]
   },
   "amounts": [
    {
     "kind": "estimated_cost",
     "value": 200,
     "unit": "KSh million",
     "fy": "2023/24-2027/28",
     "doc_id": "GOV-01-PDF",
     "page": 172,
     "label_as_printed": "Cost",
     "note": "The capital-projects table prints the header \"Cost\" without a unit; read as KSh million, as in the flagship table header \"Estimated cost (M)\"."
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "planned",
   "status_source": {
    "doc_id": "GOV-01-PDF",
    "page": 172,
    "evidence_type": "county_development_plan",
    "as_at": "2024-01-24"
   },
   "last_evidence_date": "2024-01-24",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-01-PDF",
     "page": 172,
     "evidence_type": "county_development_plan",
     "as_at": "2024-01-24",
     "finding_id": null,
     "summary": "Listed in the CIDP 2023-2027 capital projects table.",
     "confidence": 5
    }
   ],
   "conflicts": [],
   "related_project_ids": [
    "SIA-P-001"
   ],
   "status_note": "Plan entry only; no budget, contract or implementation evidence found in the sources read."
  },
  {
   "id": "SIA-P-113",
   "name": "Construction of Migwena talent Centre",
   "aliases": [],
   "sector": "sports_culture_tourism",
   "implementing_entity": "county_and_partners",
   "location": {
    "as_printed": [
     {
      "text": "Bondo",
      "doc_id": "GOV-01-PDF",
      "page": 172,
      "resolved_to": [
       {
        "constituency_id": "bondo"
       }
      ]
     }
    ],
    "ward_ids": [],
    "constituency_ids": [
     "bondo"
    ],
    "countywide": false,
    "unresolved": []
   },
   "amounts": [
    {
     "kind": "estimated_cost",
     "value": 539,
     "unit": "KSh million",
     "fy": "2023/24-2027/28",
     "doc_id": "GOV-01-PDF",
     "page": 172,
     "label_as_printed": "Cost",
     "note": "The capital-projects table prints the header \"Cost\" without a unit; read as KSh million, as in the flagship table header \"Estimated cost (M)\"."
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "planned",
   "status_source": {
    "doc_id": "GOV-01-PDF",
    "page": 172,
    "evidence_type": "county_development_plan",
    "as_at": "2024-01-24"
   },
   "last_evidence_date": "2024-01-24",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-01-PDF",
     "page": 172,
     "evidence_type": "county_development_plan",
     "as_at": "2024-01-24",
     "finding_id": null,
     "summary": "Listed in the CIDP 2023-2027 capital projects table.",
     "confidence": 5
    }
   ],
   "conflicts": [],
   "related_project_ids": [
    "SIA-P-015",
    "SIA-P-028"
   ],
   "status_note": "Plan entry only; no budget, contract or implementation evidence found in the sources read."
  },
  {
   "id": "SIA-P-114",
   "name": "Construction of office complex",
   "aliases": [],
   "sector": "governance_offices",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Siaya",
      "doc_id": "GOV-01-PDF",
      "page": 172,
      "unresolved_reason": "\"Siaya\" can mean the county, Siaya town or the Siaya/Alego Usonga sub-county; not resolved"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Siaya",
      "reason": "\"Siaya\" can mean the county, Siaya town or the Siaya/Alego Usonga sub-county; not resolved"
     }
    ]
   },
   "amounts": [
    {
     "kind": "estimated_cost",
     "value": 440,
     "unit": "KSh million",
     "fy": "2023/24-2027/28",
     "doc_id": "GOV-01-PDF",
     "page": 172,
     "label_as_printed": "Cost",
     "note": "The capital-projects table prints the header \"Cost\" without a unit; read as KSh million, as in the flagship table header \"Estimated cost (M)\"."
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "planned",
   "status_source": {
    "doc_id": "GOV-01-PDF",
    "page": 172,
    "evidence_type": "county_development_plan",
    "as_at": "2024-01-24"
   },
   "last_evidence_date": "2024-01-24",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-01-PDF",
     "page": 172,
     "evidence_type": "county_development_plan",
     "as_at": "2024-01-24",
     "finding_id": null,
     "summary": "Listed in the CIDP 2023-2027 capital projects table.",
     "confidence": 5
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Plan entry only; no budget, contract or implementation evidence found in the sources read."
  },
  {
   "id": "SIA-P-115",
   "name": "Construction of state officer residence (Governor, Deputy Governor)",
   "aliases": [],
   "sector": "governance_offices",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Siaya",
      "doc_id": "GOV-01-PDF",
      "page": 172,
      "unresolved_reason": "\"Siaya\" can mean the county, Siaya town or the Siaya/Alego Usonga sub-county; not resolved"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Siaya",
      "reason": "\"Siaya\" can mean the county, Siaya town or the Siaya/Alego Usonga sub-county; not resolved"
     }
    ]
   },
   "amounts": [
    {
     "kind": "estimated_cost",
     "value": 80,
     "unit": "KSh million",
     "fy": "2023/24-2027/28",
     "doc_id": "GOV-01-PDF",
     "page": 172,
     "label_as_printed": "Cost",
     "note": "The capital-projects table prints the header \"Cost\" without a unit; read as KSh million, as in the flagship table header \"Estimated cost (M)\"."
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "planned",
   "status_source": {
    "doc_id": "GOV-01-PDF",
    "page": 172,
    "evidence_type": "county_development_plan",
    "as_at": "2024-01-24"
   },
   "last_evidence_date": "2024-01-24",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-01-PDF",
     "page": 172,
     "evidence_type": "county_development_plan",
     "as_at": "2024-01-24",
     "finding_id": null,
     "summary": "Listed in the CIDP 2023-2027 capital projects table (the residence is for the offices, no person is named).",
     "confidence": 5
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Plan entry only; no budget, contract or implementation evidence found in the sources read."
  },
  {
   "id": "SIA-P-116",
   "name": "Establishment of L.Kanyaboli Eco-city",
   "aliases": [],
   "sector": "urban_housing_lands",
   "implementing_entity": "county_and_partners",
   "location": {
    "as_printed": [
     {
      "text": "Siaya",
      "doc_id": "GOV-01-PDF",
      "page": 172,
      "unresolved_reason": "\"Siaya\" can mean the county, Siaya town or the Siaya/Alego Usonga sub-county; not resolved"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Siaya",
      "reason": "\"Siaya\" can mean the county, Siaya town or the Siaya/Alego Usonga sub-county; not resolved"
     }
    ]
   },
   "amounts": [
    {
     "kind": "estimated_cost",
     "value": 500,
     "unit": "KSh million",
     "fy": "2023/24-2027/28",
     "doc_id": "GOV-01-PDF",
     "page": 172,
     "label_as_printed": "Cost",
     "note": "The capital-projects table prints the header \"Cost\" without a unit; read as KSh million, as in the flagship table header \"Estimated cost (M)\"."
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "planned",
   "status_source": {
    "doc_id": "GOV-01-PDF",
    "page": 172,
    "evidence_type": "county_development_plan",
    "as_at": "2024-01-24"
   },
   "last_evidence_date": "2024-01-24",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-01-PDF",
     "page": 172,
     "evidence_type": "county_development_plan",
     "as_at": "2024-01-24",
     "finding_id": null,
     "summary": "Listed in the CIDP 2023-2027 capital projects table.",
     "confidence": 5
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Plan entry only; no budget, contract or implementation evidence found in the sources read."
  },
  {
   "id": "SIA-P-117",
   "name": "Construction of speaker's residence",
   "aliases": [],
   "sector": "governance_offices",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Siaya",
      "doc_id": "GOV-01-PDF",
      "page": 173,
      "unresolved_reason": "\"Siaya\" can mean the county, Siaya town or the Siaya/Alego Usonga sub-county; not resolved"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Siaya",
      "reason": "\"Siaya\" can mean the county, Siaya town or the Siaya/Alego Usonga sub-county; not resolved"
     }
    ]
   },
   "amounts": [
    {
     "kind": "estimated_cost",
     "value": 35,
     "unit": "KSh million",
     "fy": "2023/24-2027/28",
     "doc_id": "GOV-01-PDF",
     "page": 173,
     "label_as_printed": "Cost",
     "note": "The capital-projects table prints the header \"Cost\" without a unit; read as KSh million, as in the flagship table header \"Estimated cost (M)\"."
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "planned",
   "status_source": {
    "doc_id": "GOV-01-PDF",
    "page": 173,
    "evidence_type": "county_development_plan",
    "as_at": "2024-01-24"
   },
   "last_evidence_date": "2024-01-24",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-01-PDF",
     "page": 173,
     "evidence_type": "county_development_plan",
     "as_at": "2024-01-24",
     "finding_id": null,
     "summary": "Listed in the CIDP 2023-2027 capital projects table.",
     "confidence": 5
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Plan entry only; no budget, contract or implementation evidence found in the sources read."
  },
  {
   "id": "SIA-P-118",
   "name": "Construction of County Assembly's complex",
   "aliases": [],
   "sector": "governance_offices",
   "implementing_entity": "county_executive",
   "location": {
    "as_printed": [
     {
      "text": "Siaya",
      "doc_id": "GOV-01-PDF",
      "page": 173,
      "unresolved_reason": "\"Siaya\" can mean the county, Siaya town or the Siaya/Alego Usonga sub-county; not resolved"
     }
    ],
    "ward_ids": [],
    "constituency_ids": [],
    "countywide": false,
    "unresolved": [
     {
      "text": "Siaya",
      "reason": "\"Siaya\" can mean the county, Siaya town or the Siaya/Alego Usonga sub-county; not resolved"
     }
    ]
   },
   "amounts": [
    {
     "kind": "estimated_cost",
     "value": 396,
     "unit": "KSh million",
     "fy": "2023/24-2027/28",
     "doc_id": "GOV-01-PDF",
     "page": 173,
     "label_as_printed": "Cost",
     "note": "The capital-projects table prints the header \"Cost\" without a unit; read as KSh million, as in the flagship table header \"Estimated cost (M)\"."
    }
   ],
   "contract": {
    "reference": null,
    "contractor_reference": null,
    "signed": null,
    "start": null,
    "expected_completion": null
   },
   "status": "planned",
   "status_source": {
    "doc_id": "GOV-01-PDF",
    "page": 173,
    "evidence_type": "county_development_plan",
    "as_at": "2024-01-24"
   },
   "last_evidence_date": "2024-01-24",
   "audit_finding_ids": [],
   "evidence": [
    {
     "doc_id": "GOV-01-PDF",
     "page": 173,
     "evidence_type": "county_development_plan",
     "as_at": "2024-01-24",
     "finding_id": null,
     "summary": "Listed in the CIDP 2023-2027 capital projects table.",
     "confidence": 5
    }
   ],
   "conflicts": [],
   "related_project_ids": [],
   "status_note": "Plan entry only; no budget, contract or implementation evidence found in the sources read."
  }
 ],
 "gaps": [
  "County Annual Development Plan 2025/26 (GOV-04 ADP) not obtained: only its public participation report was found. Its Annex 4 lists several hundred ward proposals (ranked wishes, not approved projects); they are not entered as projects.",
  "County budget implementation reports for FY 2024/25 (GOV-02 Q1 to Q4) and Q4 FY 2023/24 have no project annexes; only FY 2025/26 reports do.",
  "Controller of Budget Siaya tables for FY 2014/15 to 2017/18 and FY 2019/20 were not read for this register.",
  "Executive audit reports for FY 2016/17 to 2018/19 were not found (see data/siaya-audits.json gaps), so early stadium years rest on CoB county data only.",
  "No physical verification by Takwimu. Only one project (SIA-P-038) has an independent statement of completion.",
  "CIDP capital projects are programme lines; countywide lines (subsidies, routine maintenance, ECD, VTC and so on) are not entered.",
  "BIR rows \"Preparation of Valuation Roll\" (a study) and CoB FY 2022/23 rows for seeds, fertiliser, tractors and land acquisition (purchases) are not entered."
 ],
 "editorial_review": {
  "rule": "Every value not listed here is \"Provisional: awaiting editorial review\". Rejected values are removed (null) and listed with the rationale. Register: data/reviews.json; procedure: docs/editorial/review-sop.md.",
  "counts": {
   "total": 118,
   "approved": 0,
   "pending": 118,
   "rejected": 0,
   "disputed": 23,
   "superseded": 0,
   "unanchored": 0
  },
  "values": {
   "SIA-P-001": {
    "state": "DISPUTED",
    "label": "Disputed: see the conflict register"
   },
   "SIA-P-003": {
    "state": "DISPUTED",
    "label": "Disputed: see the conflict register"
   },
   "SIA-P-007": {
    "state": "DISPUTED",
    "label": "Disputed: see the conflict register"
   },
   "SIA-P-008": {
    "state": "DISPUTED",
    "label": "Disputed: see the conflict register"
   },
   "SIA-P-009": {
    "state": "DISPUTED",
    "label": "Disputed: see the conflict register"
   },
   "SIA-P-010": {
    "state": "DISPUTED",
    "label": "Disputed: see the conflict register"
   },
   "SIA-P-011": {
    "state": "DISPUTED",
    "label": "Disputed: see the conflict register"
   },
   "SIA-P-018": {
    "state": "DISPUTED",
    "label": "Disputed: see the conflict register"
   },
   "SIA-P-027": {
    "state": "DISPUTED",
    "label": "Disputed: see the conflict register"
   },
   "SIA-P-028": {
    "state": "DISPUTED",
    "label": "Disputed: see the conflict register"
   },
   "SIA-P-030": {
    "state": "DISPUTED",
    "label": "Disputed: see the conflict register"
   },
   "SIA-P-036": {
    "state": "DISPUTED",
    "label": "Disputed: see the conflict register"
   },
   "SIA-P-037": {
    "state": "DISPUTED",
    "label": "Disputed: see the conflict register"
   },
   "SIA-P-041": {
    "state": "DISPUTED",
    "label": "Disputed: see the conflict register"
   },
   "SIA-P-042": {
    "state": "DISPUTED",
    "label": "Disputed: see the conflict register"
   },
   "SIA-P-043": {
    "state": "DISPUTED",
    "label": "Disputed: see the conflict register"
   },
   "SIA-P-046": {
    "state": "DISPUTED",
    "label": "Disputed: see the conflict register"
   },
   "SIA-P-056": {
    "state": "DISPUTED",
    "label": "Disputed: see the conflict register"
   },
   "SIA-P-057": {
    "state": "DISPUTED",
    "label": "Disputed: see the conflict register"
   },
   "SIA-P-058": {
    "state": "DISPUTED",
    "label": "Disputed: see the conflict register"
   },
   "SIA-P-086": {
    "state": "DISPUTED",
    "label": "Disputed: see the conflict register"
   },
   "SIA-P-087": {
    "state": "DISPUTED",
    "label": "Disputed: see the conflict register"
   },
   "SIA-P-094": {
    "state": "DISPUTED",
    "label": "Disputed: see the conflict register"
   }
  }
 }
}