Development project register

118 county development projects named in the county’s plans and budget reports, the Controller of Budget’s reports and the Auditor-General’s reports, with what each source says about progress. Where the county’s report and the auditor’s inspection differ, both are shown.

How to read this page

Provisional: awaiting editorial review Editorial review of 118 values: 0 approved, 118 pending, 0 rejected. 23 are disputed between sources (both readings kept). What this means

The eight status states used

Planned (20)
in a plan (CIDP) with no later evidence.
Active (13)
works or payments under way and not past the expected completion date in the evidence.
Delayed (25)
incomplete after the expected completion date, from the audit or from the county's own dates.
Suspended (16)
listed as stalled by the county, or works found stopped or abandoned by the auditor.
Completed reported (23)
the county (directly, in a CoB table, or as quoted by the auditor) reports completion or 100%.
Completed, independently verified (1)
the Auditor-General (or another independent party) states on inspection that the works were complete.
Cancelled (4)
contract terminated or budget removed.
Unknown (16)
only spending, or conflicting or incomplete evidence.

Where the county’s report and the audit differ: two examples

Tarmacking of Opoda-Bondo township road (SIA-P-018)

  • County (CoB FY 2021/22) reports 100% complete and in use; the FY 2021/22 audit estimates 20% executed with the contractor off site.
  • Printed as North Sakwa, North Uyoma and South Sakwa in different rows and years.
  • CoB FY 2020/21 budget KSh 152,000,000 against an audited contract cost of KSh 52,805,116.

Supply, delivery, installation and commissioning of mortuary cold-room plant at Bondo Sub-County Hospital (SIA-P-036)

  • County reports 100% at 30 June 2025; the October 2025 audit found the plant not installed.

Projects by sector, ward and status

Projects by status: all sectors, all wards and county-wide

Unit: projects.
projects0102030PlannedActiveDelayedSuspendedCompleted reportedCompleted, independently verifiedCancelledUnknown
View as table
Projects by status, all sectors, all wards and county-wide
PeriodProjects (projects)
Planned20
Active13
Delayed25
Suspended16
Completed reported23
Completed, independently verified1
Cancelled4
Unknown16

Showing 118 of 118 projects

  1. Construction of Siaya County Stadium

    SIA-P-001DelayedSports, culture and tourismSiaya Township

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 55 (audit documentary review). Latest evidence 2024-08-30. Not reported complete by any source; the latest independent evidence (FY 2023/24 audit) records nine extensions. A separate completion contract is SIA-P for "Completion of the Siaya stadium".

    Reported beside audit-found, where sources differ
    Reported by the county or the Controller of Budget
    Found by the Auditor-General
    Where the sources differ
    • Audits print KSh 394,661,767 (original), 488,716,823 (revised) and 524,229,273 (with roof contract); CoB FY 2023/24 prints 424,872,927.
    • FY 2020/21: CoB (county data) KSh 117,602,147 against audit KSh 80,254,180 + 14,648,670. FY 2021/22: CoB KSh 67,093,742 against audit KSh 57,999,787.

    Audit findings: audit-2020-21-21, audit-2021-22-26, audit-2022-23-22, audit-2023-24-29

    Amounts as printed (19)
  2. Installation of three-phase electricity power at the Siaya Stadium

    SIA-P-002DelayedEnergy and lightingPlace as printed: Siaya Stadium

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 53 (audit physical verification). Latest evidence 2024.

    Reported beside audit-found
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General

    Audit findings: audit-2023-24-25

    Amounts as printed (1)
  3. Installation of stadium VIP seats

    SIA-P-003Completed reportedSports, culture and tourismPlace as printed: Executive

    Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483 (cob report county data). Latest evidence 2025-06-30. Completion is as reported by the county; no independent check is recorded.

    Reported beside audit-found, where sources differ
    Reported by the county or the Controller of Budget
    Found by the Auditor-General
    Where the sources differ
    • The county reports 100% (30 June 2025); the earlier FY 2023/24 audit inspection counted 45 fewer foldable seats than contracted. No independent check after the county report.

    Audit findings: audit-2023-24-26

    Amounts as printed (4)
  4. Supply and installation of stadium lighting mast for the proposed stadium for the County Government of Siaya

    SIA-P-004Completed reportedEnergy and lightingPlace as printed: Executive

    Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483 (cob report county data). Latest evidence 2025-06-30. Completion is as reported by the county; no independent check is recorded.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (2)
  5. Proposed installation of Tartan on the running track

    SIA-P-005DelayedSports, culture and tourismPlace as printed: Executive

    Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483 (cob report county data). Latest evidence 2025-06-30. Delayed on the county's own dates: 70% at 30 June 2025 against an expected completion of June 2024. The table does not say which track.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (3)
  6. Completion of the Siaya stadium

    SIA-P-006Completed reportedSports, culture and tourismPlace as printed: Executive

    Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483 (cob report county data). Latest evidence 2025-06-30. Completion is as reported by the county; no independent check is recorded. A completion contract reported at 100% by the county. Whether the stadium as a whole is complete has not been independently checked.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (2)
  7. Construction of Siaya Bus Park

    SIA-P-007CancelledRoads and transportPlace as printed: Siaya Town

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 46 (audit physical verification). Latest evidence 2023-11. Contract terminated 2 June 2023; no later source on re-tendering.

    Reported beside audit-found, where sources differ
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General
    Where the sources differ
    • FY 2021/22 audit says awarded in March 2020; FY 2022/23 audit says contract entered on 7 August 2020.

    Audit findings: audit-2021-22-31, audit-2022-23-17

    Amounts as printed (3)
  8. Construction of Haudinga Sheltered Workshop in Ukwala

    SIA-P-008DelayedSocial servicesUkwala

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 38 (audit physical verification). Latest evidence 2021-11.

    Reported beside audit-found, where sources differ
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General
    Where the sources differ
    • Management reported completion and handover; the audit inspection found it incomplete.

    Audit findings: audit-2020-21-12

    Amounts as printed (2)
  9. Construction of Nyasanda Sheltered Workshop in Ugunja

    SIA-P-009DelayedSocial servicesPlace as printed: Nyasanda Sheltered Workshop in Ugunja

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 38 (audit physical verification). Latest evidence 2021-11.

    Reported beside audit-found, where sources differ
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General
    Where the sources differ
    • Management reported completion; the audit found items not done.

    Audit findings: audit-2020-21-13

    Amounts as printed (2)
  10. Construction of Nyamnina Youth Polytechnic

    SIA-P-010DelayedEducationPlace as printed: not stated

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 38 (audit physical verification). Latest evidence 2021-11.

    Reported beside audit-found, where sources differ
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General
    Where the sources differ
    • County completion certificate (17 Feb 2021) against an incomplete finding at inspection.

    Audit findings: audit-2020-21-14

    Amounts as printed (2)
  11. Renovations at Odera Akang'o Campus (works at Directors Office)

    SIA-P-011DelayedEducationPlace as printed: not stated

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 39 (audit physical verification). Latest evidence 2021-11.

    Reported beside audit-found, where sources differ
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General
    Where the sources differ
    • Practical completion certificate (10 Feb 2021) against incomplete works at inspection.

    Audit findings: audit-2020-21-15

    Amounts as printed (3)
  12. Construction of a laboratory at Obaga West Asembo Health Centre

    SIA-P-012UnknownHealthWest Asembo

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 39 (audit physical verification). Latest evidence 2021-11. The laboratory was built with deviations from the bill of quantities; no source states completion.

    Reported beside audit-found
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General

    Audit findings: audit-2020-21-17

    Amounts as printed (1)
  13. Maintenance of Maira Othatch Road and Bar Okwiri Kayouth roads

    SIA-P-013UnknownRoads and transportPlace as printed: not stated

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 40 (audit physical verification). Latest evidence 2021-11. Management says rectified; not verified by any source.

    Reported beside audit-found
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General

    Audit findings: audit-2020-21-18

    Amounts as printed (1)
  14. Rehabilitation of Siaya Slaughterhouse

    SIA-P-014DelayedAgriculture and fisheriesPlace as printed: Siaya

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 40 (audit physical verification). Latest evidence 2021-11.

    Reported beside audit-found
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General

    Audit findings: audit-2020-21-19

    Amounts as printed (2)
  15. Construction of Migwena Sports Stadium (2017 contract)

    SIA-P-015CancelledSports, culture and tourismPlace as printed: not stated

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 40 (audit physical verification). Latest evidence 2021-11.

    Reported beside audit-found
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General

    Audit findings: audit-2020-21-20

    Amounts as printed (2)
  16. Drainage, grading, gravelling and dozing of Kwaweya Yenga Nyalula Udura Kolum road (12 km)

    SIA-P-016DelayedRoads and transportPlace as printed: not stated

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 53 (audit physical verification). Latest evidence 2022-07-27. Incomplete at verification; no later source.

    Reported beside audit-found
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General

    Audit findings: audit-2021-22-29

    Amounts as printed (1)
  17. Repairs and maintenance of Boro-Katondi Road, Ogunga Road and Segere-Ouru Road

    SIA-P-017UnknownRoads and transportPlace as printed: not stated

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 53 (audit physical verification). Latest evidence 2022-11-10.

    Reported beside audit-found
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General

    Audit findings: audit-2021-22-30

    Amounts as printed (1)
  18. Tarmacking of Opoda-Bondo township road

    SIA-P-018DelayedRoads and transportNorth Sakwa, North Uyoma, South Sakwa

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 53 (audit physical verification). Latest evidence 2022-06-30.

    Reported beside audit-found, where sources differ
    Reported by the county or the Controller of Budget
    Found by the Auditor-General
    Where the sources differ
    • County (CoB FY 2021/22) reports 100% complete and in use; the FY 2021/22 audit estimates 20% executed with the contractor off site.
    • Printed as North Sakwa, North Uyoma and South Sakwa in different rows and years.
    • CoB FY 2020/21 budget KSh 152,000,000 against an audited contract cost of KSh 52,805,116.
    Amounts as printed (5)
  19. Construction of five ECD classrooms (Mahero, Kirindo, Ninga, Nyadheho and Nyabondo primary schools)

    SIA-P-019DelayedEducationPlace as printed: Mahero, Kirindo, Ninga, Nyadheho and Nyabondo Primary Schools

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 54 (audit physical verification). Latest evidence 2022.

    Reported beside audit-found
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General

    Audit findings: audit-2021-22-32

    Amounts as printed (2)
  20. Construction of Early Childhood Development (ECD) block at Kirindo primary school

    SIA-P-020SuspendedEducationPlace as printed: Kirindo primary school

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 46 (audit physical verification). Latest evidence 2023-11.

    Reported beside audit-found
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General

    Audit findings: audit-2021-22-32, audit-2022-23-16

    Amounts as printed (2)
  21. Drilling and equipping of nine boreholes in Ugunja, Alego and Rarieda sub-counties

    SIA-P-021DelayedWater and sanitationPlace as printed: Ugunja, Alego and Rarienda [sic, Rarieda] sub-counties

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 54 (audit physical verification). Latest evidence 2022.

    Reported beside audit-found
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General

    Audit findings: audit-2021-22-33

    Amounts as printed (2)
  22. Supply and installation of machines, wiring repairs and construction of a powerhouse at Madiany Ginnery

    SIA-P-022UnknownAgriculture and fisheriesWest Uyoma

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 54 (audit physical verification). Latest evidence 2022-11-15. Works were done but the facility was not operational; no source reports completion.

    Reported beside audit-found
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General

    Audit findings: audit-2021-22-34

    Amounts as printed (1)
  23. Construction of Kagwa Dispensary laboratory

    SIA-P-023Completed reportedHealthPlace as printed: not stated

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 54 (audit physical verification). Latest evidence 2022-07. Completion is as reported by the county; no independent check is recorded. Completion rests on the county's technical inspection report quoted in the audit. The audit visit found the laboratory unused but does not itself state that the works were complete, so it is not marked independently verified.

    Reported beside audit-found
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General

    Audit findings: audit-2021-22-35

    Amounts as printed (1)
  24. Construction of Modern Market in Ukwala Market

    SIA-P-024SuspendedMarkets and tradeUkwala

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 47 (audit physical verification). Latest evidence 2023-09.

    Reported beside audit-found
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General

    Audit findings: audit-2022-23-18

    Amounts as printed (2)
  25. Construction of Nyadorera Modern Market

    SIA-P-025DelayedMarkets and tradePlace as printed: not stated

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 47 (audit physical verification). Latest evidence 2023-11.

    Reported beside audit-found
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General

    Audit findings: audit-2022-23-19

    Amounts as printed (2)
  26. Fencing and gravelling works at Akala and Ramba Markets

    SIA-P-026DelayedMarkets and tradeSiaya Township, South Gem

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 47 (audit physical verification). Latest evidence 2023-10.

    Reported beside audit-found
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General

    Audit findings: audit-2022-23-20

    Amounts as printed (1)
  27. Drilling and equipping of Aila WC Borehole

    SIA-P-027UnknownWater and sanitationPlace as printed: Aila WC

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 48 (audit physical verification). Latest evidence 2023-08.

    Reported beside audit-found, where sources differ
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General
    Where the sources differ
    • County acceptance report (fully executed) against no borehole found at the contracted site.

    Audit findings: audit-2022-23-21

    Amounts as printed (1)
  28. Proposed construction of perimeter wall at Migwena Sports and Cultural Centre (Piny Luo)

    SIA-P-028Completed reportedSports, culture and tourismPlace as printed: Executive

    Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483 (cob report county data). Latest evidence 2025-06-30. Completion is as reported by the county; no independent check is recorded.

    Reported beside audit-found, where sources differ
    Reported by the county or the Controller of Budget
    Found by the Auditor-General
    Where the sources differ
    • County reports 100% at 30 June 2025; the September 2024 audit inspection found it incomplete and not to specification.
    • Audit KSh 28,718,584 paid in FY 2023/24; county cumulative KSh 28,834,584 at 30 June 2025.

    Audit findings: audit-2023-24-27

    Amounts as printed (4)
  29. Proposed washroom, gravelling works, waterworks, powerhouse and electrification at Migwena

    SIA-P-029DelayedSports, culture and tourismPlace as printed: Migwena

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 55 (audit documentary review). Latest evidence 2024.

    Reported beside audit-found
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General

    Audit findings: audit-2023-24-28

    Amounts as printed (2)
  30. Construction of County Aggregation and Industrial Park

    SIA-P-030SuspendedIndustryCentral Alego

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 54 (audit physical verification). Latest evidence 2025-10.

    Reported beside audit-found, where sources differ
    Reported by the county or the Controller of Budget
    Found by the Auditor-General
    Where the sources differ
    • FY 2023/24 audit: 28 weeks; FY 2024/25 audit: 80 weeks.

    Audit findings: audit-2023-24-30, audit-2024-25-18

    Amounts as printed (6)
  31. Proposed Construction of Yala Cattle Ring in Yala Township Ward

    SIA-P-031DelayedAgriculture and fisheriesYala Township

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 56 (audit physical verification). Latest evidence 2024.

    Reported beside audit-found
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General

    Audit findings: audit-2023-24-31

    Amounts as printed (1)
  32. Construction of four door flushable toilets and four bathrooms at Akala Health Centre

    SIA-P-032SuspendedHealthSouth Gem

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 56 (audit physical verification). Latest evidence 2024-09-17.

    Reported beside audit-found
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General

    Audit findings: audit-2023-24-32

    Amounts as printed (2)
  33. Construction of ECD Block at Maranyona Primary School

    SIA-P-033DelayedEducationPlace as printed: Maranyona Primary School

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 54 (audit physical verification). Latest evidence 2025-07.

    Reported beside audit-found
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General

    Audit findings: audit-2024-25-19

    Amounts as printed (1)
  34. Proposed completion of ECD Block at Nyabera Primary School

    SIA-P-034SuspendedEducationPlace as printed: Nyabera Primary School

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 55 (audit physical verification). Latest evidence 2025-07.

    Reported beside audit-found
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General

    Audit findings: audit-2024-25-21

    Amounts as printed (1)
  35. Construction of a modern Early Childhood Development Education (ECDE) Centre in Bondo Sub-County

    SIA-P-035ActiveEducationPlace as printed: Bondo Sub-County

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 58 (audit physical verification). Latest evidence 2025-10. Under construction with unapproved design changes; no completion percentage printed.

    Reported beside audit-found
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General

    Audit findings: audit-2024-25-30

    Amounts as printed (1)
  36. Supply, delivery, installation and commissioning of mortuary cold-room plant at Bondo Sub-County Hospital

    SIA-P-036DelayedHealthPlace as printed: Bondo Sub-County Hospital

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 59 (audit physical verification). Latest evidence 2025-10.

    Reported beside audit-found, where sources differ
    Reported by the county or the Controller of Budget
    Found by the Auditor-General
    Where the sources differ
    • County reports 100% at 30 June 2025; the October 2025 audit found the plant not installed.

    Audit findings: audit-2024-25-31

    Amounts as printed (3)
  37. Supply, delivery and installation of medical equipment at Siaya Hospital Theatre Complex

    SIA-P-037DelayedHealthPlace as printed: Siaya Hospital Theatre Complex

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 56 (audit physical verification). Latest evidence 2025-10.

    Reported beside audit-found, where sources differ
    Reported by the county or the Controller of Budget
    Found by the Auditor-General
    Where the sources differ
    • County reports 100%; the October 2025 audit found the equipment not installed.

    Audit findings: audit-2024-25-22

    Amounts as printed (3)
  38. Proposed construction of maternity block at Malunga Dispensary

    SIA-P-038Completed, independently verifiedHealthPlace as printed: Malunga Dispensary

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 56 (audit physical verification). Latest evidence 2025-07. Completion seen by the Auditor-General on site (July 2025). The facility was idle, so complete does not mean in service.

    Reported beside audit-found
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General

    Audit findings: audit-2024-25-23

    Amounts as printed (1)
  39. Drilling and equipping of two boreholes at Ligose Primary and Ligala Dispensary

    SIA-P-039UnknownWater and sanitationPlace as printed: Ligose Primary and Ligala Dispensary

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 56 (audit physical verification). Latest evidence 2025-07. Built, but neither borehole works as intended; no source states completion.

    Reported beside audit-found
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General

    Audit findings: audit-2024-25-23

    Amounts as printed (1)
  40. Drilling and equipping of a borehole at Yenga

    SIA-P-040UnknownWater and sanitationPlace as printed: Yenga

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 56 (audit physical verification). Latest evidence 2025-10. No contract sum printed for this borehole.

    Reported beside audit-found
    Reported by the county or the Controller of Budget

    No county report recorded.

    Found by the Auditor-General

    Audit findings: audit-2024-25-23

  41. Supply, installation, configuration, customisation, testing, commissioning and support of an Enterprise Resource Planning (ERP) management information system

    SIA-P-041DelayedICTPlace as printed: Siaya Head-quarters

    Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 49 (audit documentary review). Latest evidence 2023.

    Reported beside audit-found, where sources differ
    Reported by the county or the Controller of Budget
    Found by the Auditor-General
    Where the sources differ
    • CoB FY 2021/22 KSh 10,000,000 paid to date against the FY 2021/22 audit KSh 21,600,000.

    Audit findings: audit-2021-22-25, audit-2022-23-23

    Amounts as printed (5)
  42. Drilling and equipping of boreholes and construction of water kiosks in the ward offices

    SIA-P-042SuspendedWater and sanitationCounty-wide

    Status from Report of the Auditor-General on County Assembly of Siaya for the Year Ended 30 June, 2024, PDF p. 56 (audit physical verification). Latest evidence 2024-09.

    Reported beside audit-found, where sources differ
    Reported by the county or the Controller of Budget
    Found by the Auditor-General
    Where the sources differ
    • KSh 80,730,095 (CoB 2021/22), 125,662,548 (CoB 2022/23) and 117,133,552 (audit). The audit counts 28 ward offices, the CoB tables 30.

    Audit findings: audit-asm-2022-23-06, audit-asm-2023-24-06

    Amounts as printed (7)
  43. Construction of meeting halls in the ward offices

    SIA-P-043SuspendedOffices and governanceCounty-wide

    Status from Report of the Auditor-General on County Assembly of Siaya for the Year Ended 30 June, 2024, PDF p. 56 (audit physical verification). Latest evidence 2024-09.

    Reported beside audit-found, where sources differ
    Reported by the county or the Controller of Budget
    Found by the Auditor-General
    Where the sources differ
    • The audit dates the meeting-hall contracts 1 June 2023, but CoB tables show payments for meeting halls in FY 2021/22 and FY 2022/23.

    Audit findings: audit-asm-2023-24-06

    Amounts as printed (5)
  44. Construction and Fencing of Ward Offices

    SIA-P-044ActiveOffices and governanceCounty-wide

    Status from County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516 (cob report county data). Latest evidence 2024-06-30. Last reported at 78.3% (30 June 2024); no later source.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (7)
  45. Networking of Ward offices

    SIA-P-045ActiveICTCounty-wide

    Status from County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516 (cob report county data). Latest evidence 2024-06-30.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (2)
  46. Acquisition, Supervision and Installation of Hansard and Information Technology System Infrastructure and Equipment Development

    SIA-P-046Completed reportedICTPlace as printed: County Assembly Chambers; County Assembly Head-quarters

    Status from County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412 (cob report county data). Latest evidence 2022-06-30. Completion is as reported by the county; no independent check is recorded.

    Reported beside audit-found, where sources differ
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Where the sources differ
    • FY 2018/19 budget KSh 60,735,050 against a FY 2021/22 contract sum of KSh 14,564,983; may be separate phases.
    Amounts as printed (4)
  47. Development, Installation and Commissioning of Asset Inventory and fleet Management System

    SIA-P-047Completed reportedICTPlace as printed: County Assembly Head-quarters

    Status from County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412 (cob report county data). Latest evidence 2022-06-30. Completion is as reported by the county; no independent check is recorded.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (2)
  48. Development, Supply, Installation and Commissioning of Virtual Conference Boardrooms

    SIA-P-048ActiveICTPlace as printed: County Assembly Head-quarters

    Status from County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412 (cob report county data). Latest evidence 2022-06-30. Last reported June 2022; no later source.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (2)
  49. Construction of modern market at Sigomere

    SIA-P-049ActiveMarkets and tradeSigomere

    Status from County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412 (cob report county data). Latest evidence 2022-06-30. Last reported June 2022.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (3)
  50. Installation of High masts lighting in Siaya County

    SIA-P-050ActiveEnergy and lightingPlace as printed: Siaya Head-quarters

    Status from County Governments Budget Implementation Review Report FY 2021/22, PDF p. 411 (cob report county data). Latest evidence 2022-06-30.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (2)
  51. Installation of High mast lights in various locations in Siaya County

    SIA-P-051DelayedEnergy and lightingPlace as printed: Executive

    Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483 (cob report county data). Latest evidence 2025-06-30. Delayed on the county's own dates. May be the same programme as the FY 2021/22 high-mast entry; not merged because the contract sums differ.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (3)
  52. Supply, Installation, and Maintenance of the Integrated Revenue Management System for the County Government of Siaya

    SIA-P-052ActiveICTPlace as printed: Alego Usonga H/Q

    Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483 (cob report county data). Latest evidence 2025-06-30.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (2)
  53. Promotion of agro-processing rice (Installation of Siriwo rice mill)

    SIA-P-053Completed reportedAgriculture and fisheriesPlace as printed: Executive

    Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483 (cob report county data). Latest evidence 2025-06-30. Completion is as reported by the county; no independent check is recorded.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (2)
  54. Construction of rice milling plant

    SIA-P-054ActiveAgriculture and fisheriesPlace as printed: Siriwo

    Status from County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516 (cob report county data). Latest evidence 2024-06-30.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (2)
  55. Upgrade to bitumen standard. Rabango - Siaya Township School Road

    SIA-P-055ActiveRoads and transportPlace as printed: Rabango -Siaya Township School Road.

    Status from County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516 (cob report county data). Latest evidence 2024-06-30.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (2)
  56. Upgrade to bitumen standard. Yala ring road

    SIA-P-056Completed reportedRoads and transportPlace as printed: Yala ring road (OCR "rind")

    Status from County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516 (cob report county data). Latest evidence 2024-06-30. Completion is as reported by the county; no independent check is recorded.

    Reported beside audit-found, where sources differ
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Where the sources differ
    • Amount paid (KSh 39,850,732) exceeds the contract sum (KSh 26,900,000) as printed.
    Amounts as printed (2)
  57. Purchase of land for bus park

    SIA-P-057Completed reportedRoads and transportPlace as printed: Ugunja

    Status from County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516 (cob report county data). Latest evidence 2024-06-30. Completion is as reported by the county; no independent check is recorded.

    Reported beside audit-found, where sources differ
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Where the sources differ
    • 100% reported with KSh 15,000,000 of KSh 23,000,000 paid.
    Amounts as printed (2)
  58. Refrigeration at Siaya Referral Morgue (48-body capacity refrigeration machine)

    SIA-P-058Completed reportedHealthPlace as printed: Siaya Municipality; Siaya and Bondo hospital morgues

    Status from County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516 (cob report county data). Latest evidence 2024-06-30. Completion is as reported by the county; no independent check is recorded.

    Reported beside audit-found, where sources differ
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Where the sources differ
    • FY 2022/23 names the Siaya Referral morgue only; FY 2023/24 names Siaya and Bondo hospital morgues with the same contract sum.
    Amounts as printed (5)
  59. Construction of Abura Dam

    SIA-P-059Completed reportedWater and sanitationPlace as printed: not stated

    Status from Annual County Governments Budget Implementation Review Report FY 2022/23, PDF p. 581 (cob report county data). Latest evidence 2023-06-30. Completion is as reported by the county; no independent check is recorded.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (3)
  60. Completion of Randago VTC

    SIA-P-060Completed reportedEducationPlace as printed: Randago

    Status from County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516 (cob report county data). Latest evidence 2024-06-30. Completion is as reported by the county; no independent check is recorded.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (2)
  61. Construction of bus park at Bondo

    SIA-P-061UnknownRoads and transportNorth Sakwa

    Status from County Governments Budget Implementation Review Report FY 2020/21, PDF p. 377 (cob report county data). Latest evidence 2021-06-30.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (2)
  62. Equipping of Poye, Mbaga, Karapul, Uwasi, Nyamuango, Daho and Angolo Mkt

    SIA-P-062UnknownMarkets and tradePlace as printed: Ugunja

    Status from County Governments Budget Implementation Review Report FY 2020/21, PDF p. 377 (cob report county data). Latest evidence 2021-06-30.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (2)
  63. Drilling of boreholes at Ochienga, Kobonyo, Okela, Bonde, Dhere, Utonga & Kanyichudo

    SIA-P-063UnknownWater and sanitationPlace as printed: Rarieda and Bondo Subs

    Status from County Governments Budget Implementation Review Report FY 2020/21, PDF p. 377 (cob report county data). Latest evidence 2021-06-30.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (2)
  64. Maintenance of River Yala and Lake Kanyaboli dykes

    SIA-P-064UnknownEnvironmentCentral Alego

    Status from Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272 (cob report county data). Latest evidence 2019-06-30.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (2)
  65. Construction of County Annex Siaya

    SIA-P-065UnknownOffices and governancePlace as printed: County Headquarters

    Status from Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272 (cob report county data). Latest evidence 2019-06-30.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (2)
  66. Development of East Uyoma Water Project (co-funding of the project)

    SIA-P-066UnknownWater and sanitationPlace as printed: East Uyoma Ward

    Status from Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272 (cob report county data). Latest evidence 2019-06-30.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (2)
  67. Construction of Pap - Kodero Twin Box Culvert FL

    SIA-P-067UnknownRoads and transportWest Uyoma

    Status from Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272 (cob report county data). Latest evidence 2019-06-30.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (2)
  68. Routine Maintenance Of Ndai/Kanyaboli/Kubar Pr. Sch. /Obambo Pr. Sch. Road

    SIA-P-068UnknownRoads and transportCentral Alego

    Status from Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272 (cob report county data). Latest evidence 2019-06-30.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (2)
  69. Completion of the Apuoyo animal feed pelletizing plant

    SIA-P-069CancelledAgriculture and fisheriesWest Gem

    Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483 (cob report county data). Latest evidence 2025-06-30.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (1)
  70. Fencing and installation of a gate at Kokach Beach

    SIA-P-070SuspendedAgriculture and fisheriesEast Asembo

    Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483 (cob report county data). Latest evidence 2025-06-30.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

  71. Renovation and repairs of the Siriwo rice drying floor

    SIA-P-071CancelledAgriculture and fisheriesPlace as printed: Executive

    Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483 (cob report county data). Latest evidence 2025-06-30.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

  72. Construction of modern washrooms at Ralayo beach

    SIA-P-072SuspendedWater and sanitationEast Asembo

    Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 484 (cob report county data). Latest evidence 2025-06-30.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

  73. Acquisition of storage tanks for Bondo Sub-County Hospital

    SIA-P-073SuspendedHealthPlace as printed: Bondo sch

    Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 484 (cob report county data). Latest evidence 2025-06-30.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (1)
  74. Completion of Oboch dispensary (Pending)

    SIA-P-074SuspendedHealthEast Asembo

    Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 484 (cob report county data). Latest evidence 2025-06-30.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (1)
  75. Improving the sewer system and gate at the Rwambwa sub-County hospital

    SIA-P-075SuspendedHealthUsonga

    Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 484 (cob report county data). Latest evidence 2025-06-30.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (1)
  76. Complete Automation of Revenue

    SIA-P-076ActiveICTPlace as printed: Executive

    Status from County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 11 (county budget report). Latest evidence 2026-06-30.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (4)
  77. Completion of casualty and maternity complex at Yala SCH

    SIA-P-077DelayedHealthPlace as printed: Executive

    Status from County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 11 (county budget report). Latest evidence 2026-06-30. Delayed on the county's own dates: 90% at 30 June 2026 against an expected completion of February 2026.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (3)
  78. Phased construction of Ugenya Sub County Office at Ukwala

    SIA-P-078UnknownOffices and governanceUkwala

    Status from County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12 (county budget report). Latest evidence 2026-06-30.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (4)
  79. Phased construction of Gem Sub County Office at Yala

    SIA-P-079DelayedOffices and governancePlace as printed: Gem Sub County Office at Yala

    Status from County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026, PDF p. 13 (county budget report). Latest evidence 2026-03-31. Delayed on the county's own dates. Not in the Q4 table.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (3)
  80. Completion of upgrading to bitumen standard of Ndori market ring Road (phased)

    SIA-P-080Completed reportedRoads and transportEast Asembo

    Status from County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12 (county budget report). Latest evidence 2026-06-30. Completion is as reported by the county; no independent check is recorded. Phased project: 100% may refer to the phase funded in FY 2025/26.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (3)
  81. Completion of construction and equipping of Municipal Office complex - Phase 2 (multi- year project)

    SIA-P-081DelayedUrban, housing and landsPlace as printed: Siaya municipal Coumpound [sic]

    Status from County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12 (county budget report). Latest evidence 2026-06-30. Delayed on the county's own dates.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (4)
  82. Revamping South Sakwa (Olago)

    SIA-P-082DelayedWater and sanitationSouth Sakwa

    Status from County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12 (county budget report). Latest evidence 2026-06-30. Sector code WECC&NR (water, environment). Delayed on the county's own dates; unchanged at 60% for three quarters.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (3)
  83. Provision of improved kienyeji chicks to South Gem groups

    SIA-P-083Completed reportedAgriculture and fisheriesSouth Gem

    Status from County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12 (county budget report). Latest evidence 2026-06-30. Completion is as reported by the county; no independent check is recorded. An input supply, not a construction project; kept because the county lists it as a development project.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (3)
  84. Phased of upgrading to Bitumen standard- Sega market ring road

    SIA-P-084Completed reportedRoads and transportNorth Ugenya

    Status from County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12 (county budget report). Latest evidence 2026-06-30. Completion is as reported by the county; no independent check is recorded. Phased project: 100% may refer to the phase funded in FY 2025/26.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (3)
  85. Completion of upgrading to bitumen standard of Usenge market ring Road (phased)

    SIA-P-085Completed reportedRoads and transportWest Yimbo

    Status from County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12 (county budget report). Latest evidence 2026-06-30. Completion is as reported by the county; no independent check is recorded. Phased project: 100% may refer to the phase funded in FY 2025/26.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (3)
  86. Phased construction of Ukwala Sub County Hospital Annex

    SIA-P-086Completed reportedHealthUkwala

    Status from County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12 (county budget report). Latest evidence 2026-06-30. Completion is as reported by the county; no independent check is recorded.

    Reported beside audit-found, where sources differ
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Where the sources differ
    • 100% reported with 16% of the contract sum spent; likely the FY 2025/26 phase only.
    Amounts as printed (3)
  87. Construction of out-patient unit, co-funding of Urenga hospital (KDSP II)

    SIA-P-087ActiveHealthPlace as printed: Executive

    Status from County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12 (county budget report). Latest evidence 2026-06-30.

    Reported beside audit-found, where sources differ
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Where the sources differ
    • Q3 reports 55% with KSh 16.1 million spent; Q4 also 55% with KSh 34.6 million spent.
    Amounts as printed (4)
  88. Opening, grading and gravelling of Sianga-Wambarra- Yao Kouma- Kongolo Road

    SIA-P-088Completed reportedRoads and transportCentral Sakwa

    Status from County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026, PDF p. 13 (county budget report). Latest evidence 2026-03-31. Completion is as reported by the county; no independent check is recorded.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (3)
  89. Maintenance of Nyangera sports ground access road and Nyagera pitch levelling

    SIA-P-089Completed reportedSports, culture and tourismYimbo East

    Status from County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025, PDF p. 17 (county budget report). Latest evidence 2025-12-31. Completion is as reported by the county; no independent check is recorded.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (3)
  90. Maintenace [sic] of Julius Waliera - Sirand Malwa - Uyundi road - 2.5km

    SIA-P-090Completed reportedRoads and transportWest Ugenya

    Status from County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025, PDF p. 17 (county budget report). Latest evidence 2025-12-31. Completion is as reported by the county; no independent check is recorded. The road name is printed as in the source (a place name).

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (3)
  91. Purchase, commissioning, delivery and installation of generator at Ukwala Hospital

    SIA-P-091Completed reportedHealthUkwala

    Status from County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025, PDF p. 16 (county budget report). Latest evidence 2025-12-31. Completion is as reported by the county; no independent check is recorded.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (2)
  92. Proposed Construction of Rarieda Sub-County Headquarters in Aram

    SIA-P-092SuspendedOffices and governancePlace as printed: Rarieda Sub-County Headquarters in Aram [project name; location column "Executive"]

    Status from County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026, PDF p. 14 (county budget report). Latest evidence 2026-03-31. Dropped from the Q4 report, which lists only one stalled project; no reason given.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (2)
  93. Purchase of Land for Construction of Rarieda Sub County Office

    SIA-P-093SuspendedOffices and governancePlace as printed: Rarieda Sub County Office [project name; location column "Executive"]

    Status from County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026, PDF p. 14 (county budget report). Latest evidence 2026-03-31.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (2)
  94. Completion of Nyamonye juakali

    SIA-P-094SuspendedMarkets and tradeYimbo East

    Status from County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12 (county budget report). Latest evidence 2026-06-30.

    Reported beside audit-found, where sources differ
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Where the sources differ
    • Amount paid (KSh 3,720,000) is printed above the estimated value (KSh 1,878,186.20). CoB FY 2024/25 prints the completion before stalling as 35% (OCR), the county quarterly reports 40%.
    Amounts as printed (3)
  95. Completion of an Early Childhood Development (ECD) center at Hawinga

    SIA-P-095Completed reportedEducationWest Alego

    Status from Report on Public Participation in the Siaya County Annual Development Plan (CADP) 2025-2026, PDF p. 6 (county participation report). Latest evidence 2024-09. Completion is as reported by the county; no independent check is recorded. Reported by the county in its participation report; no amount printed.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

  96. Wagai Multi-Media Resource and Learning Centre

    SIA-P-096SuspendedEducationPlace as printed: not stated (Wagai)

    Status from Report on Public Participation in the Siaya County Annual Development Plan (CADP) 2025-2026, PDF p. 10 (county participation report). Latest evidence 2024-09. Described as stalled by forum participants, as recorded by the county; no amount printed.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

  97. Muluwa Irrigation Scheme in Alego Usonga sub-county

    SIA-P-097ActiveAgriculture and fisheriesPlace as printed: Alego Usonga sub-county

    Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 168 (county development plan). Latest evidence 2024-01-24. The CIDP says the irrigation expansion is on-going under a national project; the county components are plans. No implementation report was read.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (3)
  98. Anyiko Irrigation Scheme in Ugenya sub-county

    SIA-P-098ActiveAgriculture and fisheriesPlace as printed: Ugenya sub-county

    Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 169 (county development plan). Latest evidence 2024-01-24. The CIDP says the expansion is on-going under a national project; the county components are plans. No implementation report was read.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (3)
  99. Last mile connectivity on Ugunja-Sega-Ukwala

    SIA-P-099PlannedWater and sanitationUkwala

    Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 170 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (1)
  100. Last mile connectivity on SIBOWASCO

    SIA-P-100PlannedWater and sanitationPlace as printed: Bondo and Siaya

    Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 170 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (1)
  101. Augmentation of Yala intake

    SIA-P-101PlannedWater and sanitationPlace as printed: Yala

    Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 170 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (1)
  102. Wichlum water project

    SIA-P-102PlannedWater and sanitationPlace as printed: Bondo

    Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 170 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (1)
  103. Development irrigation infrastructure

    SIA-P-103PlannedAgriculture and fisheriesPlace as printed: Alego, Ugenya

    Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 170 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (1)
  104. Upgrading of airstrips

    SIA-P-104PlannedRoads and transportPlace as printed: Sega, Gombe, Migwena

    Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 171 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (1)
  105. Establishment of Asembo bay feeder port

    SIA-P-105PlannedRoads and transportPlace as printed: Rarieda

    Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 171 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (1)
  106. Construction of energy centres

    SIA-P-106PlannedEnergy and lightingPlace as printed: Siaya, Bondo and Ugunja

    Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 171 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (1)
  107. Construction of hospital complexes

    SIA-P-107PlannedHealthPlace as printed: Siaya and Bondo

    Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 171 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (1)
  108. KEMRI -Siaya County Research and Biotech Complex

    SIA-P-108PlannedHealthPlace as printed: Siaya

    Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 171 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (1)
  109. Construction and equipping of MRI Centre

    SIA-P-109PlannedHealthPlace as printed: Siaya

    Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 171 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (1)
  110. Establishment of Industrial Park

    SIA-P-110PlannedIndustryPlace as printed: Siaya

    Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 172 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (1)
  111. Development of Got Ramogi

    SIA-P-111PlannedSports, culture and tourismPlace as printed: Bondo

    Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 172 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (1)
  112. Construction of phase II Siaya Stadium

    SIA-P-112PlannedSports, culture and tourismPlace as printed: Siaya

    Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 172 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (1)
  113. Construction of Migwena talent Centre

    SIA-P-113PlannedSports, culture and tourismPlace as printed: Bondo

    Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 172 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (1)
  114. Construction of office complex

    SIA-P-114PlannedOffices and governancePlace as printed: Siaya

    Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 172 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (1)
  115. Construction of state officer residence (Governor, Deputy Governor)

    SIA-P-115PlannedOffices and governancePlace as printed: Siaya

    Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 172 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (1)
  116. Establishment of L.Kanyaboli Eco-city

    SIA-P-116PlannedUrban, housing and landsPlace as printed: Siaya

    Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 172 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (1)
  117. Construction of speaker's residence

    SIA-P-117PlannedOffices and governancePlace as printed: Siaya

    Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 173 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (1)
  118. Construction of County Assembly's complex

    SIA-P-118PlannedOffices and governancePlace as printed: Siaya

    Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 173 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.

    Reported beside audit-found
    Reported by the county or the Controller of Budget
    Found by the Auditor-General

    No audit evidence recorded.

    Amounts as printed (1)

What is not in the register

Documents: County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file); County Government of Siaya, Budget Implementation Report for 1st Quarter Ending September 30th 2025; County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025; County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026; County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026; Report on Public Participation in the Siaya County Annual Development Plan (CADP) 2025-2026; Annual County Governments Budget Implementation Review Report FY 2018/19; County Governments Budget Implementation Review Report FY 2020/21; County Governments Budget Implementation Review Report FY 2021/22; Annual County Governments Budget Implementation Review Report FY 2022/23; County Governments Budget Implementation Review Report FY 2023/24; County Governments Budget Implementation Review Report FY 2024/25; Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021; Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022; Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023.; Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024; Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025; Report of the Auditor-General on County Assembly of Siaya for the Year Ended 30 June 2023; Report of the Auditor-General on County Assembly of Siaya for the Year Ended 30 June, 2024. Every project is in the dataset catalogue and in siaya-projects.json (contractor fields withheld).