Development project register
118 county development projects named in the county’s plans and budget reports, the Controller of Budget’s reports and the Auditor-General’s reports, with what each source says about progress. Where the county’s report and the auditor’s inspection differ, both are shown.
How to read this page
Provisional: awaiting editorial review Editorial review of 118 values: 0 approved, 118 pending, 0 rejected. 23 are disputed between sources (both readings kept). What this means
- Reported is not verified. “Completed (reported)” means the county reported completion. Only a project whose completion the Auditor-General confirmed on inspection is shown as independently verified: in this register that is
SIA-P-038(Proposed construction of maternity block at Malunga Dispensary) alone. Takwimu has made no site visits. - Not exhaustive. The reports list mainly the highest-spending and stalled projects, so many projects are not here.
- Audit findings are findings, not convictions. Linked finding ids open the finding on Audit findings. No individual is named, and contractor company names are withheld from this site pending editorial review.
- Amounts are as printed, in the document’s own year; they are never added together.
The eight status states used
- Planned (20)
- in a plan (CIDP) with no later evidence.
- Active (13)
- works or payments under way and not past the expected completion date in the evidence.
- Delayed (25)
- incomplete after the expected completion date, from the audit or from the county's own dates.
- Suspended (16)
- listed as stalled by the county, or works found stopped or abandoned by the auditor.
- Completed reported (23)
- the county (directly, in a CoB table, or as quoted by the auditor) reports completion or 100%.
- Completed, independently verified (1)
- the Auditor-General (or another independent party) states on inspection that the works were complete.
- Cancelled (4)
- contract terminated or budget removed.
- Unknown (16)
- only spending, or conflicting or incomplete evidence.
Where the county’s report and the audit differ: two examples
Tarmacking of Opoda-Bondo township road (SIA-P-018)
- County (CoB FY 2021/22) reports 100% complete and in use; the FY 2021/22 audit estimates 20% executed with the contractor off site.
- Printed as North Sakwa, North Uyoma and South Sakwa in different rows and years.
- CoB FY 2020/21 budget KSh 152,000,000 against an audited contract cost of KSh 52,805,116.
Supply, delivery, installation and commissioning of mortuary cold-room plant at Bondo Sub-County Hospital (SIA-P-036)
- County reports 100% at 30 June 2025; the October 2025 audit found the plant not installed.
Projects by sector, ward and status
Projects by status: all sectors, all wards and county-wide
View as table
| Period | Projects (projects) |
|---|---|
| Planned | 20 |
| Active | 13 |
| Delayed | 25 |
| Suspended | 16 |
| Completed reported | 23 |
| Completed, independently verified | 1 |
| Cancelled | 4 |
| Unknown | 16 |
Showing 118 of 118 projects
Construction of Siaya County Stadium
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 55 (audit documentary review). Latest evidence 2024-08-30. Not reported complete by any source; the latest independent evidence (FY 2023/24 audit) records nine extensions. A separate completion contract is SIA-P for "Completion of the Siaya stadium".
Reported beside audit-found, where sources differ
Reported by the county or the Controller of Budget
- Listed among projects with the highest expenditure; 47.4% absorption of the project budget.
Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272, as at 2019-06-30, cob report county data, confidence 5 of 5 - Expenditure above budget (168%), attributed to a supplementary budget cut.
County Governments Budget Implementation Review Report FY 2020/21, PDF p. 376, as at 2021-06-30, cob report county data, confidence 3 of 5 - 60% complete (as stated). County: implementation status 60%, "Project is incomplete".
County Governments Budget Implementation Review Report FY 2021/22, PDF p. 411, as at 2022-06-30, cob report county data, confidence 3 of 5 - 85% complete (as stated). County: implementation status 85%.
County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516, as at 2024-06-30, cob report county data, confidence 3 of 5
Found by the Auditor-General
- 83% complete (as stated). Audit verification in November 2021: incomplete 23 months after the completion date; about 83% complete per the 1 March 2021 valuation; performance bond expired 20 Apr 2020.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 41, as at 2021-11, audit physical verification, confidence 4 of 5; finding audit-2020-21-21 - Audit verification in November 2022: still incomplete about 35 months after inception; six extensions, latest to 25 May 2022; 24% variation without evaluation committee.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 51, as at 2022-11, audit physical verification, confidence 4 of 5; finding audit-2021-22-26 - Contract period expired July 2023; physical verification found pending works; separate roof contract raised cost to KSh 524,229,273.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 48, as at 2023, audit physical verification, confidence 4 of 5; finding audit-2022-23-22 - Project status report shows nine extensions as of 30 Aug 2024 (not verified by the auditor); variation of 24% without evaluation committee.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 55, as at 2024-08-30, audit documentary review, confidence 4 of 5; finding audit-2023-24-29
Where the sources differ
- Audits print KSh 394,661,767 (original), 488,716,823 (revised) and 524,229,273 (with roof contract); CoB FY 2023/24 prints 424,872,927.
- FY 2020/21: CoB (county data) KSh 117,602,147 against audit KSh 80,254,180 + 14,648,670. FY 2021/22: CoB KSh 67,093,742 against audit KSh 57,999,787.
Audit findings: audit-2020-21-21, audit-2021-22-26, audit-2022-23-22, audit-2023-24-29
Amounts as printed (19)
- approved budget: KSh 180,000,000 (FY 2018/19; “Project Budget”) Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272
- expenditure in fy: KSh 85,303,489 (FY 2018/19; “Project Expenditure”) Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272
- approved budget: KSh 70,000,000 (FY 2020/21; “Budget (column as read by OCR)”) County Governments Budget Implementation Review Report FY 2020/21, PDF p. 376
- expenditure in fy: KSh 117,602,147 (FY 2020/21; “Expenditure (absorption 168.0%)”) County Governments Budget Implementation Review Report FY 2020/21, PDF p. 376
- contract sum: KSh 394,661,767 (FY 2020/21; “contract sum (contract signed 30 Aug 2018)”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 41
- certified cumulative: KSh 327,091,241 (FY 2020/21; “total certified works (valuation certificate 1 Mar 2021)”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 41
- paid in fy: KSh 80,254,180 (FY 2020/21; “paid to the main contractor”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 41
- paid in fy: KSh 14,648,670 (FY 2020/21; “paid to two local sub-contractors (plumbing, electrical)”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 41
- contract sum: KSh 394,661,767 (FY 2021/22; “Contract sum”) County Governments Budget Implementation Review Report FY 2021/22, PDF p. 411
- approved budget: KSh 78,207,870 (FY 2021/22; “Budget”) County Governments Budget Implementation Review Report FY 2021/22, PDF p. 411
- paid cumulative: KSh 67,093,742 (FY 2021/22; “Amount paid to date”) County Governments Budget Implementation Review Report FY 2021/22, PDF p. 411
- paid in fy: KSh 57,999,787 (FY 2021/22; “paid towards construction (OCR: Kshs.S7,999,787)”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 51
- revised contract sum: KSh 488,716,823 (FY 2021/22; “contract sum revised”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 51
- variation: KSh 94,055,056 (FY 2021/22; “variation (24%)”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 51
- contract sum: KSh 35,512,450 (FY 2022/23; “separate roof-works contract (14 Sep 2022)”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 48
- revised contract sum: KSh 524,229,273 (FY 2022/23; “construction cost including roof contract (variation 32%)”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 48
- paid cumulative: KSh 425,038,687 (FY 2022/23; “total payments to contractors at the time of audit”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 48
- contract sum: KSh 424,872,927 (FY 2023/24; “Contract sum”) County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516
- paid cumulative: KSh 441,964,497 (FY 2023/24; “Amount paid to date”) County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516
- Listed among projects with the highest expenditure; 47.4% absorption of the project budget.
Installation of three-phase electricity power at the Siaya Stadium
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 53 (audit physical verification). Latest evidence 2024.
Reported beside audit-found
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- Physical inspection: transformer not installed; stadium has no power connected. Requisition 23 Sep 2023, payment 16 Nov 2023.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 53, as at 2024, audit physical verification, confidence 4 of 5; finding audit-2023-24-25
Audit findings: audit-2023-24-25
Amounts as printed (1)
- paid in fy: KSh 1,336,721 (FY 2023/24; “cost paid 16 Nov 2023”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 53
- Physical inspection: transformer not installed; stadium has no power connected. Requisition 23 Sep 2023, payment 16 Nov 2023.
Installation of stadium VIP seats
Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483 (cob report county data). Latest evidence 2025-06-30. Completion is as reported by the county; no independent check is recorded.
Reported beside audit-found, where sources differ
Reported by the county or the Controller of Budget
- 100% complete (as stated). County: implementation status 100%.
County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483, as at 2025-06-30, cob report county data, confidence 4 of 5
Found by the Auditor-General
- Physical inspection: 1,494 fixed seats and 471 foldable seats installed, 45 fewer foldable seats than the bill of quantities (516); advance paid without an inspection report.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 54, as at 2024, audit physical verification, confidence 4 of 5; finding audit-2023-24-26
Where the sources differ
- The county reports 100% (30 June 2025); the earlier FY 2023/24 audit inspection counted 45 fewer foldable seats than contracted. No independent check after the county report.
Audit findings: audit-2023-24-26
Amounts as printed (4)
- contract sum: KSh 25,101,114 (FY 2023/24; “contract sum”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 54
- advance: KSh 5,020,222 (FY 2023/24; “advance payment (20%)”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 54
- contract sum: KSh 25,101,114 (FY 2024/25; “Contract sum”) County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483
- paid cumulative: KSh 25,101,114 (FY 2024/25; “Cumulative expenditure as of 30 June 2025”) County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483
- 100% complete (as stated). County: implementation status 100%.
Supply and installation of stadium lighting mast for the proposed stadium for the County Government of Siaya
Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483 (cob report county data). Latest evidence 2025-06-30. Completion is as reported by the county; no independent check is recorded.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 100% complete (as stated). County: implementation status 100%.
County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483, as at 2025-06-30, cob report county data, confidence 4 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (2)
- contract sum: KSh 20,614,000 (FY 2024/25; “Contract sum”) County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483
- paid cumulative: KSh 20,614,000 (FY 2024/25; “Cumulative expenditure as of 30 June 2025”) County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483
- 100% complete (as stated). County: implementation status 100%.
Proposed installation of Tartan on the running track
Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483 (cob report county data). Latest evidence 2025-06-30. Delayed on the county's own dates: 70% at 30 June 2025 against an expected completion of June 2024. The table does not say which track.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 70% complete (as stated). County: 70% against an expected completion of June 2024.
County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483, as at 2025-06-30, cob report county data, confidence 3 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (3)
- contract sum: KSh 137,350,000 (FY 2024/25; “Contract sum (two of three OCR reads)”) County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483
- paid in fy: KSh 56,010,500 (FY 2024/25; “Amount paid in FY 2024/25”) County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483
- paid cumulative: KSh 56,010,500 (FY 2024/25; “Cumulative expenditure as of 30 June 2025”) County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483
- 70% complete (as stated). County: 70% against an expected completion of June 2024.
Completion of the Siaya stadium
Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483 (cob report county data). Latest evidence 2025-06-30. Completion is as reported by the county; no independent check is recorded. A completion contract reported at 100% by the county. Whether the stadium as a whole is complete has not been independently checked.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 100% complete (as stated). County: implementation status 100%.
County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483, as at 2025-06-30, cob report county data, confidence 4 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (2)
- contract sum: KSh 28,175,350 (FY 2024/25; “Contract sum”) County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483
- paid cumulative: KSh 28,175,350 (FY 2024/25; “Cumulative expenditure as of 30 June 2025”) County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483
- 100% complete (as stated). County: implementation status 100%.
Construction of Siaya Bus Park
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 46 (audit physical verification). Latest evidence 2023-11. Contract terminated 2 June 2023; no later source on re-tendering.
Reported beside audit-found, where sources differ
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- 60% complete (as stated). About 60% complete; duration lapsed by over 16 months; extension to 22 Feb 2022 without evaluation committee.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 53, as at 2022, audit documentary review, confidence 4 of 5; finding audit-2021-22-31 - Contract terminated at the contractor's request on 2 June 2023; physical verification in November 2023 found works stalled and abandoned.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 46, as at 2023-11, audit physical verification, confidence 4 of 5; finding audit-2022-23-17
Where the sources differ
- FY 2021/22 audit says awarded in March 2020; FY 2022/23 audit says contract entered on 7 August 2020.
Audit findings: audit-2021-22-31, audit-2022-23-17
Amounts as printed (3)
- contract sum: KSh 23,014,867 (FY 2021/22; “cost (awarded March 2020)”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 53
- paid cumulative: KSh 12,582,218 (FY 2021/22; “paid at the time of audit”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 53
- paid cumulative: KSh 17,582,978 (FY 2022/23; “total paid before termination”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 46
- 60% complete (as stated). About 60% complete; duration lapsed by over 16 months; extension to 22 Feb 2022 without evaluation committee.
Construction of Haudinga Sheltered Workshop in Ukwala
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 38 (audit physical verification). Latest evidence 2021-11.
Reported beside audit-found, where sources differ
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- Physical inspection November 2021: incomplete over a year after the expected completion; no completion certificate. Management said it was complete and handed over.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 38, as at 2021-11, audit physical verification, confidence 4 of 5; finding audit-2020-21-12
Where the sources differ
- Management reported completion and handover; the audit inspection found it incomplete.
Audit findings: audit-2020-21-12
Amounts as printed (2)
- contract sum: KSh 6,678,405 (FY 2020/21; “contract sum”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 38
- paid in fy: KSh 5,407,305 (FY 2020/21; “paid to a local contractor”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 38
- Physical inspection November 2021: incomplete over a year after the expected completion; no completion certificate. Management said it was complete and handed over.
Construction of Nyasanda Sheltered Workshop in Ugunja
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 38 (audit physical verification). Latest evidence 2021-11.
Reported beside audit-found, where sources differ
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- Physical verification November 2021: latrine, electricity, water tank and gutters not done; contractor not on site; no extension. Management said complete and handed over.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 38, as at 2021-11, audit physical verification, confidence 4 of 5; finding audit-2020-21-13
Where the sources differ
- Management reported completion; the audit found items not done.
Audit findings: audit-2020-21-13
Amounts as printed (2)
- contract sum: KSh 6,831,702 (FY 2020/21; “contract sum”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 38
- paid in fy: KSh 1,500,000 (FY 2020/21; “paid to a local contractor”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 38
- Physical verification November 2021: latrine, electricity, water tank and gutters not done; contractor not on site; no extension. Management said complete and handed over.
Construction of Nyamnina Youth Polytechnic
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 38 (audit physical verification). Latest evidence 2021-11.
Reported beside audit-found, where sources differ
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- Physical verification November 2021: still incomplete, contractor not on site, despite a completion certificate dated 17 Feb 2021.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 38, as at 2021-11, audit physical verification, confidence 4 of 5; finding audit-2020-21-14
Where the sources differ
- County completion certificate (17 Feb 2021) against an incomplete finding at inspection.
Audit findings: audit-2020-21-14
Amounts as printed (2)
- contract sum: KSh 3,870,156 (FY 2020/21; “contract price”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 38
- paid in fy: KSh 2,908,328 (FY 2020/21; “paid to a contractor”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 38
- Physical verification November 2021: still incomplete, contractor not on site, despite a completion certificate dated 17 Feb 2021.
Renovations at Odera Akang'o Campus (works at Directors Office)
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 39 (audit physical verification). Latest evidence 2021-11.
Reported beside audit-found, where sources differ
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- Physical verification November 2021: renovation of the principal's office not started; contractor not on site; practical completion certificate of 10 Feb 2021 without a snag list.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 39, as at 2021-11, audit physical verification, confidence 4 of 5; finding audit-2020-21-15
Where the sources differ
- Practical completion certificate (10 Feb 2021) against incomplete works at inspection.
Audit findings: audit-2020-21-15
Amounts as printed (3)
- contract sum: KSh 36,653,220 (FY 2020/21; “contract sum”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 39
- paid in fy: KSh 5,067,399 (FY 2020/21; “paid on 1 Oct 2020”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 39
- certified cumulative: KSh 33,955,486 (FY 2020/21; “certified for payment (92% of contract sum)”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 39
- Physical verification November 2021: renovation of the principal's office not started; contractor not on site; practical completion certificate of 10 Feb 2021 without a snag list.
Construction of a laboratory at Obaga West Asembo Health Centre
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 39 (audit physical verification). Latest evidence 2021-11. The laboratory was built with deviations from the bill of quantities; no source states completion.
Reported beside audit-found
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- Physical verification November 2021: cracked door frames, 10 of 14 windows and 4 of 5 doors installed, paving not done; variation not documented; no completion certificate.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 39, as at 2021-11, audit physical verification, confidence 4 of 5; finding audit-2020-21-17
Audit findings: audit-2020-21-17
Amounts as printed (1)
- paid in fy: KSh 1,295,372 (FY 2020/21; “paid to a local contractor”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 39
- Physical verification November 2021: cracked door frames, 10 of 14 windows and 4 of 5 doors installed, paving not done; variation not documented; no completion certificate.
Maintenance of Maira Othatch Road and Bar Okwiri Kayouth roads
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 40 (audit physical verification). Latest evidence 2021-11. Management says rectified; not verified by any source.
Reported beside audit-found
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- Physical verification November 2021: no evidence of clearing, grading or gravelling. Management said defects were later rectified; no completion certificate.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 40, as at 2021-11, audit physical verification, confidence 4 of 5; finding audit-2020-21-18
Audit findings: audit-2020-21-18
Amounts as printed (1)
- paid in fy: KSh 10,305,315 (FY 2020/21; “paid, equal to the contract sum”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 40
- Physical verification November 2021: no evidence of clearing, grading or gravelling. Management said defects were later rectified; no completion certificate.
Rehabilitation of Siaya Slaughterhouse
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 40 (audit physical verification). Latest evidence 2021-11.
Reported beside audit-found
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- Physical verification November 2021: incomplete four months after the contract period; contractor not on site; no extension evidence.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 40, as at 2021-11, audit physical verification, confidence 4 of 5; finding audit-2020-21-19
Audit findings: audit-2020-21-19
Amounts as printed (2)
- contract sum: KSh 9,984,993 (FY 2020/21; “contract sum”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 40
- paid in fy: KSh 3,999,999 (FY 2020/21; “paid to a local contractor”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 40
- Physical verification November 2021: incomplete four months after the contract period; contractor not on site; no extension evidence.
Construction of Migwena Sports Stadium (2017 contract)
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 40 (audit physical verification). Latest evidence 2021-11.
Reported beside audit-found
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- Contract ended after a breach by the county; audit inspection November 2021 found only the pavilion foundation and about 15 tonnes of ballast.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 40, as at 2021-11, audit physical verification, confidence 4 of 5; finding audit-2020-21-20
Audit findings: audit-2020-21-20
Amounts as printed (2)
- contract sum: KSh 22,433,511 (FY 2020/21; “cost sum (24-week contract)”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 40
- other payment: KSh 6,966,833 (FY 2019/20; “awarded to the contractor for works done, paid in FY 2019/20”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021, PDF p. 40
- Contract ended after a breach by the county; audit inspection November 2021 found only the pavilion foundation and about 15 tonnes of ballast.
Drainage, grading, gravelling and dozing of Kwaweya Yenga Nyalula Udura Kolum road (12 km)
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 53 (audit physical verification). Latest evidence 2022-07-27. Incomplete at verification; no later source.
Reported beside audit-found
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- Physical verification 27 July 2022: 3 km of the 12 km not graded or gravelled.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 53, as at 2022-07-27, audit physical verification, confidence 4 of 5; finding audit-2021-22-29
Audit findings: audit-2021-22-29
Amounts as printed (1)
- paid in fy: KSh 7,722,584 (FY 2021/22; “paid”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 53
- Physical verification 27 July 2022: 3 km of the 12 km not graded or gravelled.
Repairs and maintenance of Boro-Katondi Road, Ogunga Road and Segere-Ouru Road
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 53 (audit physical verification). Latest evidence 2022-11-10.
Reported beside audit-found
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- Physical verification 10 Nov 2022: damaged culvert line on Boro-Katondi road. The paid amount is partly illegible in the text layer.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 53, as at 2022-11-10, audit physical verification, confidence 3 of 5; finding audit-2021-22-30
Audit findings: audit-2021-22-30
Amounts as printed (1)
- contract sum: KSh 14,659,268 (FY 2021/22; “contract sum, three roads”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 53
- Physical verification 10 Nov 2022: damaged culvert line on Boro-Katondi road. The paid amount is partly illegible in the text layer.
Tarmacking of Opoda-Bondo township road
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 53 (audit physical verification). Latest evidence 2022-06-30.
Reported beside audit-found, where sources differ
Reported by the county or the Controller of Budget
- Four rows for this road (North Sakwa x3, North Uyoma x1) with absorption 29.7%, 22.1%, 47.5% and 14.4%; only row 2 is transcribed.
County Governments Budget Implementation Review Report FY 2020/21, PDF p. 376, as at 2021-06-30, cob report county data, confidence 2 of 5 - 100% complete (as stated). County: implementation 100%, "Project complete and in use".
County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412, as at 2022-06-30, cob report county data, confidence 3 of 5
Found by the Auditor-General
- 20% complete (as stated). Audit paragraph 8.5: executed works estimated at only 20%, contractor not on site (not one of the findings transcribed in data/siaya-audits.json).
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 53, as at 2022, audit physical verification, confidence 4 of 5
Where the sources differ
- County (CoB FY 2021/22) reports 100% complete and in use; the FY 2021/22 audit estimates 20% executed with the contractor off site.
- Printed as North Sakwa, North Uyoma and South Sakwa in different rows and years.
- CoB FY 2020/21 budget KSh 152,000,000 against an audited contract cost of KSh 52,805,116.
Amounts as printed (5)
- approved budget: KSh 152,000,000 (FY 2020/21; “Budget (OCR "I 52,000,000"; the same figure is printed on three rows)”) County Governments Budget Implementation Review Report FY 2020/21, PDF p. 376
- expenditure in fy: KSh 45,199,541 (FY 2020/21; “Expenditure, row 2 (absorption 29.7%)”) County Governments Budget Implementation Review Report FY 2020/21, PDF p. 376
- contract sum: KSh 52,805,116 (FY 2021/22; “cost (OCR "S2,805,116"; 17,692,949 is printed as 33.5% of it)”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 53
- paid cumulative: KSh 17,692,949 (FY 2021/22; “paid as at 30 June 2022”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 53
- paid cumulative: KSh 17,692,949 (FY 2021/22; “Amount paid to date (also printed in the contract-sum column)”) County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412
- Four rows for this road (North Sakwa x3, North Uyoma x1) with absorption 29.7%, 22.1%, 47.5% and 14.4%; only row 2 is transcribed.
Construction of five ECD classrooms (Mahero, Kirindo, Ninga, Nyadheho and Nyabondo primary schools)
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 54 (audit physical verification). Latest evidence 2022.
Reported beside audit-found
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- Physical verification: windows, doors, floors, plastering and electrical works pending; contractors not on site at all five.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 54, as at 2022, audit physical verification, confidence 4 of 5; finding audit-2021-22-32
Audit findings: audit-2021-22-32
Amounts as printed (2)
- contract sum: KSh 19,124,181 (FY 2021/22; “total contract sum”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 54
- paid in fy: KSh 9,701,685 (FY 2021/22; “paid (legible in the closing sentence)”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 54
- Physical verification: windows, doors, floors, plastering and electrical works pending; contractors not on site at all five.
Construction of Early Childhood Development (ECD) block at Kirindo primary school
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 46 (audit physical verification). Latest evidence 2023-11.
Reported beside audit-found
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- One of the five incomplete ECD classrooms.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 54, as at 2022, audit physical verification, confidence 4 of 5; finding audit-2021-22-32 - Site visit November 2023: works stalled; contractor not on site; no extension.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 46, as at 2023-11, audit physical verification, confidence 4 of 5; finding audit-2022-23-16
Audit findings: audit-2021-22-32, audit-2022-23-16
Amounts as printed (2)
- contract sum: KSh 3,888,053 (FY 2022/23; “contract sum”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 46
- paid cumulative: KSh 2,570,332 (FY 2022/23; “paid by 30 June 2023”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 46
- One of the five incomplete ECD classrooms.
Drilling and equipping of nine boreholes in Ugunja, Alego and Rarieda sub-counties
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 54 (audit physical verification). Latest evidence 2022.
Reported beside audit-found
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- Physical verification of sampled boreholes (Alara, Pala Kobong and Kolo primary schools): not equipped; contractors not on site; no extension.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 54, as at 2022, audit physical verification, confidence 4 of 5; finding audit-2021-22-33
Audit findings: audit-2021-22-33
Amounts as printed (2)
- contract sum: KSh 29,040,488 (FY 2021/22; “contract sum”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 54
- paid in fy: KSh 9,640,750 (FY 2021/22; “paid (legible in the closing sentence)”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 54
- Physical verification of sampled boreholes (Alara, Pala Kobong and Kolo primary schools): not equipped; contractors not on site; no extension.
Supply and installation of machines, wiring repairs and construction of a powerhouse at Madiany Ginnery
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 54 (audit physical verification). Latest evidence 2022-11-15. Works were done but the facility was not operational; no source reports completion.
Reported beside audit-found
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- Visit 15 Nov 2022: no power, cracked powerhouse slab, project not operational.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 54, as at 2022-11-15, audit physical verification, confidence 4 of 5; finding audit-2021-22-34
Audit findings: audit-2021-22-34
Amounts as printed (1)
- contract sum: KSh 10,237,191 (FY 2021/22; “contract sum”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 54
- Visit 15 Nov 2022: no power, cracked powerhouse slab, project not operational.
Construction of Kagwa Dispensary laboratory
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 54 (audit physical verification). Latest evidence 2022-07. Completion is as reported by the county; no independent check is recorded. Completion rests on the county's technical inspection report quoted in the audit. The audit visit found the laboratory unused but does not itself state that the works were complete, so it is not marked independently verified.
Reported beside audit-found
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- Works certified complete by a county technical inspection report (21 June 2021); audit site verification in July 2022 found the laboratory not in use.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 54, as at 2022-07, audit physical verification, confidence 4 of 5; finding audit-2021-22-35
Audit findings: audit-2021-22-35
Amounts as printed (1)
- certified cumulative: KSh 4,326,869 (FY 2021/22; “works certified complete as per bills of quantities”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 54
- Works certified complete by a county technical inspection report (21 June 2021); audit site verification in July 2022 found the laboratory not in use.
Construction of Modern Market in Ukwala Market
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 47 (audit physical verification). Latest evidence 2023-09.
Reported beside audit-found
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- Physical verification September 2023: floor works, stalls and electrical works incomplete; contractor had abandoned the project; performance bond expired.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 47, as at 2023-09, audit physical verification, confidence 4 of 5; finding audit-2022-23-18
Audit findings: audit-2022-23-18
Amounts as printed (2)
- contract sum: KSh 5,740,187.46 (FY 2022/23; “contract award”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 47
- paid cumulative: KSh 4,252,545 (FY 2022/23; “paid to date”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 47
- Physical verification September 2023: floor works, stalls and electrical works incomplete; contractor had abandoned the project; performance bond expired.
Construction of Nyadorera Modern Market
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 47 (audit physical verification). Latest evidence 2023-11.
Reported beside audit-found
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- Visit November 2023: floor, surface, painting and toilet works incomplete; contractor not on site; bond expired.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 47, as at 2023-11, audit physical verification, confidence 4 of 5; finding audit-2022-23-19
Audit findings: audit-2022-23-19
Amounts as printed (2)
- contract sum: KSh 11,665,784 (FY 2022/23; “contract sum”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 47
- paid cumulative: KSh 8,532,406 (FY 2022/23; “paid as at 30 June 2023”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 47
- Visit November 2023: floor, surface, painting and toilet works incomplete; contractor not on site; bond expired.
Fencing and gravelling works at Akala and Ramba Markets
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 47 (audit physical verification). Latest evidence 2023-10.
Reported beside audit-found
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- 73% complete (as stated). Interim certificates (22 June 2022): Ramba 88%, Akala 55%; site visits October 2023 found remaining works not done; overall 73%.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 47, as at 2023-10, audit physical verification, confidence 4 of 5; finding audit-2022-23-20
Audit findings: audit-2022-23-20
Amounts as printed (1)
- contract sum: KSh 7,715,774 (FY 2022/23; “contract price”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 47
- 73% complete (as stated). Interim certificates (22 June 2022): Ramba 88%, Akala 55%; site visits October 2023 found remaining works not done; overall 73%.
Drilling and equipping of Aila WC Borehole
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 48 (audit physical verification). Latest evidence 2023-08.
Reported beside audit-found, where sources differ
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- County inspection and acceptance report says fully executed; physical verification August 2023 found no drilling at the site. Management said works were done elsewhere, without documents.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 48, as at 2023-08, audit physical verification, confidence 4 of 5; finding audit-2022-23-21
Where the sources differ
- County acceptance report (fully executed) against no borehole found at the contracted site.
Audit findings: audit-2022-23-21
Amounts as printed (1)
- contract sum: KSh 4,479,975 (FY 2022/23; “contract sum”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 48
- County inspection and acceptance report says fully executed; physical verification August 2023 found no drilling at the site. Management said works were done elsewhere, without documents.
Proposed construction of perimeter wall at Migwena Sports and Cultural Centre (Piny Luo)
Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483 (cob report county data). Latest evidence 2025-06-30. Completion is as reported by the county; no independent check is recorded.
Reported beside audit-found, where sources differ
Reported by the county or the Controller of Budget
- 100% complete (as stated). County: implementation status 100%.
County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483, as at 2025-06-30, cob report county data, confidence 4 of 5
Found by the Auditor-General
- Physical verification September 2024: keying and plaster differ from the bill of quantities; project not complete; only a perimeter wall exists.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 54, as at 2024-09, audit physical verification, confidence 4 of 5; finding audit-2023-24-27
Where the sources differ
- County reports 100% at 30 June 2025; the September 2024 audit inspection found it incomplete and not to specification.
- Audit KSh 28,718,584 paid in FY 2023/24; county cumulative KSh 28,834,584 at 30 June 2025.
Audit findings: audit-2023-24-27
Amounts as printed (4)
- contract sum: KSh 33,841,097 (FY 2023/24; “contract sum”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 54
- paid in fy: KSh 28,718,584 (FY 2023/24; “cumulative payments, certificates 1 and 2 (85%)”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 54
- contract sum: KSh 33,841,097.5 (FY 2024/25; “Contract sum”) County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483
- paid cumulative: KSh 28,834,584 (FY 2024/25; “Cumulative expenditure as of 30 June 2025”) County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483
- 100% complete (as stated). County: implementation status 100%.
Proposed washroom, gravelling works, waterworks, powerhouse and electrification at Migwena
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 55 (audit documentary review). Latest evidence 2024.
Reported beside audit-found
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- Paid KSh 4,350,440; no approved extension of time after the intended completion of 8 Aug 2024.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 55, as at 2024, audit documentary review, confidence 4 of 5; finding audit-2023-24-28
Audit findings: audit-2023-24-28
Amounts as printed (2)
- contract sum: KSh 18,630,456 (FY 2023/24; “contract sum”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 55
- paid in fy: KSh 4,350,440 (FY 2023/24; “paid for works done”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 55
- Paid KSh 4,350,440; no approved extension of time after the intended completion of 8 Aug 2024.
Construction of County Aggregation and Industrial Park
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 54 (audit physical verification). Latest evidence 2025-10.
Reported beside audit-found, where sources differ
Reported by the county or the Controller of Budget
- 15% complete (as stated). County: implementation status 15%.
County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516, as at 2024-06-30, cob report county data, confidence 3 of 5
Found by the Auditor-General
- Physical inspection 16 Sep 2024: foundations for some warehouses only; no plant, materials or ongoing work on site.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 55, as at 2024-09-16, audit physical verification, confidence 4 of 5; finding audit-2023-24-30 - 12% complete (as stated). Progress report of 9 Sep 2024: 12% complete; physical inspection October 2025: contractor not on site, project stalled.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 54, as at 2025-10, audit physical verification, confidence 3 of 5; finding audit-2024-25-18
Where the sources differ
- FY 2023/24 audit: 28 weeks; FY 2024/25 audit: 80 weeks.
Audit findings: audit-2023-24-30, audit-2024-25-18
Amounts as printed (6)
- contract sum: KSh 483,688,922.23 (FY 2023/24; “contract sum (multi-year project)”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 55
- advance: KSh 48,368,892.2 (FY 2023/24; “advance payment”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 55
- contract sum: KSh 483,688,922 (FY 2023/24; “Contract sum”) County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516
- paid cumulative: KSh 48,368,892 (FY 2023/24; “Amount paid to date”) County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516
- contract sum: KSh 483,688,922 (FY 2024/25; “cost (co-funded equally with the National Government)”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 54
- other payment: KSh 62,500,000 (FY 2024/25; “National Government transfer as at 30 March 2025”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 54
- 15% complete (as stated). County: implementation status 15%.
Proposed Construction of Yala Cattle Ring in Yala Township Ward
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 56 (audit physical verification). Latest evidence 2024.
Reported beside audit-found
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- Physical inspection: completion date elapsed; contractor not on site.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 56, as at 2024, audit physical verification, confidence 4 of 5; finding audit-2023-24-31
Audit findings: audit-2023-24-31
Amounts as printed (1)
- contract sum: KSh 4,500,962.55 (FY 2023/24; “contract price inclusive of 16% VAT”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 56
- Physical inspection: completion date elapsed; contractor not on site.
Construction of four door flushable toilets and four bathrooms at Akala Health Centre
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 56 (audit physical verification). Latest evidence 2024-09-17.
Reported beside audit-found
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- 36% complete (as stated). Certified 36% on 1 Apr 2024; inspection 17 Sep 2024 found no work since; only substructure and wall frames.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 56, as at 2024-09-17, audit physical verification, confidence 4 of 5; finding audit-2023-24-32
Audit findings: audit-2023-24-32
Amounts as printed (2)
- contract sum: KSh 3,215,578.8 (FY 2023/24; “contract sum”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 56
- paid in fy: KSh 1,000,000 (FY 2023/24; “paid against invoice of 8 Apr 2024”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024, PDF p. 56
- 36% complete (as stated). Certified 36% on 1 Apr 2024; inspection 17 Sep 2024 found no work since; only substructure and wall frames.
Construction of ECD Block at Maranyona Primary School
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 54 (audit physical verification). Latest evidence 2025-07.
Reported beside audit-found
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- Physical inspection July 2025: not completed over 25 months from the contract date; painting, tiling, glazing and latrine incomplete.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 54, as at 2025-07, audit physical verification, confidence 3 of 5; finding audit-2024-25-19
Audit findings: audit-2024-25-19
Amounts as printed (1)
- contract sum: KSh 4,134,669 (FY 2024/25; “contract sum”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 54
- Physical inspection July 2025: not completed over 25 months from the contract date; painting, tiling, glazing and latrine incomplete.
Proposed completion of ECD Block at Nyabera Primary School
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 55 (audit physical verification). Latest evidence 2025-07.
Reported beside audit-found
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- As at July 2025 the project had stalled; contractor not on site; site neglected.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 55, as at 2025-07, audit physical verification, confidence 3 of 5; finding audit-2024-25-21
Audit findings: audit-2024-25-21
Amounts as printed (1)
- contract sum: KSh 4,307,957 (FY 2024/25; “contract sum”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 55
- As at July 2025 the project had stalled; contractor not on site; site neglected.
Construction of a modern Early Childhood Development Education (ECDE) Centre in Bondo Sub-County
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 58 (audit physical verification). Latest evidence 2025-10. Under construction with unapproved design changes; no completion percentage printed.
Reported beside audit-found
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- Physical inspections July and October 2025: unauthorised changes (roof fixings, windows, truss spacing 4.4 m against 2 m).
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 58, as at 2025-10, audit physical verification, confidence 3 of 5; finding audit-2024-25-30
Audit findings: audit-2024-25-30
Amounts as printed (1)
- advance: KSh 10,931,825 (FY 2024/25; “advance payment (20% of the contract sum)”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 58
- Physical inspections July and October 2025: unauthorised changes (roof fixings, windows, truss spacing 4.4 m against 2 m).
Supply, delivery, installation and commissioning of mortuary cold-room plant at Bondo Sub-County Hospital
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 59 (audit physical verification). Latest evidence 2025-10.
Reported beside audit-found, where sources differ
Reported by the county or the Controller of Budget
- 100% complete (as stated). County: implementation status 100%.
County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483, as at 2025-06-30, cob report county data, confidence 4 of 5
Found by the Auditor-General
- At the audit in October 2025 the cold-room plant was not yet installed; contractor on site; contract period lapsed without extension.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 59, as at 2025-10, audit physical verification, confidence 3 of 5; finding audit-2024-25-31
Where the sources differ
- County reports 100% at 30 June 2025; the October 2025 audit found the plant not installed.
Audit findings: audit-2024-25-31
Amounts as printed (3)
- contract sum: KSh 54,685,880 (FY 2024/25; “contract sum”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 59
- contract sum: KSh 54,685,880 (FY 2024/25; “Contract sum”) County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483
- paid cumulative: KSh 51,785,880 (FY 2024/25; “Cumulative expenditure as of 30 June 2025”) County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483
- 100% complete (as stated). County: implementation status 100%.
Supply, delivery and installation of medical equipment at Siaya Hospital Theatre Complex
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 56 (audit physical verification). Latest evidence 2025-10.
Reported beside audit-found, where sources differ
Reported by the county or the Controller of Budget
- 100% complete (as stated). County: implementation status 100%.
County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483, as at 2025-06-30, cob report county data, confidence 3 of 5
Found by the Auditor-General
- Physical inspection October 2025: equipment delivered 6 Feb 2025 but not installed or commissioned; some stored in open spaces.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 56, as at 2025-10, audit physical verification, confidence 3 of 5; finding audit-2024-25-22
Where the sources differ
- County reports 100%; the October 2025 audit found the equipment not installed.
Audit findings: audit-2024-25-22
Amounts as printed (3)
- contract sum: KSh 22,974,650 (FY 2024/25; “cost”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 55
- paid cumulative: KSh 20,477,338 (FY 2024/25; “paid (89%)”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 55
- paid cumulative: KSh 20,477,338 (FY 2024/25; “Cumulative expenditure as of 30 June 2025”) County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483
- 100% complete (as stated). County: implementation status 100%.
Proposed construction of maternity block at Malunga Dispensary
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 56 (audit physical verification). Latest evidence 2025-07. Completion seen by the Auditor-General on site (July 2025). The facility was idle, so complete does not mean in service.
Reported beside audit-found
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- Physical verification July 2025 "revealed that the facility was complete but remained idle".
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 56, as at 2025-07, audit physical verification, confidence 3 of 5; finding audit-2024-25-23
Audit findings: audit-2024-25-23
Amounts as printed (1)
- contract sum: KSh 4,400,000 (FY 2024/25; “cost”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 56
- Physical verification July 2025 "revealed that the facility was complete but remained idle".
Drilling and equipping of two boreholes at Ligose Primary and Ligala Dispensary
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 56 (audit physical verification). Latest evidence 2025-07. Built, but neither borehole works as intended; no source states completion.
Reported beside audit-found
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- Physical inspection July 2025: Ligose borehole non-operational (vandalism); Ligala has leaking pipes and corroded tank supports.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 56, as at 2025-07, audit physical verification, confidence 3 of 5; finding audit-2024-25-23
Audit findings: audit-2024-25-23
Amounts as printed (1)
- contract sum: KSh 5,819,100 (FY 2024/25; “contract cost, two boreholes”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 56
- Physical inspection July 2025: Ligose borehole non-operational (vandalism); Ligala has leaking pipes and corroded tank supports.
Drilling and equipping of a borehole at Yenga
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 56 (audit physical verification). Latest evidence 2025-10. No contract sum printed for this borehole.
Reported beside audit-found
Reported by the county or the Controller of Budget
No county report recorded.
Found by the Auditor-General
- Physical verification October 2025: not functional (no flow from the elevated tank); poor paint on the tank supports.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025, PDF p. 56, as at 2025-10, audit physical verification, confidence 3 of 5; finding audit-2024-25-23
Audit findings: audit-2024-25-23
- Physical verification October 2025: not functional (no flow from the elevated tank); poor paint on the tank supports.
Supply, installation, configuration, customisation, testing, commissioning and support of an Enterprise Resource Planning (ERP) management information system
Status from Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 49 (audit documentary review). Latest evidence 2023.
Reported beside audit-found, where sources differ
Reported by the county or the Controller of Budget
- 20% complete (as stated). County: 20%, "Project still ongoing".
County Governments Budget Implementation Review Report FY 2021/22, PDF p. 413, as at 2022-06-30, cob report county data, confidence 3 of 5
Found by the Auditor-General
- Still in development 14 months after the contract.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 51, as at 2022, audit documentary review, confidence 4 of 5; finding audit-2021-22-25 - Interviews with ICT staff: still under development 24 months after signing.
Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 49, as at 2023, audit documentary review, confidence 4 of 5; finding audit-2022-23-23
Where the sources differ
- CoB FY 2021/22 KSh 10,000,000 paid to date against the FY 2021/22 audit KSh 21,600,000.
Audit findings: audit-2021-22-25, audit-2022-23-23
Amounts as printed (5)
- contract sum: KSh 72,420,000 (FY 2021/22; “Contract sum”) County Governments Budget Implementation Review Report FY 2021/22, PDF p. 413
- paid cumulative: KSh 10,000,000 (FY 2021/22; “Amount paid to date”) County Governments Budget Implementation Review Report FY 2021/22, PDF p. 413
- paid cumulative: KSh 21,600,000 (FY 2021/22; “paid”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022, PDF p. 51
- contract sum: KSh 72,420,000 (FY 2022/23; “contract sum”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 49
- paid cumulative: KSh 28,000,000 (FY 2022/23; “paid as at June 2023”) Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023., PDF p. 49
- 20% complete (as stated). County: 20%, "Project still ongoing".
Drilling and equipping of boreholes and construction of water kiosks in the ward offices
Status from Report of the Auditor-General on County Assembly of Siaya for the Year Ended 30 June, 2024, PDF p. 56 (audit physical verification). Latest evidence 2024-09.
Reported beside audit-found, where sources differ
Reported by the county or the Controller of Budget
- 50% complete (as stated). County: 50%, "Projects still ongoing".
County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412, as at 2022-06-30, cob report county data, confidence 3 of 5 - 51.6% complete (as stated). County: 51.6%.
Annual County Governments Budget Implementation Review Report FY 2022/23, PDF p. 581, as at 2023-06-30, cob report county data, confidence 4 of 5
Found by the Auditor-General
- Still incomplete at the audit in November 2023 after extension to May 2022.
Report of the Auditor-General on County Assembly of Siaya for the Year Ended 30 June 2023, PDF p. 54, as at 2023-11, audit documentary review, confidence 4 of 5; finding audit-asm-2022-23-06 - Field verification September 2024: projects stalled; water kiosks completed but unlabelled.
Report of the Auditor-General on County Assembly of Siaya for the Year Ended 30 June, 2024, PDF p. 56, as at 2024-09, audit physical verification, confidence 4 of 5; finding audit-asm-2023-24-06
Where the sources differ
- KSh 80,730,095 (CoB 2021/22), 125,662,548 (CoB 2022/23) and 117,133,552 (audit). The audit counts 28 ward offices, the CoB tables 30.
Audit findings: audit-asm-2022-23-06, audit-asm-2023-24-06
Amounts as printed (7)
- contract sum: KSh 80,730,095 (FY 2021/22; “Contract sum (OCR "80,730,09s")”) County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412
- paid cumulative: KSh 19,066,450 (FY 2021/22; “Amount paid to date (OCR "r9,066,450")”) County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412
- contract sum: KSh 125,662,548 (FY 2022/23; “Contract sum”) Annual County Governments Budget Implementation Review Report FY 2022/23, PDF p. 581
- approved budget: KSh 63,558,814 (FY 2022/23; “Budget”) Annual County Governments Budget Implementation Review Report FY 2022/23, PDF p. 581
- paid cumulative: KSh 64,836,353 (FY 2022/23; “Amount paid to date”) Annual County Governments Budget Implementation Review Report FY 2022/23, PDF p. 581
- contract sum: KSh 117,133,552 (FY 2022/23; “contract sum (28 ward offices)”) Report of the Auditor-General on County Assembly of Siaya for the Year Ended 30 June 2023, PDF p. 54
- paid cumulative: KSh 64,836,353 (FY 2022/23; “payments made”) Report of the Auditor-General on County Assembly of Siaya for the Year Ended 30 June 2023, PDF p. 54
- 50% complete (as stated). County: 50%, "Projects still ongoing".
Construction of meeting halls in the ward offices
Status from Report of the Auditor-General on County Assembly of Siaya for the Year Ended 30 June, 2024, PDF p. 56 (audit physical verification). Latest evidence 2024-09.
Reported beside audit-found, where sources differ
Reported by the county or the Controller of Budget
- 30% complete (as stated). County: 30%, ongoing.
County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412, as at 2022-06-30, cob report county data, confidence 3 of 5 - 60.1% complete (as stated). County: 60.1%.
Annual County Governments Budget Implementation Review Report FY 2022/23, PDF p. 581, as at 2023-06-30, cob report county data, confidence 4 of 5
Found by the Auditor-General
- Notices issued to contractors 23 May 2024 over the quality of works; field verification September 2024: stalled.
Report of the Auditor-General on County Assembly of Siaya for the Year Ended 30 June, 2024, PDF p. 56, as at 2024-09, audit physical verification, confidence 4 of 5; finding audit-asm-2023-24-06
Where the sources differ
- The audit dates the meeting-hall contracts 1 June 2023, but CoB tables show payments for meeting halls in FY 2021/22 and FY 2022/23.
Audit findings: audit-asm-2023-24-06
Amounts as printed (5)
- contract sum: KSh 65,000,000 (FY 2021/22; “Contract sum”) County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412
- paid cumulative: KSh 15,099,708 (FY 2021/22; “Amount paid to date”) County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412
- contract sum: KSh 149,913,785 (FY 2022/23; “Contract sum”) Annual County Governments Budget Implementation Review Report FY 2022/23, PDF p. 581
- approved budget: KSh 104,900,292 (FY 2022/23; “Budget”) Annual County Governments Budget Implementation Review Report FY 2022/23, PDF p. 581
- paid cumulative: KSh 90,168,197 (FY 2022/23; “Amount paid to date”) Annual County Governments Budget Implementation Review Report FY 2022/23, PDF p. 581
- 30% complete (as stated). County: 30%, ongoing.
Construction and Fencing of Ward Offices
Status from County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516 (cob report county data). Latest evidence 2024-06-30. Last reported at 78.3% (30 June 2024); no later source.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 50% complete (as stated). County: 50%, ongoing.
County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412, as at 2022-06-30, cob report county data, confidence 3 of 5 - 77.4% complete (as stated). County: 77.4%.
Annual County Governments Budget Implementation Review Report FY 2022/23, PDF p. 580, as at 2023-06-30, cob report county data, confidence 4 of 5 - 78.3% complete (as stated). County: 78.3%.
County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516, as at 2024-06-30, cob report county data, confidence 3 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (7)
- contract sum: KSh 57,934,334 (FY 2021/22; “Contract sum”) County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412
- paid cumulative: KSh 19,205,163 (FY 2021/22; “Amount paid to date”) County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412
- contract sum: KSh 160,167,929 (FY 2022/23; “Contract sum”) Annual County Governments Budget Implementation Review Report FY 2022/23, PDF p. 580
- approved budget: KSh 34,759,153 (FY 2022/23; “Budget”) Annual County Governments Budget Implementation Review Report FY 2022/23, PDF p. 580
- paid cumulative: KSh 124,001,160 (FY 2022/23; “Amount paid to date”) Annual County Governments Budget Implementation Review Report FY 2022/23, PDF p. 580
- contract sum: KSh 160,167,929 (FY 2023/24; “Contract sum”) County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516
- paid cumulative: KSh 125,408,776 (FY 2023/24; “Amount paid to date”) County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516
- 50% complete (as stated). County: 50%, ongoing.
Networking of Ward offices
Status from County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516 (cob report county data). Latest evidence 2024-06-30.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 98.4% complete (as stated). County: 98.4%.
County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516, as at 2024-06-30, cob report county data, confidence 3 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (2)
- contract sum: KSh 102,183,608 (FY 2023/24; “Contract sum”) County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516
- paid cumulative: KSh 100,520,437 (FY 2023/24; “Amount paid to date”) County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516
- 98.4% complete (as stated). County: 98.4%.
Acquisition, Supervision and Installation of Hansard and Information Technology System Infrastructure and Equipment Development
Status from County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412 (cob report county data). Latest evidence 2022-06-30. Completion is as reported by the county; no independent check is recorded.
Reported beside audit-found, where sources differ
Reported by the county or the Controller of Budget
- 54.2% absorption of the project budget.
Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272, as at 2019-06-30, cob report county data, confidence 5 of 5 - 100% complete (as stated). County: 100%, "Project completed and in use".
County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412, as at 2022-06-30, cob report county data, confidence 3 of 5
Found by the Auditor-General
No audit evidence recorded.
Where the sources differ
- FY 2018/19 budget KSh 60,735,050 against a FY 2021/22 contract sum of KSh 14,564,983; may be separate phases.
Amounts as printed (4)
- approved budget: KSh 60,735,050 (FY 2018/19; “Project Budget”) Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272
- expenditure in fy: KSh 32,897,056 (FY 2018/19; “Project Expenditure”) Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272
- contract sum: KSh 14,564,983 (FY 2021/22; “Contract sum”) County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412
- paid cumulative: KSh 14,564,983 (FY 2021/22; “Amount paid to date”) County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412
- 54.2% absorption of the project budget.
Development, Installation and Commissioning of Asset Inventory and fleet Management System
Status from County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412 (cob report county data). Latest evidence 2022-06-30. Completion is as reported by the county; no independent check is recorded.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 100% complete (as stated). County: 100%, "Project complete and in use".
County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412, as at 2022-06-30, cob report county data, confidence 3 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (2)
- contract sum: KSh 12,850,000 (FY 2021/22; “Contract sum”) County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412
- paid cumulative: KSh 12,260,000 (FY 2021/22; “Amount paid to date”) County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412
- 100% complete (as stated). County: 100%, "Project complete and in use".
Development, Supply, Installation and Commissioning of Virtual Conference Boardrooms
Status from County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412 (cob report county data). Latest evidence 2022-06-30. Last reported June 2022; no later source.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 70% complete (as stated). County: 70%, "Project still ongoing".
County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412, as at 2022-06-30, cob report county data, confidence 3 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (2)
- contract sum: KSh 14,792,974 (FY 2021/22; “Contract sum (OCR "r4,792,974")”) County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412
- paid cumulative: KSh 11,476,177 (FY 2021/22; “Amount paid to date (OCR "tt,476,177")”) County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412
- 70% complete (as stated). County: 70%, "Project still ongoing".
Construction of modern market at Sigomere
Status from County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412 (cob report county data). Latest evidence 2022-06-30. Last reported June 2022.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 80% complete (as stated). County: 80%, "Project still ongoing".
County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412, as at 2022-06-30, cob report county data, confidence 3 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (3)
- contract sum: KSh 17,450,085 (FY 2021/22; “Contract sum”) County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412
- approved budget: KSh 4,800,000 (FY 2021/22; “Budget”) County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412
- paid cumulative: KSh 11,765,952 (FY 2021/22; “Amount paid to date (OCR "t1,765,952")”) County Governments Budget Implementation Review Report FY 2021/22, PDF p. 412
- 80% complete (as stated). County: 80%, "Project still ongoing".
Installation of High masts lighting in Siaya County
Status from County Governments Budget Implementation Review Report FY 2021/22, PDF p. 411 (cob report county data). Latest evidence 2022-06-30.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 70% complete (as stated). County: 70%, "Projects still ongoing".
County Governments Budget Implementation Review Report FY 2021/22, PDF p. 411, as at 2022-06-30, cob report county data, confidence 3 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (2)
- contract sum: KSh 59,865,960 (FY 2021/22; “Contract sum”) County Governments Budget Implementation Review Report FY 2021/22, PDF p. 411
- paid cumulative: KSh 25,105,080 (FY 2021/22; “Amount paid to date (OCR "25, I 05,080")”) County Governments Budget Implementation Review Report FY 2021/22, PDF p. 411
- 70% complete (as stated). County: 70%, "Projects still ongoing".
Installation of High mast lights in various locations in Siaya County
Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483 (cob report county data). Latest evidence 2025-06-30. Delayed on the county's own dates. May be the same programme as the FY 2021/22 high-mast entry; not merged because the contract sums differ.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 65% complete (as stated). County: 65% against an expected completion of 30 Sep 2022.
County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483, as at 2025-06-30, cob report county data, confidence 4 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (3)
- contract sum: KSh 179,009,460 (FY 2024/25; “Contract sum”) County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483
- paid in fy: KSh 66,241,800 (FY 2024/25; “Amount paid in FY 2024/25”) County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483
- paid cumulative: KSh 132,452,280 (FY 2024/25; “Cumulative expenditure as of 30 June 2025”) County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483
- 65% complete (as stated). County: 65% against an expected completion of 30 Sep 2022.
Supply, Installation, and Maintenance of the Integrated Revenue Management System for the County Government of Siaya
Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483 (cob report county data). Latest evidence 2025-06-30.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 95% complete (as stated). County: 95%.
County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483, as at 2025-06-30, cob report county data, confidence 4 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (2)
- contract sum: KSh 50,914,550.92 (FY 2024/25; “Contract sum”) County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483
- paid cumulative: KSh 24,986,440 (FY 2024/25; “Cumulative expenditure as of 30 June 2025”) County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483
- 95% complete (as stated). County: 95%.
Promotion of agro-processing rice (Installation of Siriwo rice mill)
Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483 (cob report county data). Latest evidence 2025-06-30. Completion is as reported by the county; no independent check is recorded.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 100% complete (as stated). County: 100%.
County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483, as at 2025-06-30, cob report county data, confidence 4 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (2)
- contract sum: KSh 31,020,000.05 (FY 2024/25; “Contract sum”) County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483
- paid cumulative: KSh 31,020,000.05 (FY 2024/25; “Cumulative expenditure as of 30 June 2025”) County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483
- 100% complete (as stated). County: 100%.
Construction of rice milling plant
Status from County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516 (cob report county data). Latest evidence 2024-06-30.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 83% complete (as stated). County: 83%. Row partly illegible; name from the low-resolution OCR.
County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516, as at 2024-06-30, cob report county data, confidence 2 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (2)
- contract sum: KSh 47,721,373 (FY 2023/24; “Contract sum”) County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516
- paid cumulative: KSh 40,000,000 (FY 2023/24; “Amount paid to date”) County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516
- 83% complete (as stated). County: 83%. Row partly illegible; name from the low-resolution OCR.
Upgrade to bitumen standard. Rabango - Siaya Township School Road
Status from County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516 (cob report county data). Latest evidence 2024-06-30.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 90% complete (as stated). County: 90%.
County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516, as at 2024-06-30, cob report county data, confidence 3 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (2)
- contract sum: KSh 52,542,620 (FY 2023/24; “Contract sum”) County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516
- paid cumulative: KSh 50,000,000 (FY 2023/24; “Amount paid to date”) County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516
- 90% complete (as stated). County: 90%.
Upgrade to bitumen standard. Yala ring road
Status from County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516 (cob report county data). Latest evidence 2024-06-30. Completion is as reported by the county; no independent check is recorded.
Reported beside audit-found, where sources differ
Reported by the county or the Controller of Budget
- 100% complete (as stated). County: 100%.
County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516, as at 2024-06-30, cob report county data, confidence 3 of 5
Found by the Auditor-General
No audit evidence recorded.
Where the sources differ
- Amount paid (KSh 39,850,732) exceeds the contract sum (KSh 26,900,000) as printed.
Amounts as printed (2)
- contract sum: KSh 26,900,000 (FY 2023/24; “Contract sum”) County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516
- paid cumulative: KSh 39,850,732 (FY 2023/24; “Amount paid to date (above the contract sum, as printed)”) County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516
- 100% complete (as stated). County: 100%.
Purchase of land for bus park
Status from County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516 (cob report county data). Latest evidence 2024-06-30. Completion is as reported by the county; no independent check is recorded.
Reported beside audit-found, where sources differ
Reported by the county or the Controller of Budget
- 100% complete (as stated). County: 100%.
County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516, as at 2024-06-30, cob report county data, confidence 3 of 5
Found by the Auditor-General
No audit evidence recorded.
Where the sources differ
- 100% reported with KSh 15,000,000 of KSh 23,000,000 paid.
Amounts as printed (2)
- contract sum: KSh 23,000,000 (FY 2023/24; “Contract sum”) County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516
- paid cumulative: KSh 15,000,000 (FY 2023/24; “Amount paid to date”) County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516
- 100% complete (as stated). County: 100%.
Refrigeration at Siaya Referral Morgue (48-body capacity refrigeration machine)
Status from County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516 (cob report county data). Latest evidence 2024-06-30. Completion is as reported by the county; no independent check is recorded.
Reported beside audit-found, where sources differ
Reported by the county or the Controller of Budget
- 70% complete (as stated). County: 70%.
Annual County Governments Budget Implementation Review Report FY 2022/23, PDF p. 581, as at 2023-06-30, cob report county data, confidence 3 of 5 - 100% complete (as stated). County: 100%.
County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516, as at 2024-06-30, cob report county data, confidence 3 of 5
Found by the Auditor-General
No audit evidence recorded.
Where the sources differ
- FY 2022/23 names the Siaya Referral morgue only; FY 2023/24 names Siaya and Bondo hospital morgues with the same contract sum.
Amounts as printed (5)
- contract sum: KSh 50,227,989.24 (FY 2022/23; “Contract sum”) Annual County Governments Budget Implementation Review Report FY 2022/23, PDF p. 581
- approved budget: KSh 50,000,000 (FY 2022/23; “Budget”) Annual County Governments Budget Implementation Review Report FY 2022/23, PDF p. 581
- paid cumulative: KSh 35,159,593 (FY 2022/23; “Amount paid to date (OCR "35,r59,593")”) Annual County Governments Budget Implementation Review Report FY 2022/23, PDF p. 581
- contract sum: KSh 50,227,989 (FY 2023/24; “Contract sum”) County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516
- paid cumulative: KSh 47,659,593 (FY 2023/24; “Amount paid to date”) County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516
- 70% complete (as stated). County: 70%.
Construction of Abura Dam
Status from Annual County Governments Budget Implementation Review Report FY 2022/23, PDF p. 581 (cob report county data). Latest evidence 2023-06-30. Completion is as reported by the county; no independent check is recorded.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 100% complete (as stated). County: 100%.
Annual County Governments Budget Implementation Review Report FY 2022/23, PDF p. 581, as at 2023-06-30, cob report county data, confidence 4 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (3)
- contract sum: KSh 44,044,800 (FY 2022/23; “Contract sum”) Annual County Governments Budget Implementation Review Report FY 2022/23, PDF p. 581
- approved budget: KSh 44,620,240 (FY 2022/23; “Budget”) Annual County Governments Budget Implementation Review Report FY 2022/23, PDF p. 581
- paid cumulative: KSh 44,044,800 (FY 2022/23; “Amount paid to date”) Annual County Governments Budget Implementation Review Report FY 2022/23, PDF p. 581
- 100% complete (as stated). County: 100%.
Completion of Randago VTC
Status from County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516 (cob report county data). Latest evidence 2024-06-30. Completion is as reported by the county; no independent check is recorded.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 100% complete (as stated). County: 100% (OCR "vompiction of Randago").
County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516, as at 2024-06-30, cob report county data, confidence 3 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (2)
- contract sum: KSh 3,293,368 (FY 2023/24; “Contract sum”) County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516
- paid cumulative: KSh 3,293,368 (FY 2023/24; “Amount paid to date”) County Governments Budget Implementation Review Report FY 2023/24, PDF p. 516
- 100% complete (as stated). County: 100% (OCR "vompiction of Randago").
Construction of bus park at Bondo
Status from County Governments Budget Implementation Review Report FY 2020/21, PDF p. 377 (cob report county data). Latest evidence 2021-06-30.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Absorption 52.7%; no completion status printed.
County Governments Budget Implementation Review Report FY 2020/21, PDF p. 377, as at 2021-06-30, cob report county data, confidence 3 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (2)
- approved budget: KSh 28,947,290 (FY 2020/21; “Budget”) County Governments Budget Implementation Review Report FY 2020/21, PDF p. 377
- expenditure in fy: KSh 15,244,220 (FY 2020/21; “Expenditure (absorption 52.7%)”) County Governments Budget Implementation Review Report FY 2020/21, PDF p. 377
- Absorption 52.7%; no completion status printed.
Equipping of Poye, Mbaga, Karapul, Uwasi, Nyamuango, Daho and Angolo Mkt
Status from County Governments Budget Implementation Review Report FY 2020/21, PDF p. 377 (cob report county data). Latest evidence 2021-06-30.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Absorption 100% of the budget; no completion status printed.
County Governments Budget Implementation Review Report FY 2020/21, PDF p. 377, as at 2021-06-30, cob report county data, confidence 3 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (2)
- approved budget: KSh 11,432,917 (FY 2020/21; “Budget (OCR "11,432,9t7")”) County Governments Budget Implementation Review Report FY 2020/21, PDF p. 377
- expenditure in fy: KSh 11,432,917 (FY 2020/21; “Expenditure (absorption 100%)”) County Governments Budget Implementation Review Report FY 2020/21, PDF p. 377
- Absorption 100% of the budget; no completion status printed.
Drilling of boreholes at Ochienga, Kobonyo, Okela, Bonde, Dhere, Utonga & Kanyichudo
Status from County Governments Budget Implementation Review Report FY 2020/21, PDF p. 377 (cob report county data). Latest evidence 2021-06-30.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Absorption 100% of the budget; no completion status printed.
County Governments Budget Implementation Review Report FY 2020/21, PDF p. 377, as at 2021-06-30, cob report county data, confidence 3 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (2)
- approved budget: KSh 11,338,862 (FY 2020/21; “Budget”) County Governments Budget Implementation Review Report FY 2020/21, PDF p. 377
- expenditure in fy: KSh 11,338,862 (FY 2020/21; “Expenditure (absorption 100%)”) County Governments Budget Implementation Review Report FY 2020/21, PDF p. 377
- Absorption 100% of the budget; no completion status printed.
Maintenance of River Yala and Lake Kanyaboli dykes
Status from Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272 (cob report county data). Latest evidence 2019-06-30.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Absorption 99.6%; no completion status printed.
Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272, as at 2019-06-30, cob report county data, confidence 5 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (2)
- approved budget: KSh 20,000,000 (FY 2018/19; “Project Budget”) Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272
- expenditure in fy: KSh 19,925,666 (FY 2018/19; “Project Expenditure”) Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272
- Absorption 99.6%; no completion status printed.
Construction of County Annex Siaya
Status from Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272 (cob report county data). Latest evidence 2019-06-30.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Absorption 34.3%; no completion status printed.
Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272, as at 2019-06-30, cob report county data, confidence 5 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (2)
- approved budget: KSh 35,000,000 (FY 2018/19; “Project Budget”) Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272
- expenditure in fy: KSh 11,995,022 (FY 2018/19; “Project Expenditure”) Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272
- Absorption 34.3%; no completion status printed.
Development of East Uyoma Water Project (co-funding of the project)
Status from Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272 (cob report county data). Latest evidence 2019-06-30.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Absorption 99.2%; no completion status printed.
Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272, as at 2019-06-30, cob report county data, confidence 5 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (2)
- approved budget: KSh 10,000,000 (FY 2018/19; “Project Budget”) Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272
- expenditure in fy: KSh 9,915,691 (FY 2018/19; “Project Expenditure”) Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272
- Absorption 99.2%; no completion status printed.
Construction of Pap - Kodero Twin Box Culvert FL
Status from Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272 (cob report county data). Latest evidence 2019-06-30.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Absorption 73.9%; no completion status printed.
Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272, as at 2019-06-30, cob report county data, confidence 5 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (2)
- approved budget: KSh 12,119,733 (FY 2018/19; “Project Budget”) Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272
- expenditure in fy: KSh 8,954,460 (FY 2018/19; “Project Expenditure”) Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272
- Absorption 73.9%; no completion status printed.
Routine Maintenance Of Ndai/Kanyaboli/Kubar Pr. Sch. /Obambo Pr. Sch. Road
Status from Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272 (cob report county data). Latest evidence 2019-06-30.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Absorption 99.8%; no completion status printed.
Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272, as at 2019-06-30, cob report county data, confidence 5 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (2)
- approved budget: KSh 8,265,600 (FY 2018/19; “Project Budget”) Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272
- expenditure in fy: KSh 8,252,145 (FY 2018/19; “Project Expenditure”) Annual County Governments Budget Implementation Review Report FY 2018/19, PDF p. 272
- Absorption 99.8%; no completion status printed.
Completion of the Apuoyo animal feed pelletizing plant
Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483 (cob report county data). Latest evidence 2025-06-30.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 25% complete (as stated). County stalled-projects list: "terminated"; 25% complete before stalling.
County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483, as at 2025-06-30, cob report county data, confidence 3 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (1)
- estimated value: KSh 1,500,000 (FY 2024/25; “Estimated Value of the Project”) County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483
- 25% complete (as stated). County stalled-projects list: "terminated"; 25% complete before stalling.
Fencing and installation of a gate at Kokach Beach
Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483 (cob report county data). Latest evidence 2025-06-30.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 0% complete (as stated). County stalled-projects list: "Not awarded due to budget deficit"; 0% complete before stalling.
County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483, as at 2025-06-30, cob report county data, confidence 3 of 5
Found by the Auditor-General
No audit evidence recorded.
- 0% complete (as stated). County stalled-projects list: "Not awarded due to budget deficit"; 0% complete before stalling.
Renovation and repairs of the Siriwo rice drying floor
Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483 (cob report county data). Latest evidence 2025-06-30.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 0% complete (as stated). County stalled-projects list: "Not implemented; the budget of Kshs.4,500,000 removed in the supplementary"; 0% complete before stalling.
County Governments Budget Implementation Review Report FY 2024/25, PDF p. 483, as at 2025-06-30, cob report county data, confidence 3 of 5
Found by the Auditor-General
No audit evidence recorded.
- 0% complete (as stated). County stalled-projects list: "Not implemented; the budget of Kshs.4,500,000 removed in the supplementary"; 0% complete before stalling.
Construction of modern washrooms at Ralayo beach
Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 484 (cob report county data). Latest evidence 2025-06-30.
Reported beside audit-found
Reported by the county or the Controller of Budget
- County stalled-projects list: "Budgetary Deficit".
County Governments Budget Implementation Review Report FY 2024/25, PDF p. 484, as at 2025-06-30, cob report county data, confidence 3 of 5
Found by the Auditor-General
No audit evidence recorded.
- County stalled-projects list: "Budgetary Deficit".
Acquisition of storage tanks for Bondo Sub-County Hospital
Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 484 (cob report county data). Latest evidence 2025-06-30.
Reported beside audit-found
Reported by the county or the Controller of Budget
- County stalled-projects list: "insufficient funding".
County Governments Budget Implementation Review Report FY 2024/25, PDF p. 484, as at 2025-06-30, cob report county data, confidence 3 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (1)
- estimated value: KSh 4,899,401 (FY 2024/25; “Estimated Value of the Project”) County Governments Budget Implementation Review Report FY 2024/25, PDF p. 484
- County stalled-projects list: "insufficient funding".
Completion of Oboch dispensary (Pending)
Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 484 (cob report county data). Latest evidence 2025-06-30.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 70% complete (as stated). County stalled-projects list: "insufficient funding"; 70% complete before stalling.
County Governments Budget Implementation Review Report FY 2024/25, PDF p. 484, as at 2025-06-30, cob report county data, confidence 3 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (1)
- estimated value: KSh 3,200,000 (FY 2024/25; “Estimated Value of the Project”) County Governments Budget Implementation Review Report FY 2024/25, PDF p. 484
- 70% complete (as stated). County stalled-projects list: "insufficient funding"; 70% complete before stalling.
Improving the sewer system and gate at the Rwambwa sub-County hospital
Status from County Governments Budget Implementation Review Report FY 2024/25, PDF p. 484 (cob report county data). Latest evidence 2025-06-30.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 70% complete (as stated). County stalled-projects list: "inadequate funding"; 70% complete before stalling.
County Governments Budget Implementation Review Report FY 2024/25, PDF p. 484, as at 2025-06-30, cob report county data, confidence 3 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (1)
- estimated value: KSh 1,200,000 (FY 2024/25; “Estimated Value of the Project”) County Governments Budget Implementation Review Report FY 2024/25, PDF p. 484
- 70% complete (as stated). County stalled-projects list: "inadequate funding"; 70% complete before stalling.
Complete Automation of Revenue
Status from County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 11 (county budget report). Latest evidence 2026-06-30.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 49.4% complete (as stated). County: 49.40%.
County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025, PDF p. 16, as at 2025-12-31, county budget report, confidence 4 of 5 - 86.72% complete (as stated). County: 86.72%.
County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026, PDF p. 13, as at 2026-03-31, county budget report, confidence 4 of 5 - 86.72% complete (as stated). County: 86.72%.
County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 11, as at 2026-06-30, county budget report, confidence 4 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (4)
- contract sum: KSh 33,013,561 (FY 2025/26; “Contract sum”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 11
- funding in fy: KSh 33,013,561 (FY 2025/26; “Total Funding in FY 2025/26”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 11
- expenditure in fy: KSh 16,314,695.69 (FY 2025/26; “Expenditure (accrual basis) in FY 2025/26 to 31 Dec 2025”) County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025, PDF p. 16
- paid cumulative: KSh 28,629,391 (FY 2025/26; “Cumulative project expenditure as of 30 June 2026”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 11
- 49.4% complete (as stated). County: 49.40%.
Completion of casualty and maternity complex at Yala SCH
Status from County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 11 (county budget report). Latest evidence 2026-06-30. Delayed on the county's own dates: 90% at 30 June 2026 against an expected completion of February 2026.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 86% complete (as stated). County: 86%.
County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025, PDF p. 16, as at 2025-12-31, county budget report, confidence 4 of 5 - 90% complete (as stated). County: 90%.
County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026, PDF p. 13, as at 2026-03-31, county budget report, confidence 4 of 5 - 90% complete (as stated). County: 90%.
County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 11, as at 2026-06-30, county budget report, confidence 4 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (3)
- contract sum: KSh 78,084,128 (FY 2025/26; “Contract sum”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 11
- funding in fy: KSh 30,000,000 (FY 2025/26; “Total Funding in FY 2025/26”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 11
- paid cumulative: KSh 30,881,701 (FY 2025/26; “Cumulative project expenditure as of 30 June 2026”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 11
- 86% complete (as stated). County: 86%.
Phased construction of Ugenya Sub County Office at Ukwala
Status from County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12 (county budget report). Latest evidence 2026-06-30.
Reported beside audit-found
Reported by the county or the Controller of Budget
- No completion percentage printed.
County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026, PDF p. 13, as at 2026-03-31, county budget report, confidence 4 of 5 - No completion percentage printed.
County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12, as at 2026-06-30, county budget report, confidence 4 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (4)
- contract sum: KSh 41,233,141.48 (FY 2025/26; “Contract sum”) County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026, PDF p. 13
- funding in fy: KSh 15,233,141 (FY 2025/26; “Total Funding in FY 2025/26”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12
- paid cumulative: KSh 8,246,628.3 (FY 2025/26; “Cumulative project expenditure as of 31 March 2026”) County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026, PDF p. 13
- paid cumulative: KSh 8,246,628 (FY 2025/26; “Cumulative project expenditure as of 30 June 2026”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12
- No completion percentage printed.
Phased construction of Gem Sub County Office at Yala
Status from County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026, PDF p. 13 (county budget report). Latest evidence 2026-03-31. Delayed on the county's own dates. Not in the Q4 table.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 2% complete (as stated). County: 2% against an expected completion of 12 Nov 2025.
County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026, PDF p. 13, as at 2026-03-31, county budget report, confidence 4 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (3)
- contract sum: KSh 41,593,818.75 (FY 2025/26; “Contract sum”) County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026, PDF p. 13
- funding in fy: KSh 15,593,819 (FY 2025/26; “Total Funding in FY 2025/26”) County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026, PDF p. 13
- paid cumulative: KSh 5,673,544.75 (FY 2025/26; “Cumulative project expenditure as of 31 March 2026”) County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026, PDF p. 13
- 2% complete (as stated). County: 2% against an expected completion of 12 Nov 2025.
Completion of upgrading to bitumen standard of Ndori market ring Road (phased)
Status from County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12 (county budget report). Latest evidence 2026-06-30. Completion is as reported by the county; no independent check is recorded. Phased project: 100% may refer to the phase funded in FY 2025/26.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 100% complete (as stated). County: 100%.
County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12, as at 2026-06-30, county budget report, confidence 4 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (3)
- contract sum: KSh 100,283,313 (FY 2025/26; “Contract sum”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12
- funding in fy: KSh 44,649,708 (FY 2025/26; “Total Funding in FY 2025/26”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12
- paid cumulative: KSh 43,990,003 (FY 2025/26; “Cumulative project expenditure as of 30 June 2026”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12
- 100% complete (as stated). County: 100%.
Completion of construction and equipping of Municipal Office complex - Phase 2 (multi- year project)
Status from County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12 (county budget report). Latest evidence 2026-06-30. Delayed on the county's own dates.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 60% complete (as stated). County: 60%.
County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026, PDF p. 13, as at 2026-03-31, county budget report, confidence 4 of 5 - 60% complete (as stated). County: 60% against an expected completion of 26 May 2026.
County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12, as at 2026-06-30, county budget report, confidence 4 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (4)
- contract sum: KSh 62,557,284 (FY 2025/26; “Contract sum”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12
- funding in fy: KSh 50,147,536 (FY 2025/26; “Total Funding in FY 2025/26”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12
- expenditure in fy: KSh 17,878,166 (FY 2025/26; “Expenditure (accrual basis) in FY 2025/26”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12
- paid cumulative: KSh 30,389,622 (FY 2025/26; “Cumulative project expenditure as of 30 June 2026”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12
- 60% complete (as stated). County: 60%.
Revamping South Sakwa (Olago)
Status from County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12 (county budget report). Latest evidence 2026-06-30. Sector code WECC&NR (water, environment). Delayed on the county's own dates; unchanged at 60% for three quarters.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 60% complete (as stated). County: 60%.
County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025, PDF p. 16, as at 2025-12-31, county budget report, confidence 4 of 5 - 60% complete (as stated). County: 60%.
County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026, PDF p. 13, as at 2026-03-31, county budget report, confidence 4 of 5 - 60% complete (as stated). County: 60% against an expected completion of 7 Sep 2025.
County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12, as at 2026-06-30, county budget report, confidence 4 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (3)
- contract sum: KSh 47,023,421 (FY 2025/26; “Contract sum”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12
- funding in fy: KSh 17,150,000 (FY 2025/26; “Total Funding in FY 2025/26”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12
- paid cumulative: KSh 17,146,272 (FY 2025/26; “Cumulative project expenditure as of 30 June 2026”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12
- 60% complete (as stated). County: 60%.
Provision of improved kienyeji chicks to South Gem groups
Status from County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12 (county budget report). Latest evidence 2026-06-30. Completion is as reported by the county; no independent check is recorded. An input supply, not a construction project; kept because the county lists it as a development project.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 100% complete (as stated). County: 100%.
County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025, PDF p. 16, as at 2025-12-31, county budget report, confidence 4 of 5 - 100% complete (as stated). County: 100%.
County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12, as at 2026-06-30, county budget report, confidence 4 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (3)
- contract sum: KSh 10,412,743 (FY 2025/26; “Contract sum”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12
- funding in fy: KSh 10,000,000 (FY 2025/26; “Total Funding in FY 2025/26”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12
- paid cumulative: KSh 8,436,415 (FY 2025/26; “Cumulative project expenditure as of 30 June 2026”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12
- 100% complete (as stated). County: 100%.
Phased of upgrading to Bitumen standard- Sega market ring road
Status from County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12 (county budget report). Latest evidence 2026-06-30. Completion is as reported by the county; no independent check is recorded. Phased project: 100% may refer to the phase funded in FY 2025/26.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 100% complete (as stated). County: 100%.
County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025, PDF p. 16, as at 2025-12-31, county budget report, confidence 4 of 5 - 100% complete (as stated). County: 100%.
County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026, PDF p. 13, as at 2026-03-31, county budget report, confidence 4 of 5 - 100% complete (as stated). County: 100%.
County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12, as at 2026-06-30, county budget report, confidence 4 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (3)
- contract sum: KSh 98,097,505 (FY 2025/26; “Contract sum”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12
- funding in fy: KSh 48,380,499 (FY 2025/26; “Total Funding in FY 2025/26”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12
- paid cumulative: KSh 45,355,577 (FY 2025/26; “Cumulative project expenditure as of 30 June 2026”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12
- 100% complete (as stated). County: 100%.
Completion of upgrading to bitumen standard of Usenge market ring Road (phased)
Status from County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12 (county budget report). Latest evidence 2026-06-30. Completion is as reported by the county; no independent check is recorded. Phased project: 100% may refer to the phase funded in FY 2025/26.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 100% complete (as stated). County: 100%.
County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12, as at 2026-06-30, county budget report, confidence 4 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (3)
- contract sum: KSh 99,214,278 (FY 2025/26; “Contract sum”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12
- funding in fy: KSh 56,234,818 (FY 2025/26; “Total Funding in FY 2025/26”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12
- paid cumulative: KSh 53,007,624 (FY 2025/26; “Cumulative project expenditure as of 30 June 2026”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12
- 100% complete (as stated). County: 100%.
Phased construction of Ukwala Sub County Hospital Annex
Status from County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12 (county budget report). Latest evidence 2026-06-30. Completion is as reported by the county; no independent check is recorded.
Reported beside audit-found, where sources differ
Reported by the county or the Controller of Budget
- 100% complete (as stated). County: 100% with KSh 17.2 million of a KSh 106.9 million contract spent.
County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12, as at 2026-06-30, county budget report, confidence 4 of 5
Found by the Auditor-General
No audit evidence recorded.
Where the sources differ
- 100% reported with 16% of the contract sum spent; likely the FY 2025/26 phase only.
Amounts as printed (3)
- contract sum: KSh 106,901,740 (FY 2025/26; “Contract sum”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12
- funding in fy: KSh 17,229,901 (FY 2025/26; “Total Funding in FY 2025/26”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12
- paid cumulative: KSh 17,229,901 (FY 2025/26; “Cumulative project expenditure as of 30 June 2026”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12
- 100% complete (as stated). County: 100% with KSh 17.2 million of a KSh 106.9 million contract spent.
Construction of out-patient unit, co-funding of Urenga hospital (KDSP II)
Status from County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12 (county budget report). Latest evidence 2026-06-30.
Reported beside audit-found, where sources differ
Reported by the county or the Controller of Budget
- 26% complete (as stated). County: 26% (donor-funded).
County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025, PDF p. 17, as at 2025-12-31, county budget report, confidence 4 of 5 - 55% complete (as stated). County: 55%.
County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026, PDF p. 13, as at 2026-03-31, county budget report, confidence 4 of 5 - 55% complete (as stated). County: 55%.
County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12, as at 2026-06-30, county budget report, confidence 4 of 5
Found by the Auditor-General
No audit evidence recorded.
Where the sources differ
- Q3 reports 55% with KSh 16.1 million spent; Q4 also 55% with KSh 34.6 million spent.
Amounts as printed (4)
- contract sum: KSh 84,319,813.21 (FY 2025/26; “Contract sum”) County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026, PDF p. 13
- funding in fy: KSh 67,000,000 (FY 2025/26; “Total Funding in FY 2025/26”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12
- paid cumulative: KSh 16,119,955.08 (FY 2025/26; “Cumulative project expenditure as of 31 Dec 2025”) County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025, PDF p. 17
- paid cumulative: KSh 34,606,055 (FY 2025/26; “Cumulative project expenditure as of 30 June 2026”) County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12
- 26% complete (as stated). County: 26% (donor-funded).
Opening, grading and gravelling of Sianga-Wambarra- Yao Kouma- Kongolo Road
Status from County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026, PDF p. 13 (county budget report). Latest evidence 2026-03-31. Completion is as reported by the county; no independent check is recorded.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 100% complete (as stated). County: 100%.
County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025, PDF p. 16, as at 2025-12-31, county budget report, confidence 4 of 5 - 100% complete (as stated). County: 100%.
County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026, PDF p. 13, as at 2026-03-31, county budget report, confidence 4 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (3)
- contract sum: KSh 6,448,517.98 (FY 2025/26; “Contract sum”) County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026, PDF p. 13
- funding in fy: KSh 6,500,550 (FY 2025/26; “Total Funding in FY 2025/26”) County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026, PDF p. 13
- paid cumulative: KSh 6,367,317.98 (FY 2025/26; “Cumulative project expenditure as of 31 March 2026”) County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026, PDF p. 13
- 100% complete (as stated). County: 100%.
Maintenance of Nyangera sports ground access road and Nyagera pitch levelling
Status from County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025, PDF p. 17 (county budget report). Latest evidence 2025-12-31. Completion is as reported by the county; no independent check is recorded.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 100% complete (as stated). County: 100%.
County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025, PDF p. 17, as at 2025-12-31, county budget report, confidence 4 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (3)
- contract sum: KSh 4,969,782.09 (FY 2025/26; “Contract sum”) County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025, PDF p. 17
- funding in fy: KSh 7,000,000 (FY 2025/26; “Total Funding in FY 2025/26”) County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025, PDF p. 17
- expenditure in fy: KSh 4,778,324.67 (FY 2025/26; “Expenditure (accrual basis) to 31 Dec 2025”) County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025, PDF p. 17
- 100% complete (as stated). County: 100%.
Maintenace [sic] of Julius Waliera - Sirand Malwa - Uyundi road - 2.5km
Status from County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025, PDF p. 17 (county budget report). Latest evidence 2025-12-31. Completion is as reported by the county; no independent check is recorded. The road name is printed as in the source (a place name).
Reported beside audit-found
Reported by the county or the Controller of Budget
- 100% complete (as stated). County: 100%.
County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025, PDF p. 17, as at 2025-12-31, county budget report, confidence 4 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (3)
- contract sum: KSh 4,746,930.79 (FY 2025/26; “Contract sum”) County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025, PDF p. 17
- funding in fy: KSh 4,700,000 (FY 2025/26; “Total Funding in FY 2025/26”) County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025, PDF p. 17
- expenditure in fy: KSh 4,700,000 (FY 2025/26; “Expenditure (accrual basis) to 31 Dec 2025”) County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025, PDF p. 17
- 100% complete (as stated). County: 100%.
Purchase, commissioning, delivery and installation of generator at Ukwala Hospital
Status from County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025, PDF p. 16 (county budget report). Latest evidence 2025-12-31. Completion is as reported by the county; no independent check is recorded.
Reported beside audit-found
Reported by the county or the Controller of Budget
- 100% complete (as stated). County: 100%.
County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025, PDF p. 16, as at 2025-12-31, county budget report, confidence 4 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (2)
- funding in fy: KSh 5,000,000 (FY 2025/26; “Total Funding in FY 2025/26”) County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025, PDF p. 16
- expenditure in fy: KSh 5,000,000 (FY 2025/26; “Expenditure (accrual basis) to 31 Dec 2025”) County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025, PDF p. 16
- 100% complete (as stated). County: 100%.
Proposed Construction of Rarieda Sub-County Headquarters in Aram
Status from County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026, PDF p. 14 (county budget report). Latest evidence 2026-03-31. Dropped from the Q4 report, which lists only one stalled project; no reason given.
Reported beside audit-found
Reported by the county or the Controller of Budget
- County stalled-projects list: "Land Issues".
County Government of Siaya, Budget Implementation Report for 1st Quarter Ending September 30th 2025, PDF p. 15, as at 2025-09-30, county budget report, confidence 4 of 5 - Still on the stalled list.
County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025, PDF p. 18, as at 2025-12-31, county budget report, confidence 4 of 5 - Still on the stalled list.
County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026, PDF p. 14, as at 2026-03-31, county budget report, confidence 4 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (2)
- estimated value: KSh 39,900,000 (FY 2025/26; “Estimated Value of the Project”) County Government of Siaya, Budget Implementation Report for 1st Quarter Ending September 30th 2025, PDF p. 15
- outstanding balance: KSh 42,383,851.99 (FY 2025/26; “Outstanding Balance as of 30 September 2025 (above the estimated value, as printed)”) County Government of Siaya, Budget Implementation Report for 1st Quarter Ending September 30th 2025, PDF p. 15
- County stalled-projects list: "Land Issues".
Purchase of Land for Construction of Rarieda Sub County Office
Status from County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026, PDF p. 14 (county budget report). Latest evidence 2026-03-31.
Reported beside audit-found
Reported by the county or the Controller of Budget
- County stalled-projects list: "Delayed Procurement Process".
County Government of Siaya, Budget Implementation Report for 1st Quarter Ending September 30th 2025, PDF p. 15, as at 2025-09-30, county budget report, confidence 4 of 5 - Still on the stalled list.
County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026, PDF p. 14, as at 2026-03-31, county budget report, confidence 4 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (2)
- estimated value: KSh 5,000,000 (FY 2025/26; “Estimated Value of the Project”) County Government of Siaya, Budget Implementation Report for 1st Quarter Ending September 30th 2025, PDF p. 15
- outstanding balance: KSh 5,000,000 (FY 2025/26; “Outstanding Balance as of 30 September 2025”) County Government of Siaya, Budget Implementation Report for 1st Quarter Ending September 30th 2025, PDF p. 15
- County stalled-projects list: "Delayed Procurement Process".
Completion of Nyamonye juakali
Status from County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12 (county budget report). Latest evidence 2026-06-30.
Reported beside audit-found, where sources differ
Reported by the county or the Controller of Budget
- County stalled-projects list: "inadequate funding".
County Governments Budget Implementation Review Report FY 2024/25, PDF p. 484, as at 2025-06-30, cob report county data, confidence 3 of 5 - 40% complete (as stated). County: 40% before stalling; "Stalled, review of contract awaiting termination".
County Government of Siaya, Budget Implementation Report for 1st Quarter Ending September 30th 2025, PDF p. 15, as at 2025-09-30, county budget report, confidence 4 of 5 - 40% complete (as stated). County: 40% before stalling.
County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026, PDF p. 14, as at 2026-03-31, county budget report, confidence 4 of 5 - County: the one stalled project at 30 June 2026, "currently under investigation".
County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026, PDF p. 12, as at 2026-06-30, county budget report, confidence 4 of 5
Found by the Auditor-General
No audit evidence recorded.
Where the sources differ
- Amount paid (KSh 3,720,000) is printed above the estimated value (KSh 1,878,186.20). CoB FY 2024/25 prints the completion before stalling as 35% (OCR), the county quarterly reports 40%.
Amounts as printed (3)
- estimated value: KSh 1,878,186.2 (FY 2025/26; “Estimated Value of the Project”) County Government of Siaya, Budget Implementation Report for 1st Quarter Ending September 30th 2025, PDF p. 15
- paid cumulative: KSh 3,720,000 (FY 2025/26; “Amount Paid on the stalled project (above the estimated value, as printed)”) County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025, PDF p. 18
- estimated value: KSh 1,878,186.2 (FY 2024/25; “Estimated Value of the Project”) County Governments Budget Implementation Review Report FY 2024/25, PDF p. 484
- County stalled-projects list: "inadequate funding".
Completion of an Early Childhood Development (ECD) center at Hawinga
Status from Report on Public Participation in the Siaya County Annual Development Plan (CADP) 2025-2026, PDF p. 6 (county participation report). Latest evidence 2024-09. Completion is as reported by the county; no independent check is recorded. Reported by the county in its participation report; no amount printed.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Success stories: West Alego saw "the completion of an Early Childhood Development (ECD) center at Hawinga that had been stalled for 10 years".
Report on Public Participation in the Siaya County Annual Development Plan (CADP) 2025-2026, PDF p. 6, as at 2024-09, county participation report, confidence 4 of 5
Found by the Auditor-General
No audit evidence recorded.
- Success stories: West Alego saw "the completion of an Early Childhood Development (ECD) center at Hawinga that had been stalled for 10 years".
Wagai Multi-Media Resource and Learning Centre
Status from Report on Public Participation in the Siaya County Annual Development Plan (CADP) 2025-2026, PDF p. 10 (county participation report). Latest evidence 2024-09. Described as stalled by forum participants, as recorded by the county; no amount printed.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Participants called for completion of stalled projects, "such as the Wagai Multi-Media Resource and Learning Centre".
Report on Public Participation in the Siaya County Annual Development Plan (CADP) 2025-2026, PDF p. 10, as at 2024-09, county participation report, confidence 3 of 5
Found by the Auditor-General
No audit evidence recorded.
- Participants called for completion of stalled projects, "such as the Wagai Multi-Media Resource and Learning Centre".
Muluwa Irrigation Scheme in Alego Usonga sub-county
Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 168 (county development plan). Latest evidence 2024-01-24. The CIDP says the irrigation expansion is on-going under a national project; the county components are plans. No implementation report was read.
Reported beside audit-found
Reported by the county or the Controller of Budget
- CIDP flagship project: expansion of 6,500 acres under rice is "On-going under Lower Nzoia Irrigation Project (LNIP)" (committed 5,478 M; required 403 M).
County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 168, as at 2024-01-24, county development plan, confidence 5 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (3)
- estimated cost: KSh million 5,881 (FY 2023/24-2027/28; “Sub-Total Muluwa Scheme (estimated cost, M)”) County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 168
- estimated cost: KSh million 5,478 (FY 2023/24-2027/28; “Committed (LNIP phase 1)”) County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 168
- estimated cost: KSh million 403 (FY 2023/24-2027/28; “Required”) County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 168
- CIDP flagship project: expansion of 6,500 acres under rice is "On-going under Lower Nzoia Irrigation Project (LNIP)" (committed 5,478 M; required 403 M).
Anyiko Irrigation Scheme in Ugenya sub-county
Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 169 (county development plan). Latest evidence 2024-01-24. The CIDP says the expansion is on-going under a national project; the county components are plans. No implementation report was read.
Reported beside audit-found
Reported by the county or the Controller of Budget
- CIDP flagship project: 2,000 acres under rice "On-going under Anyiko Scheme Expansion Project" (committed 478 M; required 137 M).
County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 169, as at 2024-01-24, county development plan, confidence 5 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (3)
- estimated cost: KSh million 615 (FY 2023/24-2027/28; “SUB-TOTAL ANYIKO SCHEME (estimated cost, M)”) County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 169
- estimated cost: KSh million 478 (FY 2023/24-2027/28; “Committed (on-going scheme expansion project)”) County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 169
- estimated cost: KSh million 137 (FY 2023/24-2027/28; “Required”) County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 169
- CIDP flagship project: 2,000 acres under rice "On-going under Anyiko Scheme Expansion Project" (committed 478 M; required 137 M).
Last mile connectivity on Ugunja-Sega-Ukwala
Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 170 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Listed in the CIDP 2023-2027 capital projects table.
County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 170, as at 2024-01-24, county development plan, confidence 5 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (1)
- estimated cost: KSh million 482 (FY 2023/24-2027/28; “Cost”) County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 170
- Listed in the CIDP 2023-2027 capital projects table.
Last mile connectivity on SIBOWASCO
Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 170 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Listed in the CIDP 2023-2027 capital projects table.
County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 170, as at 2024-01-24, county development plan, confidence 5 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (1)
- estimated cost: KSh million 50 (FY 2023/24-2027/28; “Cost”) County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 170
- Listed in the CIDP 2023-2027 capital projects table.
Augmentation of Yala intake
Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 170 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Listed in the CIDP 2023-2027 capital projects table.
County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 170, as at 2024-01-24, county development plan, confidence 5 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (1)
- estimated cost: KSh million 500 (FY 2023/24-2027/28; “Cost”) County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 170
- Listed in the CIDP 2023-2027 capital projects table.
Wichlum water project
Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 170 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Listed in the CIDP 2023-2027 capital projects table.
County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 170, as at 2024-01-24, county development plan, confidence 5 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (1)
- estimated cost: KSh million 50 (FY 2023/24-2027/28; “Cost”) County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 170
- Listed in the CIDP 2023-2027 capital projects table.
Development irrigation infrastructure
Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 170 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Listed in the CIDP 2023-2027 capital projects table.
County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 170, as at 2024-01-24, county development plan, confidence 5 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (1)
- estimated cost: KSh million 280 (FY 2023/24-2027/28; “Cost”) County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 170
- Listed in the CIDP 2023-2027 capital projects table.
Upgrading of airstrips
Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 171 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Listed in the CIDP 2023-2027 capital projects table.
County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 171, as at 2024-01-24, county development plan, confidence 5 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (1)
- estimated cost: KSh million 100 (FY 2023/24-2027/28; “Cost”) County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 171
- Listed in the CIDP 2023-2027 capital projects table.
Establishment of Asembo bay feeder port
Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 171 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Listed in the CIDP 2023-2027 capital projects table.
County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 171, as at 2024-01-24, county development plan, confidence 5 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (1)
- estimated cost: KSh million 30 (FY 2023/24-2027/28; “Cost”) County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 171
- Listed in the CIDP 2023-2027 capital projects table.
Construction of energy centres
Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 171 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Listed in the CIDP 2023-2027 capital projects table.
County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 171, as at 2024-01-24, county development plan, confidence 5 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (1)
- estimated cost: KSh million 30 (FY 2023/24-2027/28; “Cost”) County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 171
- Listed in the CIDP 2023-2027 capital projects table.
Construction of hospital complexes
Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 171 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Listed in the CIDP 2023-2027 capital projects table.
County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 171, as at 2024-01-24, county development plan, confidence 5 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (1)
- estimated cost: KSh million 122 (FY 2023/24-2027/28; “Cost”) County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 171
- Listed in the CIDP 2023-2027 capital projects table.
KEMRI -Siaya County Research and Biotech Complex
Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 171 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Listed in the CIDP 2023-2027 capital projects table.
County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 171, as at 2024-01-24, county development plan, confidence 5 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (1)
- estimated cost: KSh million 12,400 (FY 2023/24-2027/28; “Cost”) County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 171
- Listed in the CIDP 2023-2027 capital projects table.
Construction and equipping of MRI Centre
Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 171 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Listed in the CIDP 2023-2027 capital projects table.
County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 171, as at 2024-01-24, county development plan, confidence 5 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (1)
- estimated cost: KSh million 45 (FY 2023/24-2027/28; “Cost”) County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 171
- Listed in the CIDP 2023-2027 capital projects table.
Establishment of Industrial Park
Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 172 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Listed in the CIDP 2023-2027 capital projects table.
County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 172, as at 2024-01-24, county development plan, confidence 5 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (1)
- estimated cost: KSh million 200 (FY 2023/24-2027/28; “Cost”) County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 172
- Listed in the CIDP 2023-2027 capital projects table.
Development of Got Ramogi
Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 172 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Listed in the CIDP 2023-2027 capital projects table.
County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 172, as at 2024-01-24, county development plan, confidence 5 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (1)
- estimated cost: KSh million 152 (FY 2023/24-2027/28; “Cost”) County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 172
- Listed in the CIDP 2023-2027 capital projects table.
Construction of phase II Siaya Stadium
Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 172 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Listed in the CIDP 2023-2027 capital projects table.
County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 172, as at 2024-01-24, county development plan, confidence 5 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (1)
- estimated cost: KSh million 200 (FY 2023/24-2027/28; “Cost”) County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 172
- Listed in the CIDP 2023-2027 capital projects table.
Construction of Migwena talent Centre
Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 172 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Listed in the CIDP 2023-2027 capital projects table.
County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 172, as at 2024-01-24, county development plan, confidence 5 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (1)
- estimated cost: KSh million 539 (FY 2023/24-2027/28; “Cost”) County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 172
- Listed in the CIDP 2023-2027 capital projects table.
Construction of office complex
Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 172 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Listed in the CIDP 2023-2027 capital projects table.
County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 172, as at 2024-01-24, county development plan, confidence 5 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (1)
- estimated cost: KSh million 440 (FY 2023/24-2027/28; “Cost”) County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 172
- Listed in the CIDP 2023-2027 capital projects table.
Construction of state officer residence (Governor, Deputy Governor)
Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 172 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Listed in the CIDP 2023-2027 capital projects table (the residence is for the offices, no person is named).
County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 172, as at 2024-01-24, county development plan, confidence 5 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (1)
- estimated cost: KSh million 80 (FY 2023/24-2027/28; “Cost”) County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 172
- Listed in the CIDP 2023-2027 capital projects table (the residence is for the offices, no person is named).
Establishment of L.Kanyaboli Eco-city
Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 172 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Listed in the CIDP 2023-2027 capital projects table.
County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 172, as at 2024-01-24, county development plan, confidence 5 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (1)
- estimated cost: KSh million 500 (FY 2023/24-2027/28; “Cost”) County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 172
- Listed in the CIDP 2023-2027 capital projects table.
Construction of speaker's residence
Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 173 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Listed in the CIDP 2023-2027 capital projects table.
County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 173, as at 2024-01-24, county development plan, confidence 5 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (1)
- estimated cost: KSh million 35 (FY 2023/24-2027/28; “Cost”) County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 173
- Listed in the CIDP 2023-2027 capital projects table.
Construction of County Assembly's complex
Status from County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 173 (county development plan). Latest evidence 2024-01-24. Plan entry only; no budget, contract or implementation evidence found in the sources read.
Reported beside audit-found
Reported by the county or the Controller of Budget
- Listed in the CIDP 2023-2027 capital projects table.
County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 173, as at 2024-01-24, county development plan, confidence 5 of 5
Found by the Auditor-General
No audit evidence recorded.
Amounts as printed (1)
- estimated cost: KSh million 396 (FY 2023/24-2027/28; “Cost”) County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file), PDF p. 173
- Listed in the CIDP 2023-2027 capital projects table.
What is not in the register
- County Annual Development Plan 2025/26 (GOV-04 ADP) not obtained: only its public participation report was found. Its Annex 4 lists several hundred ward proposals (ranked wishes, not approved projects); they are not entered as projects.
- County budget implementation reports for FY 2024/25 (GOV-02 Q1 to Q4) and Q4 FY 2023/24 have no project annexes; only FY 2025/26 reports do.
- Controller of Budget Siaya tables for FY 2014/15 to 2017/18 and FY 2019/20 were not read for this register.
- Executive audit reports for FY 2016/17 to 2018/19 were not found (see data/siaya-audits.json gaps), so early stadium years rest on CoB county data only.
- No physical verification by Takwimu. Only one project (SIA-P-038) has an independent statement of completion.
- CIDP capital projects are programme lines; countywide lines (subsidies, routine maintenance, ECD, VTC and so on) are not entered.
- BIR rows "Preparation of Valuation Roll" (a study) and CoB FY 2022/23 rows for seeds, fertiliser, tractors and land acquisition (purchases) are not entered.
Documents: County Government of Siaya, County Integrated Development Plan 2023-2027 (final print file); County Government of Siaya, Budget Implementation Report for 1st Quarter Ending September 30th 2025; County Government of Siaya, Budget Implementation Report for 2nd Quarter Ending December 31st 2025; County Government of Siaya, Budget Implementation Report for 3rd Quarter Ending March 31st 2026; County Government of Siaya, Budget Implementation Report for 4th Quarter Ending June 30th 2026; Report on Public Participation in the Siaya County Annual Development Plan (CADP) 2025-2026; Annual County Governments Budget Implementation Review Report FY 2018/19; County Governments Budget Implementation Review Report FY 2020/21; County Governments Budget Implementation Review Report FY 2021/22; Annual County Governments Budget Implementation Review Report FY 2022/23; County Governments Budget Implementation Review Report FY 2023/24; County Governments Budget Implementation Review Report FY 2024/25; Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2021; Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2022; Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2023.; Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June, 2024; Report of the Auditor-General on County Executive of Siaya for the Year Ended 30 June 2025; Report of the Auditor-General on County Assembly of Siaya for the Year Ended 30 June 2023; Report of the Auditor-General on County Assembly of Siaya for the Year Ended 30 June, 2024. Every project is in the dataset catalogue and in siaya-projects.json (contractor fields withheld).